NEBRASKA PUBLIC POWER DISTRICT, Plaintiff-Appellant, v. UNITED STATES, Defendant-Appellee.
2007-5083
United States Court of Appeals for the Federal Circuit
January 12, 2010
Harold D. Lester, Jr., Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, of Washington, DC, argued for defendant-appellee. With him on the brief were Tony West, Assistant Attorney General, Jeanne E. Davidson, Director, Alan J. Lo Re, Assistant Director, and Andrew P. Averbach and Christopher J. Carney, Trial Attorneys. Of counsel was Jane K. Taylor, Attorney, United States Department of Energy, of Washington, DC.
Brad Fagg, Morgan, Lewis & Bockius LLP, of Washington, DC, for amici curiae Arizona Public Service Company, et al. With him on the brief were M. Stanford Blanton, Balch & Bingham LLP, of Birmingham, Alabama, for Southern Nuclear Operating Company, et al.; David A. Churchill, Jenner & Block LLP, of Washington, DC, for Consolidated Edison of New York, Inc.; Richard James Conway, Dickstein Shapiro LLP, of Washington, DC, for Boston Edison Company; Norman M. Hirsch, Jenner & Block, LLP, of Chicago, Illinois, for Energy Northwest; Richard W. Oehler, Perkins Coie LLP, of Seattle, Washington, for Wisconsin Electric Power Company; and Jerry Stouck and Robert Shapiro, Greenberg Traurig, LLP, of Washington, DC, for Yankee Atomic Energy Company, et al.
James Bradford Ramsay, National Association of Regulatory Utility Commissioners, of Washington, DC, for amicus curiae The National Association of Regulatory Utility Commissioners.
Appealed from: United States Court of Federal Claims
Judge Francis M. Allegra
DECIDED: January 12, 2010
Before MICHEL, Chief Judge, and NEWMAN, MAYER, LOURIE, RADER, SCHALL, BRYSON, GAJARSA, LINN, DYK, PROST, and MOORE, Circuit Judges.
Opinion for the court filed by Circuit Judge BRYSON, in which Chief Judge MICHEL and Circuit Judges NEWMAN, MAYER, LOURIE, RADER, SCHALL, LINN, DYK, PROST, and MOORE join. Concurring opinion filed by Circuit Judge DYK, in which Circuit Judge LINN joins. Dissenting opinion filed by Circuit Judge GAJARSA.
BRYSON, Circuit Judge.
This case requires us to address a difficult question involving the allocation of jurisdiction between regional circuit courts and the Court of Federal Claims. The dispute in this case centers on the interaction between a provision of the Nuclear Waste Policy Act (NWPA),
DOE did not begin accepting nuclear waste in 1998. Several years later, Nebraska Public Power District (NPPD), which had entered a nuclear waste disposal contract with DOE, filed a breach of contract action in the Court of Federal Claims. A central issue in the breach of contract action was whether prior decisions of the United States Court of Appeals for the District of Columbia Circuit interpreting DOE‘s obligations under the NWPA were binding on the parties in the action before the Court of Federal Claims. The Court of Federal Claims held that the D.C. Circuit‘s rulings were void because the D.C. Circuit lacked jurisdiction in the prior statutory review proceedings. Neb. Pub. Power Dist. v. United States, 73 Fed. Cl. 650 (2006). That issue is now before us on interlocutory review. We hold that the D.C. Circuit had jurisdiction to review DOE‘s compliance with the NWPA, and that the mandamus order issued by the D.C. Circuit in that proceeding is not void. We therefore reverse the order of the Court of Federal Claims and remand to that court for further proceedings.
I
A
Spent nuclear fuel and high-level radioactive waste are by-products of the operation of nuclear power plants. Because those substances remain dangerously
While Congress assigned DOE the task of constructing the permanent storage facility, it provided that the costs of disposal should be the responsibility of the generators and owners of such waste and spent fuel.
(5) Contracts entered into under this section shall provide that—
(A) following commencement of operation of a repository, the Secretary shall take title to the high-level radioactive waste or spent nuclear fuel involved as expeditiously as practicable upon the request of the generator or owner of such waste or spent fuel; and
(B) in return for the payment of fees established by this section, the Secretary, beginning not later than January 31, 1998, will dispose of the high-level radioactive waste or spent nuclear fuel involved as provided in this subchapter.
B
Pursuant to its statutory rulemaking authority, DOE promulgated a regulation in 1983 containing what it termed the Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste. 48 Fed. Reg. 16,590 (Apr. 18, 1983) (codified at
Under the mandatory nuclear waste contracts, the utilities began making payments to DOE, and they have continued to do so since that time. At present, the licensed nuclear power utilities make a total of $750 million in payments under the contracts each year. To date, however, DOE has not accepted any nuclear waste from any of the utilities.
By 1994, it had become clear that DOE was not going to have a permanent repository ready to accept nuclear waste by the statutory deadline of January 31, 1998. In recognition of that reality, DOE conducted a notice-and-comment proceeding to address the extent of DOE‘s obligations under the NWPA. At the outset of that proceeding, DOE announced its preliminary view that, although it may have created an expectation that it would begin accepting such spent nuclear fuel in 1998, it had no
After inviting and receiving comments on that issue of statutory construction, DOE issued what it termed its Final Interpretation of Nuclear Waste Acceptance Issues, 60 Fed. Reg. 21,793 (May 3, 1995) (Final Interpretation). In the Final Interpretation, DOE acknowledged that it would not be able to begin accepting nuclear waste by the January 31, 1998, deadline and in fact projected that the earliest possible date for acceptance of waste for disposal at a repository is 2010.
