93 P. 789 | Idaho | 1908
Lead Opinion
This is an appeal from the judgment and an order denying a motion for a new trial. The Nelson Bennett Company, a Washington corporation, in the month of March, 1903, entered into a contract with the Twin Falls Land & Water Company, a Utah corporation, whereby the former agreed to construct about thirty-eight miles of canal for the appellants in the counties of Lincoln and Cassia on the south side of the Snake river, and which is now commonly called the Twin Falls canal. After the work was completed, the Nelson Bennett Company filed a lien against the canal and all the property connected therewith belonging to the Twin Falls Company to secure its claim for the balance due in the sum of $185,705.62. About the same time liens were filed by subcontractors; one by Alexander Toponee and one by Ryberg & Carlson. The Nelson Bennett Company commenced an action to foreclose the lien, as did also Toponee, but it seems that Ryberg & Carlson have never prosecuted any action for the foreclosure of their lien — at least they never sought to do so in this action. At the time of the trial an order was made for the consolidation of the Nelson Bennett case and the Toponee case, and the action was thereafter prosecuted in the name of the two plaintiffs. The defendant and appellant answered, denying the material allegations of the complaint and also pleading special matters in defense. The case went to trial and resulted in a judgment in favor of plaintiffs for the sum of $162,211.26.
The questions presented on this appeal have involved the examination of a voluminous record and exhaustive briefs. In order to a proper understanding of' the questions that must
By sec. 20 of the act of the legislature of 1899, the person, company or association which secures the contract for the construction of a canal system and for the reclamation of arid lands under the Carey act is given a “prior lien on said water right and land upon which said water is used for all deferred payments for said water right.” This provision of the legislative act granting to the contractors or' construction company a lien is authorized by and is in harmony with section 1 of the sundry civil appropriation act of Congress of June 7, 1896 (6 Fed. Stat. Ann., p. 398, U. S. Comp. Stat. 1901, p. 1556), which authorizes the state to create a lien “for the actual cost and necessary expense of reclamation,” etc., under the Carey act.
By the provisions of the statute and the contract entered into thereunder, the appellant herein acquired the right to construct the system of canals and ditches covering this tract of land and the right to divert the necessary amount of water from the Snake river for the irrigation of such lands. It likewise acquired a right to charge and collect from each and every settler the sum of $25 per acre for a water right, and to have the same become an immediate and continuing lien upon the lands to be irrigated. It acquired a right of way for the ditches and canals, and also an additional strip of land not exceeding fifty feet in width along the main canal and thirty feet along the laterals as a right of way for working, inspection and improvement purposes, and the right to increase or enlarge the canal at any time it might see fit or proper to do so for the purpose of carrying any additional waters either for its own use or purposes or for that of rental and distribution, and the right to the use of any sur
The foregoing are some of the numerous rights and interests we find provided and stipulated for in the contract entered into between the appellant corporation and the state. As to the legal effect of these various stipulations and provisions and the extent of the rights, title and interest acquired by the appellant corporation under' them, we express no opinion, nor are we required in this ease to determine their extent or character beyond that of ascertaining whether they are sufficient on which to found or rest a mechanic’s lien. That the Twin Falls Land & Water Company had, and still has, an interest in this canal system and the lands thereunder and the waters appropriated for their irrigation and reclamation, and that under the statutes and decisions of this state such property rights are real estate, there can be no doubt. (Rev. Stat., see. 2825; Welch v. Garrett, 5 Ida. 639, 51 Pac. 405; Ada Co. etc. v. Farmers’ etc. Co., 5 Ida. 793, 57 Pac. 990; Hard v. Boise City Irrigation & Land Co., 9 Ida. 589, 76 Pac. 331, 65 L. R. A. 407.)
