258 Pa. 558 | Pa. | 1917
Opinion by
This is an action of assumpsit on a joint and several bond given to secure payment of the price of certain paper-making machines to be constructed by the plaintiff company for the Marshall Machinery & Supply Com
The bond of October 8th was not satisfactory to the
The present action was brought on the bond of October 30th to recover the price of the small machine, No. 554, and of the large machine, No. 557. The plaintiff’s
It will be observed that the price named in -the plaintiff’s statement for each of the two machines exceeds that stated in the recital in the bond. It is claimed by the plaintiff company that it has the right to recover not only the original price stipulated in the bond, but also the price of “any special parts or changes” which were to be charged extra under the terms of the contract for the construction of the machines. It is further claimed by the plaintiff company that if the liability of the sureties is limited to the price of the machines named in the bond, they are not discharged, but to that extent there may be a recovery in this action. The affidavits of defense set forth the contention of the defendants.
The single question involved in this appeal, as stated by the appellant, is whether the sureties on the bond in suit are discharged from liability by reason of the changes made in the machines under the provision in the contract for their construction that extra parts and changes shall be charged extra. ( In other words, the question is whether the sureties "on the bond are dis-j
We are of the opinion that the only contractual obligation assumed by the sureties is that set out in the recital of the bond, which recital is binding not only on the defendants, but on the plaintiff: Noble v. Cope, 50 Pa. 17; Young v. American Bonding Co. of Balt., 228 Pa. 373. It appears by the evidence, and is conceded that Mrs. Marx, one of the sureties, was not informed as to the terms or provisions of the contract entered into by the principal parties for the construction of the machines. Her liability, therefore, depends upon the proper interpretation of the contract recited in the bond which she admittedly, with the other obligors, executed. The recital in the bond is not simply a reference to a contract executed by the principal parties, but purports to be a complete statement of its terms and provisions. The recital first states that the two companies have entered into a contract for the construction of seven “Marshall Paper-Making Machines.” If it had said no more, there would be some ground for the appellee’s contention that it referred to the contract entered into by those parties, and might have incorporated the contract in the bond. Such reference to that contract would have put the sureties on inquiry and charged them with notice of what it disclosed. The recital, howevei, goes on and states that the contract, just referred to, was entered into “upon the following terms and conditions,” and sets forth specifically and in detail the several provisions of the contract for the construction of the machines by the Nazareth Company. It contains the covenants of the contract to be performed by both parties. The price to be paid, as stated in the recital, is for a small engine $672, plus the cost of the material in the shaft, and for a large engine $964, We think the particularity with
If our conclusion is correct that the liability of the sureties must be determined by the contract recited in the bond, has there been any change in that contract which discharges them from liability for the price of the machines stipulated in their contract? The contract provides that the Nazareth Company shall construct for the Marshall Company seven “Marshall Paper-Making Machines.” For each of these machines, the Marshall Company was to pay the price stipulated in the contract, and it was secured by the bond in suit. As we understand from the evidence, and if there is any dispute as to the fact it is a question for the jury, the two machines, the price of which is sought to be recovered in
We think the learned court did not correctly interpret the letter of January 22, 1914, written by plaintiff to the defendant company. The plaintiff company, says the letter, declines “to accept further orders from you until your account is cleáned up or unless you pay us cash for the same before we start the work,” but does not refuse to complete the seven engines for which orders had already been accepted. The plaintiff’s testimony shows that the two engines in suit had been completed and delivered more than four months prior to the institution of the suit, and, the Marshall Company
We think the learned court below was also in error in holding that both contingencies named in the bond must occur to impose liability on the sureties, namely: failure to pay for each machine within three days after payment by the customer, and failure to pay within four months after shipment. The two conditions, the nonperformance of which by the Marshall Company made the sureties liable on the bond, were in the alternative, and the failure to comply with either imposed liability. This-clearly appears from the language of the bond. The conditions of the bond required the Marshall Company to pay within three days after the purchase-price had been received by it from the 'purchaser of an engine, or within four months from the date of shipment, “irrespective of the nonpayment for said machines to the Marshall Machinery & Supply Company.” The plaintiff, therefore, was not required to aver or prove that the Marshall Company had received payment for the engines and had not turned the money over to the Nazareth Company, and, hence, the allegation in the statement, sustained by the proof, was entirely sufficient which averred that the Marshall Company had refused and neglected to pay for the engines within four months from the date of shipments. '
What has been said sufficiently covers the single question which the appellant suggests is the point involved in the case, and, as we have repeatedly ruled, no other question will be considered. We are compelled to reverse the judgment and remand the record that the case may be tried in accordance with the views herein expressed.
The first and second assignments of error aré sustained, the judgment is reversed, and a venire facias de novo is awarded.