C
A number of utilities, states, and state agencies filed a petition in the D.C. Circuit for review of the Final Interpretation. Invoking
The D.C. Circuit reviewed the Final Interpretation to determine whether it constituted a permissible interpretation of the statute by DOE. After analyzing the statute and the Final Interpretation, the court concluded that DOE‘s interpretation was contrary to the statutory mandate, and the court therefore rejected DOE‘s interpretation. Ind. Mich. Power Co. v. Dep‘t of Energy, 88 F.3d 1272 (D.C. Cir. 1996).
The court interpreted section 302 of the NWPA as imposing on DOE an unconditional obligation to accept nuclear waste upon the payment of fees by the utilities. In particular, the court explained that nothing in the statute suggested that the obligation to accept nuclear waste was conditioned on the commencement of repository operations. Under the plain language of the statute, the court held, the utilities undertook to pay fees in return for [which] the Secretary had a commensurate duty to begin disposing of the spent nuclear fuel and high-level radioactive waste by a date certain. 88 F.3d at 1276. While acknowledging that Congress had expected that a permanent facility would be available by 1998, the court ruled that even though Congress anticipated that a facility would be available, that does not mean that Congress conditioned DOE‘s obligation to begin acceptance of [nuclear waste] on the availability of a facility. Id. at 1277. The court thus concluded that
Notwithstanding the court‘s ruling, DOE subsequently advised the utilities with which it had section 302 contracts that it would not begin accepting nuclear waste by
The court of appeals denied the utilities’ request for a writ of mandamus requiring DOE to begin accepting nuclear waste as of the statutory deadline. N. States Power Co. v. U.S. Dep‘t of Energy, 128 F.3d 754 (D.C. Cir. 1997). The court acknowledged that DOE‘s current approach toward contractual remedies is inconsistent with the NWPA and with the court‘s prior decision on the matter. Id. at 756. Nonetheless, the court held that ordering DOE to comply with its statutory obligations was unnecessary because the Standard Contract provides a potentially adequate remedy if DOE fails to fulfill its obligations by the deadline. Id. at 756. The court explained that the unconditional statutory duty to begin accepting nuclear waste as of January 31, 1998, left no room for DOE to argue that it does not have a clear duty to take the [nuclear waste] from the owners and generators by the deadline imposed by Congress. Id. at 758-59. Moreover, the court held that there was no reason to believe that the expenses the utilities incurred in dealing with the nuclear waste that DOE failed to remove would not be taken into account if the contractual processes operate as Congress intended. Id. at 759.
Although the court of appeals declined to order DOE to begin accepting nuclear waste as of 1998, it entered a more limited mandamus order. Holding that the NWPA
In particular, the court of appeals rejected DOE‘s argument that it was not obligated to accept nuclear waste because its failure to do so was unavoidable within the meaning of the Unavoidable Delays clause in Article IX of the Standard Contract. 128 F.3d at 757. The court held that DOE‘s contention that its delayed performance was excusable because it did not have a permanent repository, or congressional authority to provide storage in an interim facility, was simply recycling the arguments rejected by this court in Indiana Michigan. Id. at 759-60. The court therefore ordered DOE to proceed with contractual remedies in a manner consistent with NWPA‘s command that it undertake an unconditional obligation to begin disposal of the [nuclear waste] by January 31, 1998. Id. at 760.
DOE petitioned for rehearing, arguing that the court‘s mandamus order had improperly intruded upon the jurisdiction of the Court of Federal Claims with regard to claims arising under government contracts. In response to the rehearing petition, the court issued a supplemental opinion in which it clarified the scope of its order. N. States Power Co. v. Dep‘t of Energy, No. 97-1064, 1998 WL 276581 (D.C. Cir. May 5, 1998).
D
In its complaint in the Court of Federal Claims, NPPD sought damages for breach of contract on account of DOE‘s failure to accept nuclear waste as of January 31, 1998, and thereafter. The government proposed to defend in part on the ground that its failure to meet the 1998 deadline was excused under the Unavoidable Delays clause of the contract. NPPD sought to bar the government from asserting that defense on the ground that it conflicted with the D.C. Circuit‘s mandamus order. The government responded that the D.C. Circuit lacked jurisdiction to enter the mandamus order and that the order was therefore void.
The Court of Federal Claims agreed with the government and held that the D.C. Circuit lacked jurisdiction to issue the mandamus order based on the absence of an applicable waiver of sovereign immunity. The court therefore ruled that the order was void and had no effect on the litigation over the contract. The court then certified that order for interlocutory review by this court, and this court granted interlocutory review.
II
The issue in this case is whether the D.C. Circuit‘s decisions in Indiana Michigan and Northern States are entitled to res judicata effect in the proceedings before the Court of Federal Claims. Normally, a final judgment in one court is binding on the same parties in a subsequent action before another court as a matter of res judicata; in such a setting the first judgment ordinarily cannot be collaterally challenged in the second proceeding, even on the ground that the first tribunal lacked subject matter jurisdiction. See Christopher Village, L.P. v. United States, 360 F.3d 1319, 1329-30 (Fed. Cir. 2004). However, we have recognized an exception to that principle if the first court acted in derogation of principles of sovereign immunity and its judgment was void on that ground. Id. at 1333. The Court of Federal Claims ruled that the D.C. Circuit‘s mandamus order was void because it was not supported by a waiver of sovereign immunity.