Under sec. 1 of the Mechanic’s Lien Law of this state (Sess. Laws, 1899, p. 147), “Every person performing labor upon or furnishing materials to be used in the construction, alteration or repair of any .... ditch, dyke, flume .... has a lien upon the same for the work or labor done or materials furnished,” etc. The statute further provides that
Many cases may be found where the courts have held that liens preferred against property where the party who employed the laborers or made the contract or purchased the material had only a right of possession or a leasehold interest, would extend to all the rights, interest and claim the employer nr purchaser had in or to the property. In Badger Lumber Co. v. Malone, 8 Kan. App. 692, 54 Pac. 692, the court of appeals of Kansas in discussing this question said: “We conclude the law to be that a mechanic’s lien affects whatever estate or interest in the land upon- which the building is erected is owned and possessed by the person who causes the erection of the building at the time when the contract is made for the material. And if the person contracting to have the building erected has any estate or interest in the land upon which it stands, the lien of the materialman who furnishes the material extends to the whole of that estate or interest, whatever it may be. The word ‘owner’ is not limited in its meaning to an ‘owner in fee,’ but includes also an owner of a leasehold or other estate. It therefore follows that the estate pos
Having determined that the plaintiffs were entitled to liens and were pursuing the proper remedy, we now pass to the consideration of the further questions that were raised and are presented here.
The defendant filed a special demurrer to the complaint on the grounds of ambiguity and uncertainty, and pointed out specifically numerous instances in which it claimed the complaint was too indefinite and uncertain to enable it to properly answer or go to trial. At the same time defendant filed a motion based on the grounds designated in the demurrer, and moved the court to require the plaintiff to furnish it with a bill of particulars. The demurrer and motion came on for hearing and the demurrer was overruled and the motion denied. The defendant thereafter answered. It now assigns the action of the court in overruling the demurrer and denying the motion as error. The chief ground relied upon by the appellant is that since the measurements of the amount of wort done and the estimates and classifications thereof were by the contract to be left to the appellant’s chief engineer, and in pursuance thereof the engineer had made the measurements, estimates and classifications and the respondent claimed that they were unfair, fraudulent and incorrect, and that in truth and in fact the classifications should be very different from those made, the court should have required the respondent to point out the particular place or places along the line of the works and the particular stations, sections or subdivisions where these errors and mistakes and fraudulent estimates had been committed, and the particulars on which it relied for a recovery so as to enable appellant to properly answer and to prepare its ease for trial. The respondent constructed about twenty-two miles of the main
“6. That plaintiff proceeded under said contract and employment, and in good faith completed and fulfilled said contract on its part; and did between the dates of March 9, 1908, and the 6th day of August, 1904, perform and furnish work, labor and material in the construction of said canal, ditch dams, adjuncts and irrigation system and works, as follows:
482.85 acres cleared at $10 per acre.$ 4,828.50
70,732 cubic yards solid rock at 90 cts. 63,658.80
455,569 cubic yards loose rock and hard-pan at 45 cts. per cubic yard. 205,006.05
1,632,568 cubic yards common material at 13 cts. per cubic yard . 212,233.84
499,172 cubic yards over-haul at 2 cts. per cubic yard, per 100 feet. 9,983.44
28,256 feet bridge timber at $42 per M.......... 1,186.75
336 acres bond-plowing at $3.00 per acre. 1,008.00
2 Pettelo cars furnished at $50 each. 100.00
184,551 cubic yards of embankment at 27 cts. per cubic yard. 49,828.77
9,789 yards of rip-rap at $1.25 per yard. 12,236.25
167 days pumping at $5.00 per day. 835.00
Amount to the sum of.$560,905.40
