151 Ky. 835 | Ky. Ct. App. | 1913
Opinion op the Court by
Reversing.
Appellee, a manufacturer of brick, entered into the following written contract with tbe appellant Coal Company:
“West Point, Ky., Oct. 25th, 1909.
All concerned:
The Nelson Creek Coal Company agrees to sell to tbe West Point Brick and Lumber Company their entire wants in screened nut coal, and the West Point Brick and Lumber Company agrees to buy its entire supply of screened nut coal from tbe Nelson Creek >Ooal Company for tbe remainder of tbe brick making season, .say from this date to April 1st, 1910. Tbe price is to be eighty-five cents per ton, f. o. b. tbe mimes. It is agreed that when
Nelson Creek Coal Company,
By J. W. Bastón, Geni. Mgr
West Point Brick & Lumber Company,
By J. W. A. Meyers, .Sup’t.”
Appellee brought suit in the -court below to recover damages for an alleged breach of the above contract, it being alleged in the petition that appellant failed, when notified by appellee, to deliver it coal as therein agreed, both in March and April, 1910.
The answer -specifically denies the several breaches of the contract alleged and avers that the contract te-rminated April 1st, 1910.
When the case was called for trial, a jury was waived by the parties and the law and facts submitted to the court, which, after hearing the evidence, rendered judgment in appellee’s favor for $249.68 and the costs of the action. Appellant’s dissatisfaction with that judgment and the refusal of the court to grant it a new trial, led to this appeal.
The first alleged breach of the contract occurred in March, 1910. Early in the month- appellee duly notified appellant to send it two car loads of coal. The latter said it could net furnish the coal from its own mine as it had sold its entire output to the Illinois Central Bail-road Company, but -would order it sent from the Bevier mine at Cleaton. This was done sometime in March. For these two carloads of coal appellee was charged by and paid the Bevier mines, 85 cents per ton, the contract price it would have paid if the coal had been shipped from appellant’s mine; it, however, had to pay 70 cents per ton freight on the Bevier coal, which was 10 cents in excess of the freight it would have paid on the coal, if it had been shipped from appellant’s mine as contemplated by its contract with the latter. In ether words, the freight rate at that time on such coal from appellant’s mine to appellee’s place of business, was 60 cents per ton, but from the Bevier mine it was 70 cents per ton.
As under the contract between them appellant undertook to ship appellee -the coal delivered in March from
In other respects, however, we regard the judgment erroneous.
If, as. 'claimed by appellant, the contract did not require it to deliver the appellee any coal after April 1st, 1910, judgment should not have gone against it for the failure to deliver coal at the contract price, ordered and received by appellee in April. As neither fraud nor mistake in the execution of the contract is alleged, and appellant’s manager and appellee’s superintendent, by whom the contract was made, differ in their testimony' on this point, the former contending that it was agreed it should end April 1st and the latter at the end of the brick making season, we. must interpret the contract in the light of its. language, and, in our opinion, its meaning is that it was to terminate April 1st, 1910.
In interpreting a contract the real intention of the parties must be allowed to control, and if the contract is unambiguous, such intention must be gathered from its language. Trapp v. Conly, 89 S. W. 514; Bright v. Bacon & Sons, 131 Ky. 848; Lexington B. S. Ry. Co. v. Moore, 140 Ky. 514. By the language of the contract appellant was to furnish .appellee coal “for the remainder of the brick making season, say from this date, to April 1st, 1910.” The giving of April 1st as the date of the termination of the contract, was not a mere approximation of the time it .should end, but an absolute limit, beyond which it could not extend; so, in our opinion, the contract did not require appellant to furnish appellee any coal after that date, although the brick making season may not, in fact, then have ended.
It appears from the evidence that appellant at .appellee’s request, made after April 1st, ordered for it from the Bevier mine, four car loads of coal which were delivered between the middle and last of April, and that for this coal the Bevier Company charged, and appellee was compelled to pay, $1.10 per ton, and freight charges
Wherefore the judgment is reversed and cause remanded for the entering of such a judgment as wli-11 conform to the opinion.