The trial court based its decision on three grounds. First, the court held that
Second, the court held that there was no valid waiver of sovereign immunity for the review action undertaken and the mandamus order entered by the D.C. Circuit in
Third, and relatedly, the trial court held that the D.C. Circuit had improperly addressed contract interpretation issues that were within the exclusive jurisdiction of the Court of Federal Claims. The court viewed the dispute before the D.C. Circuit as entirely contained within the terms of the contract between DOE and the utilities. While acknowledging that the Standard Contract had to be construed in light of the NWPA, the court held that the effect of the NWPA on DOE‘s obligations under the contract was a contract interpretation issue that fell outside the jurisdiction of the D.C. Circuit.
A
In General Electric, the D.C. Circuit rejected the argument that section 119 applies only to actions arising from Part A of Subchapter I of the NWPA. 764 F.2d at 901-04. The court first noted that section 119 provides for review of matters such as the choice, characterization, approval of, and authorization for construction of disposal sites, and that
In addition, as the D.C. Circuit observed in General Electric, the evolution of the placement of section 302 in the [NWPA] strongly suggests that its physical separation from the judicial review provision in section 119 is pure happenstance and in no way indicates a congressional intent that review under the different subchapters be governed by different standards. 764 F.2d at 903. A close examination of the legislative history of the NWPA provides strong support for that conclusion.
The principal bill on which the NWPA was based, H.R. 3809 (1982), contained a judicial review provision similar to the enacted version of section 119. See H.R. Rep. No. 97-491, pt. I, at 14, 56-57 (1982) (section 119). That bill also contained a substantive provision corresponding to section 302 of the enacted statute. See
Even if the statute is regarded as ambiguous as to whether section 119 places review of matters arising from section 302 in a court of appeals, or leaves such matters to district courts under the default judicial review provision of
In the aftermath of the General Electric decision, other circuits likewise rejected the argument that section 119 applies only to matters arising under Part A of Subchapter I of the NWPA. See Ala. Power Co. v. U.S. Dep‘t of Energy, 307 F.3d 1300, 1312-13 (11th Cir. 2002); County of Esmeralda v. U.S. Dep‘t of Energy, 925 F.2d 1216,
More recently, in the PSEG case, this court agreed with General Electric and the other circuit decisions holding that the reviewing authority conferred by section 119 of the NWPA is not limited to matters arising under Part A of Subchapter I of the Act. See 465 F.3d at 1349 (We agree with . . . the D.C. Circuit that agency actions mandated under [Subchapter] III which relate to the creation of repositories for spent nuclear fuel fall within the class of actions subject to review by the courts of appeals under section 119.). The court further held that the January 31, 1998, deadline for beginning nuclear waste collection was clearly statutorily mandated by section 302 of the NWPA, and it recognized that judicial review under section 119 of the NWPA as to whether the DOE properly incorporated these obligations within its contracts may fall within the jurisdiction conferred to the courts of appeals in section 119. Id. at 1350.
The government makes the further argument that even if, as PSEG held, section 119 applies to at least some issues arising under section 302, section 119 review is limited to actions relating to the creation of nuclear waste repositories. Because the government characterizes this case as involving the date for accepting nuclear waste, but not the development of or date for opening a repository, the government argues that section 119 does not vest judicial review jurisdiction in the courts of appeals. The government notes that subparagraph (A) of
B
Apart from ruling that section 119 of the NWPA did not authorize court of appeals review of a claim arising under section 302, the trial court held that the D.C. Circuit lacked jurisdiction to review the Final Interpretation because there was no statutory
Section 10(a) of the APA is the source typically invoked for waiver of sovereign immunity in a case involving judicial review of administrative action by federal agencies or officials. It provides, in pertinent part, that an action seeking relief other than money damages and stating a claim challenging an action by an agency or officer of the United States “shall not be dismissed nor relief therein be denied on the ground that it is against the United States.”
We disagree with the trial court’s interpretation of section 10(c) of the APA. That statute provides, in pertinent part: “Agency action made reviewable by statute and final agency action for which there is no other adequate remedy in a court are subject to judicial review.”