“9. That according to the terms of the contract between plaintiff and defendant canal company, the amount and classification of the work done under said contract, said plaintiff was to be governed by the rules, regulations and restrictions*20 and specifications of the engineers in charge of said work, which said engineers were in the employ of said defendant canal company. That the said defendant canal company and its said engineers fraudulently and arbitrarily and without having made actual or correct measurements and without having made proper inspection of the same, and without sufficient knowledge upon which to found an honest judgment in respect either to the proper measurements or the amount of cubic yards excavated or the classifications of the same as to earth, loose rock, solid rock, hard-pan, and of the other work done, and with intent to injure and defraud this plaintiff and to deprive it of the just amount of compensation due for said work and material as aforesaid, the said defendant canal company and its engineers arbitrarily and in violation of good faith and duty, did make or cause to be made false and untrue final estimates, so called, or calculations and certificates of the amount or kind of work done by the plaintiff. That said estimates and calculations and certificates of the kind of work done by said plaintiff, as made by the defendant canal company and its engineers, were false and untrue in this, to wit: That according to the estimates made by said defendant canal company and'its engineers, they allowed and furnished estimates to plaintiff for solid rock in the amount of 33,214 cubic yards, at the rate of ninety cents per cubic yard, when in truth and in fact there were 70,732 cubic yards of solid, rock, at the same price. That according to the estimates and classifications made by said defendant canal company and its engineers, they allowed for loose rock and hard-pan in the amount of 101,394.3 cubic yards, at the rate of forty-five cents per cubic yard, when in truth and in fact there were 455,569 cubic yards of loose rock and hard-pan, at the same price. That according to the estimates and classifications made by the said defendant canal company and its engineers and as furnished defendant canal company, they allowed for overhaul 249,585.5 cubic yards, at the rate of two cents per cubic yard, while in truth and in fact there were 499,172 cubic yards at the same price. That the said defendant canal company did knowingly, intentionally, and with an intent to*21 cheat and defraud plaintiff, order and direct in the performance of its said contract that it perform and plow 336 acres of bond-plowing, for which plaintiff was to receive, and should have been allowed and received, the sum of $3 per acre. That said defendant canal company neglected and refused to allow said plaintiff anything whatsoever for said bond-plowing, and have never made any allowance therefor. That the defendant canal company did take and appropriate and use for its own use and benefit in the construction of said canal two Pettelo grading cars of the value and price of $50 each, which cars were reasonably worth and were worth at said time the sum of $50 each, or $100. That said defendant canal company neglected and refused, and have always and still do neglect and refuse, to pay or allow plaintiff for said cars, although demand has been made for the payment of same. That the said defendant canal company, although ordering and directing that the plaintiff perform and furnish for its use and benefit in the puddling of its said dam while under construction 167 days pumping of water, at the sum of $5 per day; that said services performed by plaintiff for said canal company in pumping of said water were reasonably worth and were worth the sum of $5 per day, which said defendant canal company promised and agreed to pay, but that they have neglected and refused, and do still neglect and refuse, to pay said pumping as heretofore set forth, or any part thereof. That according to the estimates and specifications made by the said defendant canal company and its engineers, which were furnished to plaintiff, they allowed for 8,873 yards of rip-rap, at the rate of $1.25 a yard, when in truth and in fact there were 9,789 yards at the same price. That according to the estimates and specifications made by the said defendant canal company and its engineers, which were furnished to plaintiff, they allowed for 160,273 cubic yards for embankment and construction of its dam and canal, at the price of twenty-seven cents per cubic yard, when in truth and in fact there were 184,551 cubic yards, at the same price. That in respect to the above enumerated items and estimates; calculations and computations as made by said defendant*22 canal company and its engineers, they were false and nntrne and grossly incorrect, and were arbitrarily made for the purpose of cheating and defrauding and depriving this plaintiff of the amount justly due to it for work performed under and in pursuance of said contract.”
