NATIONAL UTILITY SERVICE, INC. v. CAMBRIDGE-LEE INDUSTRIES, INC., Appellant.
No. 04-2952.
United States Court of Appeals, Third Circuit.
Sept. 25, 2006.
Outram also attempts now to collaterally attack his 1993 removal order, which was issued in absentia, arguing that it was fundamentally unfair. Initially, we note that Outram failed to raise this claim in his original appeal of his sentence and is foreclosed from doing so now. See United States v. Pultrone, 241 F.3d 306, 307-08 (3d Cir. 2001).
The challenge also fails on the merits. To prevail on a collateral attack on a deportation order under
Outram has not demonstrated that the entry of the order was fundamentally unfair. “[F]undamental fairness is a question of procedure.” Id. at 103 (quoting United States v. Lopez-Ortiz, 313 F.3d 225, 230 (5th Cir. 2002)). With respect tо removal proceedings, “due process requires that an alien who faces [removal] be provided (1) notice of the charges against him, (2) a hearing before an executive or administrative tribunal, and (3) a fair opportunity to be heard.” Id. at 104 (quoting Lopez-Ortiz, 313 F.3d at 230).
In the present case, Outram reсeived notice of the removal proceedings and an opportunity to be heard before an Immigration Judge. He failed, however, to appear at this hearing. This is not a denial of due process. Further, we note that Outram does not appear to contest the fаcts underlying the removal order.
Accordingly, we will affirm the Judgment of the District Court.
Submitted Pursuant to Third Circuit LAR 34.1(a) Sept. 11, 2006.
Filed: Sept. 25, 2006.
Anthony Argiropoulos, Fox Rothschild, Lawrenceville, NJ, Ronald L. Williams, Fox Rothschild, Exton, PA, for Appellant.
Before: SCIRICA, Chief Judge, SLOVITER and BARRY, Circuit Judges.
OPINION OF THE COURT
SCIRICA, Chief Judge.
Cambridge-Lee Industries, Inc., appeals the District Court‘s judgment in favor of National Utility Service, Inc., in a breach of contract action. We will affirm.
I.
On May 25, 1994, National Utility contracted with Cambridge-Lee to review Cambridge-Lee‘s monthly utility bills and recommend cost-saving changes to its services, with National Utility entitled to 50% of savings realized by Cambridge-Lee for 60 months through approval and implementation of any of those suggestions (after recapture of an initial service fee). The contract was for a three-year term, automatically renewable absent notice by Cambridge-Lеe. It also entitled National Utility to 50% of savings attributable to recommendations implemented after the contract‘s expiration, and required Cambridge-Lee to continue sending National Utility information and invoices covering outstanding recommendations at expiration.
In May 1995, Cambridgе-Lee stopped sending its monthly utility bills to National Utility. On June 9, 1995, National Utility made an initial report to Cambridge-Lee,
National Utility sued Cambridge-Lee for breach of contract on July 10, 2002. National Utility contended Cambridge-Lee breached by failing to submit monthly invoices for National Utility‘s review and analysis after National Utility made its initial recommendations. National Utility also contended it was entitled to 50% of savings Cambridge-Lee realized through implementation of the UniPLAN service for intra-and interstate telephone service. Finally, although National Utility had not made a recommendation that Cambridge-Lee implement AT&T‘s UniPLAN service for intraLATA (local) telephone service, it contended it would have done so before the end оf the contract term, had Cambridge-Lee not breached, and that it was also entitled to 50% of savings from implementation of the UniPLAN service for local calls.
A bench trial followed. At the end of National Utility‘s case-in-chief, Cambridge-Lee moved to dismiss National Utility‘s claims as time barred. The District Court denied the motion without prejudice (reserving judgment) and invited counsel for Cambridge-Lee to re-argue the issue at the conclusion of the case. Cambridge-Lee contended it had not breached, and, alternatively, contended the statute of limitations barred National Utility‘s сlaims.
After the bench trial, the District Court again rejected Cambridge-Lee‘s statute of limitations argument. On three separate and independent grounds—all of which Cambridge-Lee now contends were raised sua sponte—the District Court declared National Utility‘s claims were not time barred. First, thе District Court found Cambridge-Lee attempted to terminate the contract prematurely through its October 10, 1996 letter. Second, it found Cambridge-Lee‘s failure to submit billing records to National Utility was a “continuing breach” until August 25, 2003. Third, it found Cambridge-Lee‘s failure to remit National Utility‘s 50% share of savings resulting from implementаtion of AT&T‘s UniPLAN service a “continuing breach” until August 2003. All three breaches, the court found, occurred within the six-year statute of limitations.
The District Court attributed Cambridge-Lee‘s implementation of AT&T‘s UniPLAN service to National Utility‘s recommendation. It inferred that, had Cambridge-Lee complied with its obligations tо provide data, National Utility would have continued to recommend the UniPLAN service for long-distance calls until the expiration of the contract in May 1997. The court concluded the contract unambiguously provided for a 50% split of cost savings resulting from an implementation of a rеcommendation, for sixty months, whether or not the implementation occurred during the contract term or within a reasonable period of time thereafter. It found the (at most) one-year-and-three-month period between the contract‘s expiration and Uni-
The District Court had diversity jurisdiction under
II.