Although the statutory language can be interpreted, with some effort, to apply the “adequate remedy” proviso to both statutory and nonstatutory review, the courts have not interpreted section 10(c) in that manner. In Abbott Laboratories v. Gardner, 387 U.S. 136 (1967), the Supreme Court characterized section 10(c) of the APA as providing “specifically not only for review of ‘[a]gency action made reviewable by statute’ but also for review of ‘final agency action for which there is no other adequate remedy in a court.’” Id. at 140; see also Bowen v. Massachusetts, 487 U.S. 879, 904 (1988) (quoting the pertinent language in Abbott Laboratories approvingly); id. at 926 & n.4 (Scalia, J., dissenting) (distinguishing between agency action specifically made reviewable by another statute and nonstatutory review in which review of final agency action is permitted under the APA if there is no “other adequate remedy”).4
This court and others have characterized section 10(c) in the same way. On several occasions, we have noted that the “no other adequate remedy in a court” formulation is associated with “nonstatutory review.” See Doe v. United States, 372 F.3d 1308, 1312 (Fed. Cir. 2004) (stating that in a “nonstatutory review action” there must be “no other adequate remedy in a court”); Brazos Elec. Power Coop., Inc. v. United States, 144 F.3d 784, 786 (Fed. Cir. 1998) (same); Nat‘l Ctr. for Mfg. Scis. v. United States, 114 F.3d 196, 200 (Fed. Cir. 1997) (same). Other circuits have uniformly characterized section 10(c) in the same fashion.5 We concur with those characterizations and accord section 10(c) its natural meaning, under which the “no
Consideration of Congress’s objectives in enacting section 10(a) shows why this construction makes sense. Congress was, of course, aware of the pre-existing statutes that provided for special review of particular agency action, including review in the courts of appeals for actions of agencies such as the Interstate Commerce Commission, the National Labor Relations Board, and the Federal Trade Commission. See Bowen, 487 U.S. at 903. It was to fill in the gaps in that patchwork of special review provisions that Congress created the right to general review of agency action in the district courts through section 10(a). Congress provided that the new default review created by section 10(a) would not be available if there were already an adequate remedy available in a court, because it “did not intend that general grant of jurisdiction to duplicate the previously established special statutory procedures relating to specific agencies.” Id. By the same token, however, Congress plainly did not intend section 10(a) to narrow the scope of the pre-existing special statutory review provisions, which would be the effect if the “no adequate remedy” requirement were deemed applicable to those provisions. Accordingly, we reject the rationale of the Court of Federal Claims to the extent that it relies on the “no other adequate remedy in a court” provision of section 10(c) to hold that the D.C. Circuit was foreclosed from conducting the review proceeding in this case.6
C
In addition to holding that Congress did not waive sovereign immunity for the D.C. Circuit’s review proceeding in Indiana Michigan, the Court of Federal Claims focused in particular on the mandamus order and held that the order “pretermits a key aspect of the contractual dispute before this court,” 73 Fed. Cl. at 662, and in so doing “plainly encroaches upon this court’s jurisdiction.” Id. at 663.
In assessing whether the D.C. Circuit’s mandamus order improperly invaded the jurisdiction of the Court of Federal Claims over the adjudication of contract rights, it is important to focus on precisely what agency action was challenged in the D.C. Circuit and what relief the D.C. Circuit granted. The issue before the D.C. Circuit in Indiana Michigan was whether section 302(a)(5)(B) of the NWPA imposed an unconditional obligation on DOE to accept nuclear waste by the statutory deadline. The agency action challenged in that case was DOE’s announcement in the Final Interpretation that it had no statutory obligation to accept nuclear waste by 1998 if DOE did not have an appropriate storage facility at that time. The D.C. Circuit rejected that argument as clearly contrary to the NWPA.
The issue before the D.C. Circuit in Northern States was what relief was appropriate in light of what the court characterized as DOE’s effort to circumvent the
The D.C. Circuit concluded that it was necessary to bar DOE from doing under the rubric of contract interpretation what section 302(a)(5)(B) prohibited as a matter of statutory compulsion. Beyond that, however, the court stated that the utilities would be required to seek relief for any asserted breach of contract in an action before the Court of Federal Claims. On rehearing, in response to DOE’s argument that the court had erroneously “designated itself as the proper forum for adjudication of disputes arising under the Standard Contract,” the D.C. Circuit stated, “[W]e did not; we merely prohibited the DOE from implementing an interpretation that would place it in violation of its duty under the NWPA to assume an unconditional obligation to begin disposal by January 31, 1998. The statutory duty . . . is independent of any rights under the contract.” N. States Power Co. v. Dep‘t of Energy, No. 97-1064, 1998 WL 276581, at *2 (D.C. Cir. May 5, 1998). The court added that its initial decision in Northern States described “the nature of the DOE’s obligation, which was created by the NWPA and undertaken by the DOE under the Standard Contract. It does not place the question of
A later opinion by the D.C. Circuit in a different case sheds further light on what that court regarded as the proper scope of its reviewing authority with respect to the NWPA and the Standard Contract. In Wisconsin Electric Power Co. v. United States Department of Energy, 211 F.3d 646 (D.C. Cir. 2000), a nuclear power producer petitioned for a writ of mandamus from the D.C. Circuit declaring that the Department of Energy must provide both monetary and non-monetary relief for having failed to begin disposing of the company’s nuclear waste by January 31, 1998. The court denied the petition. The court explained that it had held in Indiana Michigan that DOE had an unconditional statutory obligation to begin disposing of nuclear waste by January 31, 1998, but that DOE had “acted to frustrate that decision by holding that its failure to perform was ‘unavoidable’ and therefore, under the terms of the [Standard] Contract, did not render the Department liable for damages of any kind.” Id. at 647. For that reason, the court noted, it had issued a writ of mandamus “forbidding the DOE from claiming, in proceedings under its contracts, that its failure to perform was ‘unavoidable’ because a repository was not available.” Id. The court stated that it had “expressed no opinion about the relief the DOE would have to provide for breach of that obligation,” and that “[t]he Court of Federal Claims, not this court, is the proper forum for adjudicating contract disputes.” Id. at 648. Thus, in Wisconsin Electric, as in Northern States, the D.C. Circuit characterized its authority as limited to prohibiting the government from acting in derogation of its statutory obligations under the NWPA. The
The trial court in this case characterized the D.C. Circuit’s mandamus order as being at odds with the analysis in this court’s recent decision in PSEG Nuclear, L.L.C. v. United States, 465 F.3d 1343 (Fed. Cir. 2006), but we disagree. Like this case, PSEG was a case brought by a nuclear power producer alleging a breach of contract because of DOE’s failure to begin accepting nuclear waste as of January 31, 1998. In PSEG, however, the Court of Federal Claims held that it lacked jurisdiction over the plaintiff’s breach of contract claim because section 119 of the NWPA gave the courts of appeals exclusive jurisdiction over all actions relating to the contract term requiring performance by January 31, 1998. On appeal, this court rejected the Court of Federal Claims’ conclusion that section 119 divested it of jurisdiction over the underlying breach of contract action. We held that section 119 gave the regional courts of appeals jurisdiction to decide whether the Standard Contract complied with the requirements of section 302, but that it did not strip the Court of Federal Claims of its Tucker Act jurisdiction over the breach of contract suit. 465 F.3d at 1349-50.