It will be seen from these allegations that the plaintiff in every instance gave the classification and number of cubic yards thereunder that had been allowed by the appellant’s engineer, and also gave the number of cubic yards and classifications it contended was correct and that it should have received. The controversy and difficulty is therefore reduced to this: "Was it necessary for the plaintiff, where it claimed 70,000 eubic yards of solid rock, when in fact the engineer’s estimate had only given it 33,000 cubic yards, to state in its pleading or bill of particulars the particular point or points, station or stations, along the line of work at which it should have received increased estimates or different classifications; or, for instance, where it had only received an estimate of 100 eubic yards when it should have had 125 cubic yards in any given distance of the canal. It should be borne in mind, too, that the appellant company had on file all the figures, estimates, classifications and records of its engineers showing the amount of excavation and work done along the entire length of this canal and the number of eubic yards removed for every 100 feet thereof. It is further worthy of note that there was no material difference between the appellant and respondent as to the total number of cubic yards of material handled in the construction of this canal with the exception of one piece of work known as the Dry creek dam. The principal controversy arose over the classifications given the respondent by the appellant’s engineer. For example, the appellant only allowed respondent for 101,394.3 cubic yards of loose rock and hard-pan, while the respondent claimed that it should have had an estimate of 455,569 cubic yards of loose rock and hard-pan. On the other hand, the engineer’s estimate of common material was much larger than respondent claims it was entitled to — this difference arising out of the fact that he had not given large enough estimates of the more expensive classi-
It is nest urged by appellant that the court erred in refusing to give effect to the “contract provision giving engineer of defendant right to decide upon disputed questions”; and further, that “the controversies have been decided by the chief engineer pursuant to the provisions of the contract.” The provision of the contract involved in these assignments; is as follows:
“ENGINEER as Umpire. — 1. To prevent all disputes and misunderstanding in relation to any of the stipulations contained in this agreement or their performance by either of said parties, the said engineer shall be and hereby is made umpire to decide all controversies arising or growing out of this contract, and his decision on any point or matter touching this agreement shall be final and conclusive between the parties. And it is further agreed between said parties that wherever the word ‘Engineer’ is used it shall be taken and construed to mean Chief Engineer employed by said second party.’'’ Respondent in the first place urges that there are two reasons why this provision of the contract was ineffectual. 1. That it is so general and sweeping that it amounts to an attempt by contract to oust the courts of jurisdiction, and in-support thereof cites Waite Eng. & Arch. Juris., sec. 406, p. 340; 2 Am. & Eng. Ency. of Law, 2d ed., 570; Louisville Ry. v. Donevan, 111 Ind. 179, 12 N. E. 153; Wood v. Chicago Ry. Co., 39 Fed. 152. See, also, Baltimore etc. Co. v. Scholes, 14 Ind. App. 524, 43 N. E. 156, 56 Am. St. Rep. 307, and note.
The second objection is that the contract under consideration reserved to the Land & Water Company the right to question the estimates of the engineer both as to “amount and character of the work,” etc. That provision of the contract is embodied in paragraph 3 thereof, and is as follows:
“True Estimates. — Said second party shall not be estopped by any estimate by its engineer from showing at any time the-true and correct amount and character of the work which shall have been done and materials which shall have been fur*25 nished by said first party or by any person under this agreement. ’ ’
In the first place, it would seem that the stipulation constituting the chief engineer as umpire could not, and perhaps would not, receive a construction by the courts that would give to the engineer “the determination of questions relating to the meaning and interpretation of the contract itself,” and would rather limit his determinations to estimates, classifications, character of work,” etc., provided by the contract to be done and performed. (Waite Eng. & Arch. Juris., sec. 408, p. 342.) It is clear to us, on the other hand, that a stipulation in a contract requiring the submission of any given questions or controversies to an engineer as umpire, in order to be binding upon one party must be made obligatory on the other, and in so far as it is made inoperative by the contract against one party, it will be held inoperative by the courts as against the other. If this point, however, were conceded in favor of appellant, there is another and equally serious reason why the courts will go back of the findings of the engineer in this case and that reason we will consider presently.
As will be seen from an examination of paragraph 9 of the complaint above quoted, the issue tendered was that the “canal company and its said engineers fraudulently and arbitrarily and without having made actual and correct measurements and without having made proper inspection of the same, and without sufficient knowledge upon which to found an honest judgment in respect either to the proper measurements or the amount of cubic yards excavated or the classifications of the same .... and with intent to injure and defraud this plaintiff and to deprive it of the just amount of compensation due .... its engineers arbitrarily and in violation of good faith and duty, did make or cause to be made false and untrue final estimates,” etc. In contracts for this character of work, stipulations for the submission of questions of difference and controversies to the decision of the chief engineer on the works have been generally sustained and enforced. (Waite Eng. & Arch. Juris., sec. 433; Chicago etc. R. R. Co. v. Price, 138 U. S. 185, 11 Sup. Ct. 290, 34 L.