Cambridge-Lee presents two issues on appeal. First, error in failing to find the statute of limitatiоns barred National Utility‘s claims, and, second, error in finding Cambridge-Lee‘s contract with AT&T was an unlawful implementation of National Utility‘s recommendations.
As for the statute of limitations, the District Court found National Utility‘s claims were not barred under a continuing breach of contract theory. In New Jersey, the statute of limitations on breach of contract claims is six years from the date of accrual.
New Jersey courts have applied the “continuing breach” standard to allow claims when the initial breach of a contract occurred outside the statutory period, but successive breaches occurred within it. See Fauver, 153 N.J. at 108-09, 707 A.2d at 971-72 (citing cases). The standard is typically applied in installment contracts, so that “a new cause of action arises from the date each payment is missed.” Id. at 971. But it has also been applied where a party has continuously breached a non-payment performance obligation. See Ballantyne House Assocs. v. City of Newark, 269 N.J. Super. 322, 331-32, 635 A.2d 551, 555-56 (App. Div. 1993) (finding, when city of Newark failed to collect garbage under tax abatement agreement with limited dividend housing corporation, that its failure “could be considered a series of continuing
Cambridge-Lee also contends its initial failure to submit monthly invoices, in May 1995, constituted a repudiation of the contract. If true, National Utility‘s claims might be time barred, beсause repudiation could operate as a “single total breach.” Corbin, supra, § 956; see also Metromedia, 139 N.J. at 535, 655 A.2d at 1381 (noting that, in the case of continuing breach of an installment contract, “absent a repudiation, a plaintiff may sue for each breach only as it occurs, and the statute of limitations begins to run at that time“). But the District Court did not err in rejecting Cambridge-Lee‘s contention that a total breach occurred in May 1995, because Cambridge-Lee failed to establish that its actions constituted a repudiation at that time. Repudiation “entails a statement or ‘voluntary аffirmative act’ indicating that the promisor ‘will commit a breach’ when performance becomes due.” Franconia Assocs. v. United States, 536 U.S. 129, 143, 122 S.Ct. 1993, 153 L.Ed.2d 132 (2002) (quoting Restatement (Second) of Contracts § 250 (1981)). In a continuous or installment contract, the first instance of a continuing breach alone is not a “total breach” unless acсompanied by an anticipatory repudiation of performance due in the future. Corbin, supra, § 954. Accordingly, while Cambridge-Lee‘s continuing breach as to its obligation to submit information to National Utility might have begun in May 1995, there was no repudiation or total breach at that point, because there was no indication then that Cambridge-Lee would not fulfill its future obligations under the contract. In fact, after National Utility submitted its initial recommendations in June 1995, Cambridge-Lee told National Utility that same month that it would designate an employee to submit information to National Utility. Nationаl Utility continually requested the information thereafter.2
Cambridge-Lee also contends the District Court improperly raised the theory of continuing breach sua sponte in its ruling “without giving [Cambridge-Lee] the opportunity to offer a legal or factual defense,” violating Cambridge-Lee‘s right to prоcedural due process. The record belies this argument. Cambridge-Lee raised the affirmative statute of limitations defense in its answer and later moved to have National Utility‘s claims dismissed as time-barred. Once during National Utility‘s case-in-chief and again at its conclusion, the District Court informed counsel continuing breach would be an issue in any statute of limitations defense. Due process requires that parties be given a full and fair opportunity to litigate issues critical to their case. Luxliner P.L. Export Co. v. RDI/Luxliner, Inc., 13 F.3d 69, 72, 75 (3d Cir. 1993). Cambridge-Lee had
As for finding Cambridge-Lee‘s contract with AT&T was an unlawful implementation of National Utility‘s recommendations, the District Court did not err. Thе finding that National Utility would have continued to recommend UniPLAN until May 1997 if Cambridge-Lee had fulfilled its obligations was not clearly erroneous. As the District Court stated, the contract unambiguously provided that cost savings would be split between the parties, whether or not recommendations were implemented during or after the contract term. We need not decide whether there was a temporal limitation on this provision.3 A contract whose obligations are of indefinite duration should be interpreted to require performance for a reasonable period of time. Aboczky v. Stier, 126 N.J.L. 109, 111, 18 A.2d 262, 263 (N.J. 1941). The District Court did not err in finding the period between May 1997 and August 1998 reasonable.
III.
We will affirm the District Court‘s judgment.
Michael RICHARDS, Appellant v. Frank TENNIS, Superintendent, SCI Bellefonte; The District Attorney of the County of Philadelphia; The Attorney General of the State of Pennsylvania.
No. 05-2725.
United States Court of Appeals, Third Circuit.
Sept. 25, 2006.
Submitted Pursuant to Third Circuit LAR 34.1(a) Sept. 11, 2006.
Filed: Sept. 25, 2006.