In the course of its analysis, the PSEG court distinguished between “judicial review as to whether the DOE properly incorporated [its statutory] obligations within its contracts,” an issue that the court said could fall within the jurisdiction of the courts of appeals under sections 119 and 302 of the NWPA, and “the performance of and any damages for failure to meet those obligations.” 465 F.3d at 1350. The latter issues, the court held, “are not within the DOE’s statutory obligations under the NWPA,” but fall within the jurisdiction of the Court of Federal Claims. Id.
First, the PSEG court recognized that section 119 of the NWPA authorizes court of appeals review of DOE actions taken under section 302. Second, the court made clear that the breadth of the reviewing court’s mandate under that authority depends on whether the agency action in question “involve[s] the agency’s authority under that statutory mandate,” that is “whether the DOE properly incorporated [the statutory] obligations within its contracts.” PSEG, 465 F.3d at 1350. Finally, the court explained that answering that question does not involve the reviewing court in “issues of whether the DOE breached its contractual obligations, and if so, to what damages, if any, PSEG is entitled for the breach.” Id.
That is the same line the D.C. Circuit drew in the Indiana Michigan, Northern States, and Wisconsin Electric decisions, and we reaffirm that distinction here. It was within the authority of the D.C. Circuit to say what section 302(a)(5) of the NWPA means; and, except to the extent that the D.C. Circuit’s ruling on the statutory question controls as a matter of res judicata, it is within the authority of the Court of Federal Claims to interpret, apply, and enforce the provisions of the Standard Contract.
Section 302(a)(5)(B) of the NWPA directs that DOE’s contracts with nuclear power producers must provide that DOE will begin disposing of nuclear waste by January 31, 1998. As a matter of statutory construction, the D.C. Circuit interpreted DOE’s obligation to begin accepting nuclear waste in 1998 as unconditional. If DOE had omitted the clause required by section 302(a)(5)(B) from its contracts, it is clear that a court order directing the inclusion of that clause in its contracts would constitute a straightforward enforcement of DOE’s statutory responsibilities and would not intrude on the Tucker Act jurisdiction of the Court of Federal Claims. See PSEG, 465 F.3d at 1348.
What the D.C. Circuit did in the Indiana Michigan and Northern States cases is not meaningfully different. As the D.C. Circuit viewed the matter, DOE included a provision in the Standard Contract pertaining to its obligation to begin accepting nuclear
The government argues—with a passing endorsement from the trial court, 73 Fed. Cl. at 672 n.30—that the D.C. Circuit’s mandamus order fell outside the waiver of sovereign immunity in section 10(a) of the APA because it ran afoul of the proviso in that section barring review “if any other statute that grants consent to suit expressly or impliedly forbids the relief which is sought.”
Sharp and the other cases on which the government relies stand for the proposition that “[t]he sole remedy for an alleged breach of contract by the federal government is a claim for money damages, either in the United States Claims Court under the Tucker Act or, if damages of no more than $10,000 are sought, in the district court under the Little Tucker Act.” Sharp, 798 F.2d at 1523 (citations omitted). But the cases cited by the government involve actions for relief based on rights conferred by a
The D.C. Circuit subsequently explained that a case is not a “contract case” that is subject to the “impliedly forbids” limitation in section 10(a) simply because it involves contractual issues. Instead, the question whether the Tucker Act impliedly forbids a district court from acting in a case depends on “whether, despite the presence of a contract, plaintiffs’ claims are founded only on a contract, or whether they stem from a statute or the Constitution.” Transohio Sav. Bank v. Dir., Office of Thrift Supervision, 967 F.2d 598, 609 (D.C. Cir. 1992). The court drew the following lesson from Sharp: that under section 10(a) and the Tucker Act, “litigants may bring common-law contract claims only as actions for money damages in the Claims Court, but they may bring statutory and constitutional claims for specific relief in federal district court even when the claims depend on the existence and terms of a contract with the government.” Id. at 610; see also Roberts v. United States, 242 F.3d 1065, 1068-69 (Fed. Cir. 2001) (quoting with approval the standard articulated in Transohio); Katz v. Cisneros, 16 F.3d 1204, 1209 (Fed. Cir. 1994) (same).
In Indiana Michigan, unlike in Sharp, the utilities sought relief based on a statute. Even though it was clear that the D.C. Circuit’s remedial order would affect later litigation over contract-based rights, it remains the case that the D.C. Circuit was interpreting statutory rights, not rights under a contract. For that reason, the D.C. Circuit’s action was not impliedly forbidden by the Tucker Act.