Upon the issues made on this point the court found “That the said chief engineer wrongfully, arbitrarily, and without having made proper examination, inspections and tests, and without having made proper observations, and without sufficient knowledge upon which to found a just judgment in respect to the kind, quality and classification of materials, and in violation of good faith and duty, did make, cause to be made and permit untrue and grossly erroneous estimates and •classifications of the kind, character and amount of materials removed and placed, and work done, by said plaintiff. The •said chief engineer in arriving at his conclusion based his judgment almost entirely upon reports made to him by his •subordinates, and without any due or proper examination made by him to verify these reports. That the reports of the subordinates were grossly incorrect and untrue.” It is argued by appellant that this finding is not sufficient to justify or
Pursuing this contention, however, appellant contends that the facts before tbe court were not sufficient to justify these findings and warrant the court in going back of tbe estimates and classifications made by tbe engineer. As stated by appellant in its brief, “Tbe great controversy in tbe case, as to which the greater amount of testimony was given, was over that part of tbe specifications, Exhibit ‘A,5 which classified loose rock and hard-pan.” Tbe chief engineer bad allowed tbe Nelson Bennett Company for 101,394.3 cubic yards of '“loose rock and hard-pan” at forty-five cents per cubic yard, while tbe plaintiff contended that it was entitled to an allowance of 455.569 cubic yards of “loose rock and hard-pan,” at ■the price above stated. It seems to have been conceded by
Appellant also urges that the evidence was not sufficient to warrant a* finding and conclusion that the engineer acted either fraudulently, arbitrarily or dishonestly or without honest inquiry and investigation or without sufficient information to enable him to make honest and true estimates. The appellant’s chief engineer was a Mr. Biekel, under whose charge were a number of assistant engineers. It is conceded that the larger part of the Nelson Bennett contract was examined and superintended by an assistant engineer named Shobert. It is also apparent from the record that Biekel received practically all his information, reports, estimates and classifications from Shobert. Differences arose between the Nelson Bennett
The contract provided for any additional work, changes or alterations that might be ordered by the Land & Water Company or its chief engineer, and for the classification thereof and payment therefor.in the same manner and under the same rules and regulations as set out in the contract and specifications for the main work.' In the course of the construction of this canal, the company decided to have a dam built across what is called Dry creek, and which dam is referred to throughout the case as Dry creek dam. No special contract nor plans nor specifications were drawn for this piece of work. The dam was about one mile long at the top. A difference arose between the Nelson Bennett Company and the engineer over the measurements of this work. The engineer1 allowed 160,273 cubic yards as his measurement. The court, after hearing the evidence, allowed 184,551 cubic yards. Small differences and disputes arose over other pieces of work and extras and additional work; among those items was that of “rip-rapping” and “bond-plowing.” Without going into a consideration of the evidence on these items and charges, we are content to dispose of them by saying that there is sufficient evidence in the record to justify the findings and conclusion of the court on each of them.
