Neff v. General Development Corp.Neff v. General Development Corp.
This is an appeal of a final judgment on the pleadings entered in favor of appellee/defendant, Drage Industries, in an action filed on April 28, 1977 by appellant/plaintiff, Albert K. Neff, d/b/a Neff Hardware, Inc.
17. The Defendant, DRAGE INDUSTRIES, was an electrical contractor that did electrical work on the south meter room in 1969 during the remodeling of the Port Charlotte Shopping Plaza, for the Defendant, GENERAL DEVELOPMENT CORPORATION.
18. That the Defendant, DRAGE INDUSTRIES, was negligent in failing to correct or report the defects in the south meter room described above when such defects should have been apparent to said Defendant, and in failing to use the proper wiring when modifying the system during the remodeling project.
19. That the negligence of the Defendant, DRAGE INDUSTRIES, was a direct cause of the above described fire and was a direct and proximate cause of the damages suffered by the Plaintiff.
In granting the motion on the pleadings the trial court found that the statute of limitations,
As this court stated in the recent case of Smith v. Continental Insurance Co., 326 So.2d 189 (Fla.App. 2d DCA 1976):
A statute of limitations starts running when there has been notice of invasion of the legal rights of the plaintiff, i.e., when he has been put on notice of his right of action. This long has been held to be the law in actions based on negligence.
Even though the alleged negligence occurred in 1969 it was not until the personalty was damaged that appellant was made aware of his right to bring this action and that his cause of action arose. The complaint was filed within the time period applicable to any action for injury to personal property under the applicable statute,
Accordingly, the judgment appealed is reversed, and the case is remanded for further proceedings consistent with this opinion.
REVERSED and REMANDED.
GRIMES and DANAHY, JJ., concur.