The mandamus order was issued pursuant to the D.C. Circuit’s authority to construe the NWPA and to direct DOE to comply with its obligations under the statute. The order did not address any issue of contract breach, direct the implementation of any remedy, or construe any contract defense, except to the extent that the proposed interpretation of the contract would conflict with the statutory directive in section 302(a)(5). Those issues are all left to the Court of Federal Claims to decide in the contract breach action before it. We are satisfied that the D.C. Circuit’s order was confined to the issue of statutory interpretation and did not impermissibly invade the jurisdiction of the Court of Federal Claims to adjudicate the parties’ rights and remedies under the contract between them.
REVERSED and REMANDED.
United States Court of Appeals for the Federal Circuit
2007-5083
NEBRASKA PUBLIC POWER DISTRICT,
Plaintiff- Appellant,
v.
UNITED STATES,
Defendant-Appellee.
Appeal from the United States Court of Federal Claims in 01-CV-116, Judge Francis M. Allegra.
DYK, Circuit Judge, with whom LINN, Circuit Judge, joins, concurring.
While I join the majority, I write separately to address what I view as the dissent’s overreading of the majority opinion.
The court appears to be unanimous in agreeing that the District of Columbia Circuit had jurisdiction to interpret the statute, and that the D.C. Circuit did not (and could not) address purely remedial questions. I read the majority opinion here as holding that as a matter of res judicata, the D.C. Circuit’s statutory interpretation bars interpreting the Unavoidable Delays clause as creating a defense to liability. However, contrary to the dissent, I do not read either the D.C. Circuit or the majority here as ordering the government to pay money damages (expectancy damages) for breach of the agreement.1 Although I read the majority as establishing government liability, it
United States Court of Appeals for the Federal Circuit
2007-5083
NEBRASKA PUBLIC POWER DISTRICT,
Plaintiff-Appellant,
v.
UNITED STATES,
Defendant-Appellee.
Appeal from the United States Court of Federal Claims in 01-CV-116, Judge Francis M. Allegra.
GAJARSA, Circuit Judge, dissenting.
The issue before the court is a fundamental question of jurisdiction between this court and the D.C. Circuit. If the order in mandamus issued by the D.C. Circuit had interpreted the statutory requirements of the Nuclear Waste Policy Act (NWPA), then it would have been within that court’s jurisdiction. Instead, the D.C. Circuit actually forbids the United States from defending itself in a contract action in the Court of Federal Claims. In my judgment, the order in mandamus is clearly directed to the interpretation of the Standard Contract (not the NWPA) and is thus not only outside the jurisdiction of the D.C. Circuit, but also infringes upon the Court of Federal Claims’s exclusive Tucker Act jurisdiction over the administration of contract disputes, thereby impacting the sovereign immunity of the United States and undermining this court’s duty to review the contract decisions of the Court of Federal Claims. I must therefore dissent from the majority’s judgment.
I.
As an initial matter, I am compelled to highlight the procedural posture of this case. Nebraska Public Power District appeals an interlocutory decision of the Court of Federal Claims (the “trial court”), Nebraska Public Power District v. United States, 73 Fed. Cl. 650 (2006), that sustained the United States’ collateral attack on the D.C. Circuit’s decisions in Indiana Michigan Power Company v. Department of Energy (“Indiana Michigan Power”), 88 F.3d 1272 (D.C. Cir. 1996), and Northern States Power Company v Department of Energy (“Northern States I”), 128 F.3d 754 (D.C. Cir. 1997). The trial court certified its decision for immediate review by this court, and we accepted the appeal.
The appeal was argued before a panel of this court. Thereafter, a poll of the judges in regular active service was conducted to determine whether the appeal should be heard en banc. An en banc hearing was subsequently granted. The en banc court requested supplemental briefing relating to the interpretation and preclusive effects of the D.C. Circuit’s Northern States I decision and heard further argument.
At no time during this process has the trial court issued any decision on the merits of this case. Accordingly, this court’s review is limited solely to the trial court’s decision before us on interlocutory appeal. The question presented is simple: whether the D.C. Circuit’s order in mandamus in Northern States I precludes the Department of Energy (“DOE”) from relying on a clause of the Standard Contract—the Unavoidable Delays clause—in a breach of contract action brought by several nuclear power companies in the Court of Federal Claims. Importantly, it is not for this court to determine in the first instance whether the DOE should be estopped from relying on the
II.
Turning, then, to the limited question at hand, it is undisputed that traditional notions of res judicata and comity1 require that the valid judgments of other courts be given preclusive effect in the Court of Federal Claims. But it is similarly beyond dispute that only valid judgments are deserving of preclusive effect. See, e.g., Restatement (Second) of Judgments § 17 (1982). And to be valid, a judgment must be within the issuing court’s subject matter jurisdiction. See, e.g., Restatement (Second) of Judgments § 11 (1982) (“A judgment may properly be rendered against a party only if the court has authority to adjudicate the type of controversy involved in the action.”).