Appellant assigns as error that the court made excessive allowances, and that the total allowances made by the court under the various classifications amounted to some 38,000 cubic yards more than was contained in the works and was actually moved. It seems that respondent originally proceeded on the theory that the measurements made by the
The sixth assignment of error is that so much of the mechanic’s lien law of this state as allows attorney’s fees to a
Numerous errors have been assigned against the ruling® of the court in the admission and rejection of evidence. The-particular objection to the ruling in each instance has not-been pointed out by brief, nor have they been separately considered therein. Upon an examination of them, however, we are satisfied that the rulings of the court have generally been-correct — in some instances perhaps erroneous; but it is clear-to us that the appellant has not been injured or prejudiced' thereby. This was an equity, ease and no question of fact, was submitted to a jury, .and in such cases the rule as to the admission of evidence is much more liberal, and the appellate court will hesitate to reverse a judgment on account of; an erroneous ruling in the admission of evidence unless it appears that the court was proceeding on a wrong theory of the-case, or that the admission or rejection of the evidence offered)
After the entry of judgment the plaintiffs filed a cost-bill in which they claimed costs to the amount of $2,488.60. The defendant Twin Falls Land & "Water Company made a motion to retax costs and supported the same by affidavit, and the two principal objections appear to have been: First, that mileage and per diem had been allowed to a number of subcontractors, who, while not parties to the action, were really interested in the outcome of the case, and were therefore such interested parties as were not entitled to per diem and mileage for attendance as witnesses; and, second, that mileage had been claimed for attendance of witnesses a distance of more than thirty miles. The court denied the motion, and the appellant assigns the same as error. The action of the court in denying the" motion was clearly within the purview of the law as announced by this court in Anderson v. Ferguson-Bach Sheep Company, 12 Ida. 418, 86 Pac. 41.
We are satisfied that there is no error in this record that has been called to our attention that would justify us in a reversal of the judgment herein. It is the order of this court that the judgment be modified and reduced in the sum of $1,423, and that as so modified and reduced it be and is hereby in all other respects affirmed. Each party will pay its own costs incurred on this appeal. The case is remanded, with direction that the judgment be modified as above indicated.
Rehearing
ON PETITION POR REHEARING.
A petition for a rehearing has been filed in this case, and upon an examination of it, the court was at first disposed to strike it from the files on account of the disrespectful and discourteous language in which it was couched. However, since it was filed, the resident attorney has with
Counsel for petitioner raises six questions in his petition, all of which have been considered in the former hearing of this ease, except one, and that is the first question suggested by the petition to the effect that the respondent, the Nelson Bennett Co., showed no legal right to recover in this action and that it affirmatively appears that it has no right to recover by reason of the fact that it had not complied with the requirements of the statutes of Idaho as to foreign corporations.
The trial court in its first finding of fact found that the Nelson Bennett Co. was an incorporation duly organized and existing under and by virtue of the laws of the state of Washington, and during all of the times mentioned in the complaint had carried on business as a contractor, in its corporate name, in Cassia county, state of Idaho, and at all of said times had accepted the provisions of the constitution and complied with the laws of the state of Idaho relative to nonresident corporations doing business within this state. In support of this contention, counsel calls our attention to folio 707 of the transcript, wherein it is made to appear, on the trial of the case, the respondent’s counsel offered in evidence a certificate executed by the Secretary of State, dated December 1, 1904, reciting the fact that the articles of the incorporation of the Nelson Bennett Co. were filed August 1st, 1904, and marked “Plaintiff’s Exhibit 11,” which was received in evidence. It also appears in the transcript that counsel for respondent offered in evidence a certified copy of the written designation of agent by the Nelson Bennett Co., from the county recorder of Cassia county, which certificate was marked “Plaintiff’s Exhibit 21” and received in evidence. Those exhibits with others introduced on the trial of the case were brought to this court by stipulation of counsel for inspection, and many of them not printed in the tran
Said exhibit 11 shows that a mistake was made in the transcript at folio 707, where it recites that the certificate of the Secretary of State shows that the articles of incorporation of the Nelson Bennett Co. were filed in the office of the Secretary of State on August 1, 1904, when, as a matter of fact, said certificate shows that said articles were filed August 1, 1903.
Another complete answer to this contention is that the court by its first finding of fact found that the Nelson Bennett Co. was a foreign corporation, “and at all said times had accepted of the constitution and complied with the laws of the state of Idaho relative to nonresident corporations doing business within this state.” That finding was not excepted to and there is no assignment of error in the record specifying in any manner that said finding is not supported by the evidence. Under the practice of this court, it will review no decision or ruling of the trial court unless the same is assigned as error. And under the rules of this court, the brief of appellant must contain a distinct enumeration of all errors relied upon by the appellant. The record contains no exception to said finding of the court, and appellant’s brief contains no suggestion that that finding of the court is not supported by the evidence. It is too late to assign that finding of fact as an error and present it for the first time on a petition for a rehearing.