This does not mean, of course, that a judgment of questionable validity is always susceptible to collateral attack. See Ins. Corp. of Ir., Ltd. v. Compagnie des Bauxites de Guinee, 456 U.S. 694, 702 n.9 (1982); Christopher Village v. United States, 360 F.3d 1319, 1329-30 (Fed Cir. 2004). Rather, “[w]hen a court has rendered a judgment in a contested action, the judgment precludes the parties from litigating the question of the court’s subject matter jurisdiction in subsequent litigation except if: (1) [t]he subject matter of the action was so plainly beyond the court‘s jurisdiction that its entertaining the action was a manifest abuse of authority; or (2) [a]llowing the judgment to stand would
On several occasions, the Supreme Court has taken the opportunity to address the circumstances under which a collateral attack to an extra-jurisdictional judgment may be maintained. For example, in United States v. United States Fidelity & Guarantee Co., 309 U.S. 506, 507 (1940), the Court considered whether “a former judgment against the United States on a cross-claim, which was entered without statutory authority, fixing a balance of indebtedness to be collected as provided by law, [is] res judicata in [a subsequent] litigation for collection of the balance.” The Court decided that such a judgment was without res judicata effect, explaining: “It has heretofore been shown that the suability of the United States . . . depends on affirmative statutory authority. Consent alone gives jurisdiction to adjudge against a sovereign. Absent that consent, the attempted exercise of judicial power is void.” Id. at 514. See also Kalb v. Feuerstein, 308 U.S. 433, 438-39 (1940) (permitting collateral attack on judgment where Congress had limited the issuing court‘s jurisdiction); Durfee v. Duke, 375 U.S. 106, 114 (1963) (“To be sure, the general rule of finality of jurisdictional determinations is not without exceptions. Doctrines of federal pre-emption or sovereign immunity may in some contexts be controlling.“).
Relying on this precedent, this court has established a framework for determining when we will sustain a collateral attack. In Christopher Village v. United States, we considered whether a decision of the Fifth Circuit, holding that the Department of Housing and Urban Development (“HUD“) had violated its statutory and contractual duties, should be given res judicata effect by the Court of Federal Claims. 360 F.3d 1319, 1324-26 (Fed. Cir. 2004).
The majority here does not disagree that the Christopher Village framework should guide our decision in the present appeal. Instead, applying that framework, the majority somehow finds that the D.C. Circuit‘s writ of mandamus in Northern States I was within that court‘s jurisdiction. I cannot agree. In my judgment, the D.C. Circuit established a clear predicate to a damages action and exceeded its jurisdiction when it issued the writ of mandamus in Northern States I; that extra-jurisdictional act implicates issues of sovereign immunity by interfering with the exclusive jurisdiction of the Court of Federal Claims.
III.
The D.C. Circuit‘s jurisdiction is defined by the
[S]ection 302 of the
NWPA only required that the DOE include certain obligations in its contracts. Therefore, judicial review as to whether the DOE properly incorporated these obligations within its contracts may fall within the jurisdiction conferred to the courts of appeals in section 119. However, the performance of and any damages for failure to meet those obligations were not provided for by statute. The claims at issue here involve only issues of whether the DOE breached its contractual obligations, and if so, to what damages, if any, PSEG is entitled for the breach. Because these are not within the DOE‘s statutory obligations under theNWPA , City of Burbank [v. United States, 273 F.3d 1370 (Fed. Cir. 2001)] does not compel us to conclude that section 119 of theNWPA strips the Claims Court of its Tucker Act jurisdiction over PSEG‘s claim merely because the claim involves a statutorily mandated provision.
Id. at 1350. Similarly, in Wisconsin Electric Power v. Department of Energy, the D.C. Circuit decided that, although the
Beginning in the opening paragraph of the Northern States I decision, the D.C. Circuit condemns the “DOE‘s current approach toward contractual remedies” and “preclud[es] DOE from advancing any construction of the Standard Contract that would
Indeed, even the D.C. Circuit recognized that “breach by the DOE [of the Standard Contract] does not violate a statutory duty.” Northern States Power Co. v. Dep‘t of Energy, No. 97-1064, 1998 WL 276581, at *2 (D.C. Cir. May 5, 1998) (per curiam). But the D.C. Circuit‘s mandamus is directed precisely and explicitly to the
The text of the Unavoidable Delays clause demonstrates that the inquiries are separate. It states that “[n]either the Government nor the Purchaser shall be liable under this contract for damages caused by failure to perform its obligations hereunder, if such failure arises out of causes beyond the control and without the fault or negligence of the party failing to perform.”
The majority concedes that the D.C. Circuit interpreted the Unavoidable Delays clause.5 Maj. Op. at 33 (“[The mandamus order] did not . . . construe any contract defense except to the extent that the government‘s proposed interpretation of the contract would conflict with the statutory directive of section 302(a)(5).“) (emphasis added). Yet, inexplicably, the majority considers the D.C. Circuit‘s action “not meaningfully different” from the D.C. Circuit‘s statutory construction of the
The majority‘s attempt to maintain comity with the D.C. Circuit by distinguishing between liability qua breach and liability qua damages is, in my view, not intellectually defensible. First, it is unclear to me how this supposed distinction is functional in the context of the Unavoidable Delays clause, which is directed to “liab[ility] for damages.” And second, even if the clause was amenable to linguistic parsing of this sort, I fail to see how such a distinction would place the D.C. Circuit‘s Northern States I decision within that court‘s jurisdiction. Specifically, the question of breach is every bit as much within the exclusive jurisdiction of the Court of Federal Claims as is the question of
IV.
Because the majority holds simply that the D.C. Circuit‘s Northern States I decision did not exceed that court‘s jurisdiction, it does not need to reach the second prong of the Christopher Village analysis—whether the extra-jurisdictional act implicates the United States’ sovereign immunity. My disagreement over the issue of jurisdiction, however, requires me to continue the analysis. The D.C. Circuit‘s extra-jurisdictional writ interferes with the exclusive jurisdiction of the Court of Federal Claims, thereby implicating the United States’ sovereign immunity. As we explained in PSEG:
The
Tucker Act generally vests the Court of Federal Claims with jurisdiction to render judgment in government contract disputes. This jurisdiction is supplanted only if, in a specific jurisdictional statute, Congress grants exclusive jurisdiction over a contract dispute to another court. TheNWPA did not strip the Court of Federal Claims of its jurisdiction over [breach of contract] claims because it did not vest that jurisdiction in another court.
465 F.3d at 1349 (citations omitted). The
A person suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof. An action in a court of the United States seeking relief other than money damages . . . shall not be dismissed nor relief therein be denied on the ground that it is against
the United States . . . . The United States may be named as a defendant in any such action, and a judgment or decree may be entered against the United States . . . . Nothing herein . . . (2) confers authority to grant relief if any other statute that grants consent to suit expressly or impliedly forbids the relief which is sought.
See Consol. Edison Co. of New York, Inc. v. Dep‘t of Energy, 247 F.3d 1378, 1382-83 (Fed. Cir. 2001) (“Under specified circumstances, the
A.
In Bowen v. Massachusetts, the Supreme Court considered the first restriction on the
The D.C. Circuit‘s writ of mandamus in Northern States I presents a scenario that is the converse of Bowen. The D.C. Circuit did not offer specific relief; indeed, it acknowledged that it has no authority to do so. Rather, the D.C. Circuit ordered what is, in effect, compensatory relief. Specifically, the D.C. Circuit interpreted contractual terms by distinguishing between the treatment of avoidable and unavoidable delays under Article IX of the Standard Contract, Northern States I, 128 F.3d at 759 (explaining that avoidable delays result in money damages whereas unavoidable delays create no liability), and precluded the DOE from relying on the unavoidable delays provision, id. at 760. The D.C. Circuit exceeded its jurisdiction in doing so and by its writ thus obligated the DOE to pay compensatory damages in a subsequent breach of contract action. Therefore, even under Bowen‘s broad view of
Since Bowen, the Supreme Court has adopted a narrower and clearer position on the issue:
Almost invariably . . . suits seeking (whether by judgment, injunction, or declaration) to compel the defendant to pay a sum of money to the plaintiff are suits for ‘money damages,’ as that phrase has traditionally been applied, since they seek no more than compensation for loss resulting from the defendant‘s breach of legal duty.
Great-West Life & Annuity Ins. Co. v. Knudson, 534 U.S. 204, 210 (2002) (internal quotation marks and citation omitted). Certainly, the D.C. Circuit‘s writ is addressed to nothing more than compensation for loss resulting from the DOE‘s alleged breach of its
The precedents of this court require the same result. For example and as acknowledged by the majority, in Christopher Village we held that “[a] party may not circumvent the Claims Court‘s [now the Court of Federal Claims‘s] exclusive jurisdiction by framing a complaint in the district court as one seeking injunctive, declaratory or mandatory relief where the thrust of the suit is to obtain money from the United States.” 360 F.3d at 1328 (quoting Consolidated Edison Co. of New York, Inc. v. Dep‘t of Energy, 247 F.3d 1378, 1385 (Fed. Cir. 2001)). But the majority fails to recognize that the D.C. Circuit did exactly that in Northern States I—it circumvented the Court of Federal Claims‘s exclusive jurisdiction by crafting its order as a writ of mandamus that interprets the Standard Contract thereby removing the contractual shield of protection held by the United States. This is a subterfuge to provide the power companies with a means to obtain money damages from a now-defenseless United States in a later breach of contract action. This clearly is tantamount to a money mandate infringing upon our jurisdiction, the jurisdiction of the Court of Federal Claims, and the sovereign immunity of the United States.
B.
Moreover, as explained above, contract claims are within the exclusive jurisdiction of the Court of Federal Claims. See Roberts v. United States, 242 F.3d 1065, 1068 (Fed. Cir. 2001). Therefore, the
There is little room for debate that Nebraska Power‘s rights are contractual. But for the existence of the contract, there would be no right at all. Nor can it be contested that the relief sought in Northern States I was contractual—Nebraska Power requested a writ of mandamus ordering the United States to perform on its contract.6 Moreover, the relief granted by the D.C. Circuit was contractual—a writ of mandamus precluding the DOE from relying on a contract defense in a future breach-of-contract action. The action before the D.C. Circuit in this case neither presented an independent statutory claim, nor would a breach of contract by the DOE be contrary to statute. See N. States Power Co., 1998 WL 276581, at *2 (“While the statute requires the DOE to include an unconditional obligation in the Standard Contract, it does not itself require performance. Breach by the DOE does not violate a statutory duty . . . .“). The D.C. Circuit‘s writ is thus properly viewed as contractual relief, cf. Katz v. Cisneros, 16 F.3d 1204, 1209 (Fed. Cir. 1994) (distinguishing between “declaratory relief in the performance of a contract” and “judicial interpretation of a federal regulation“), and is impliedly forbidden by the
C.
Finally, the
--o0o--
Notwithstanding the protective fervor with which the majority persists in defending the jurisdiction of the D.C. Circuit by interstitially parsing liability and damages, I believe that the D.C. Circuit exceeded the limits of its jurisdiction under section 119 of the