Under the provisions of sec. 4183, Bev. Stat., if a defendant has no information and belief upon the subject sufficient to enable him to answer an allegation of the complaint, he may so state in the answer and place his denial on that ground, but this does not authorize a defendant to make a denial on information and belief when the truth of the fact alleged is a matter of public record and within his reach. This court has held in Simpson v. Remington, 6 Ida. 681, 59 Pac. 360, that a denial on information and belief is not permitted “where by a mere inspection of a public record the defendant may have obtained the knowledge as to whether an execution had been issued and returned.” This court again said, in Work Bros. v. Kinney, 7 Ida. 460, 63 Pac. 596, when considering such denials, that ‘ ‘ This is not good pleading, and such denials of matters of record within reach of the defendants, are insufficient.”
We shall consider the second and third contentions as one, as they refer to the same stipulation in the contract on which this action was brought.
“Said second party shall not be estopped by any estimate made by its engineer from showing at any time the true and correct amount and character of the work which shall have been done and materials which shall have been furnished by said first party, or by any person under this agreement. ’ ’
There the contract expressly provides that the second party shall not be bound by the estimates of its engineer of the amount and character of the work. We take it that that applies to all estimates of the several varieties of material required to be excavated and removed and classification of the same. So far as the umpire is concerned, his decision is made •binding upon the first party and not binding upon the second, and for that reason the courts of this state will not enforce such a one-sided provision.
Counsel cites in support of his contention the case of Mundy v. Louisville etc. R. R., 67 Fed. 635, 14 C. C. A. 583. That case involved a contract for the construction of a railroad, and contained a provision to the effect that in computing the.final estimate and giving his final certificate, the engineer should not be bound by any preceding estimates and •certificates, but that such preceding estimates and certificates should be held to be only approximate to the final estimate. That is a very different provision from the one.under consid
It is also contended that this court has expressly found that the lower court was authorized to go behind the stipulation of the contract as to the finality of the chief engineer’s decision, and thus sets aside the contract for constructive fraud of the chief engineer, and that the court lays down a new rule of law in that regard. Counsel seems to misapprehend, or does not desire to understand, the decision in that regard. In support of this contention, counsel quotes as follows from the opinion:
“The decision of the questions which arise and require the exercise of a judgment of a qwsi-judieial character cannot be delegated by the chief engineer or umpire to anyone. The parties in this ease have agreed to abide by the deliberate and fair judgment of the ‘chief engineer.’ In order for him to fairly, honestly and justly exercise that judgment, it was necessary for him to hear the facts and to take such steps as would enable him to come into possession of the facts in controversy or on which, his judgment and decision depended. Such was not done.”
Counsel says that he does not propose that the implications which arise therefrom shall go unchallenged. The quoted portion of the opinion fairly expresses the views of this court upon the point there under consideration. The record clearly shows that the chief engineer took the estimates and classifications from his subordinates. He knew that his subordinate, Shobert, was very much prejudiced against Mr. Bennett and threatened to “do him.” Mr. Bennett informed Mr. Bickel of this fact and requested him to place some other engineer who was not prejudiced against him in
In this connection it is contended in the third specification that this “court has abrogated the stipulation of the contract, making the decision of the engineer final, not because of any actual or positive fraud or dishonesty, bias or prejudice, but for mistakes of policy, or constructive fraud, thereby declaring a new rule of law, heretofore unheard of.” The court has done nothing of the kind, and no such construction can reasonably be drawn from the opinion. The trial court found as follows:
“That the said chief engineer wrongfully, arbitrarily and without having made proper examinations, inspections and tests, and without having made proper observations, and without sufficient knowledge upon which to found a just judgment in respect to the kind, quality and classification of materials, and in violation of good faith and duty, did make, cause to be made and permit untrue and grossly erroneous estimates and classifications' of the kind, character and amount of materials removed and placed, and work done, by said plaintiff. The said chief engineer, in arriving at his conclusions, based his judgment almost entirely upon reports made to him by his subordinates, and without any due or proper examination made by him to verify these reports. That the reports of the subordinates were grossly incorrect and untrue. ’ ’
If that finding of the trial court is not sufficiently strong to satisfy counsel that the court found the chief engineer ex
The contract considered in Mundy v. Louisville etc. R. R. Co., supra, expressly stipulated that the decision of the engineer should not be conclusive in case of “fraud or mistake.” But the court there held that the stipulation in the contract, to wit, that the engineer’s decision should not be conclusive in cases of fraud or mistake, did not vary the construction of the contract; that in such a contract, the exception therefrom of fraud or mistake would be implied if they were not expressed in the contract; that that exception in such contract is always implied whether it is written in the contract or not. We think that the correct rule. That the provision is not contained in the contract under consideration, but it is clearly implied therein, and the contract will be construed the same as though it were written in the contract.
The court has not desired to reflect on the integrity of any person, as insinuated by counsel for the petitioner, but is controlled solely by the facts as they appear in the records before us. Counsel, with some asperity, has deemed it wise to suggest in his petition for a rehearing that the standing of the engineers referred to, for fairness and honesty, will continue to be of the best, regardless of the decision of this court. So far as this decision is concerned, it is immaterial
It is next contended that the court misapprehended the proof in respect to certain items of work in the “hard-pan,” and for that reason failed to reduce the judgment as it ought to have been. "We have gone through the evidence and carefully considered the extensive quotations therefrom contained in the petition, and we are fully convinced that the conclusion reached by the court is correct and should be sustained. The controversy arises mostly from the classification of the hard-pan. While it is true the evidence shows that much of said hard-pan was plowed with a ten-inch plow and six horses, it is also true that the evidence shows that in plowing with six horses and a ten-inch plow, the plow was so set as to cut but six or eight inches in width, and, under the contract, all hard-pan or all earth that could not be successfully plowed with a ten-inch plow and six horses was to be classified as “loose rock,” and simply because many of the contractors did, as they testified, “wear the hard-pan out” with a ten-inch plow and six horses, the record does not show that they could successfully plow it with six horses and a ten-inch plow. There is nothing in this contention.
It is next contended that the court is mistaken as to the state of the proof as to the total quantity of material removed, and upon the. uncontested facts the judgment should be further reduced. It was alleged in the complaint that there had been placed 184,551 cubic yards of embankment in the Dry creek dam, and the answer admitted that there had been placed there 176,073 yards. It was contended that respondent should be paid for only 160,273 cubic yards thereof, that being “within the lines of the stakes and directions given by defendant’s engineer,” and it is averred that respondent was to put a two-foot excess on the sides and top of the dam without pay. It was admitted that there was more material actually placed on the Dry creek dam than was included in the
The next question raised by the petition is an allowance of $1,008 for “bond-plowing” on the main canal. There is nothing whatever in the contract or specifications requiring “bond-plowing.” In the specifications for the Dry creek dam, which were handed the respondent sometime after he had commenced work on his contract, was a specification for “bond-plowing” and it is as follows: “The surface will then be thoroughly plowed, first, in a direction parallel with the stream-bed, and the second time, parallel with the axis of the dam, throwing up ridges and making deep furrows between.” There is no requirement in the contract or specifications for “bond-plowing” anywhere on said canal, except as above set forth, and that applies only to the Dry creek dam.
It is contended that as respondent agreed to construct the banks of the canal in a good, workmanlike manner out of materials excavated out of the prism of the canal, making the embankment as near water-tight as possible of suitable fiia-terials to be judged by the engineer and in accordance with his instructions, respondent was required to do certain “bond-plowing,” and that in order to do said work in a workmanlike manner, “bond-plowing” must be done. It was held by the
We find no merit in the petition. A rehearing is denied.