This matter comes before the Court upon Defendant Omar Negron‘s (“Negron“) Motion for Entry of Default Judgment (“Motion“) (Doc. No. 56) against Defendant Rebecca Bradshaw (“Bradshaw“) in relation to Negron‘s Crossclaim (“Crossclaim“) (Doc. No. 13) against Bradshaw. In his Crossclaim, Negron seeks indemnification and contribution from Defendant Bradshaw with respect to the damages sought by Plaintiff National Union Fire Insurance Company of Pittsburgh, Pa. (“Plaintiff” or “National Union“) against Negron in its Complaint (Doc. No. 1), as well as any costs associated with Negron‘s Crossclaim. (See generally Crossclaim at PageID #62-64.) Negron now seeks default judgment against Bradshaw in the amount of $4,956,267. (Motion at PageID #307.) Bradshaw has not responded to Negron‘s Motion. For the following reasons, Negron‘s Motion is GRANTED IN PART and DENIED IN PART.
I. Background
A. Procedural History1
Plaintiff filed the instant action on May 29, 2024 against Defendants Bradshaw, Negron, and Rosen. (Doc. No. 1.) Plaintiff sets forth five claims in its Complaint: Count 1, Fraud; Count 2, Conversion; Count 3, Breach of Fiduciary Duty; Count 4, Civil Conspiracy; and Count 5, Unjust Enrichment. (Id. at ¶¶ 27-45.) Plaintiff seeks judgment against the Defendants, jointly and severally on Counts 1 through 4 of the Complaint, for compensatory damages in the amount of $4,956,267, together with punitive damages, interest, costs, and all further relief that the Court determines to be appropriate. (Id. at PageID #5-8.)
On May 30, 2024, the Clerk of Court issued the original summons to Plaintiff‘s counsel for service upon the Defendants. (Doc. No. 3.) On July 17, 2024, Plaintiff filed proof of service demonstrating that Bradshaw was served with the summons and Complaint on June 27, 2024, by leaving the documents at her residence with Melvin Bradshaw, her husband and co-resident of suitable age and discretion. (Doc. No. 4.) Following the service on June 27, 2024, Bradshaw was required to file her Answer or otherwise respond to Plaintiff‘s Complaint no later than July 18, 2024.
On July 22, 2024, Plaintiff applied for an entry of default against Bradshaw.2 (Doc. No. 6.) The same day, the Clerk entered default against Bradshaw. (Doc. No. 7.) On August 22, 2024, this Court issued an Order to Show Cause ordering Plaintiff to file a Motion for Default Judgment against
On September 17, 2024, Plaintiff filed a Motion for Entry of Default Judgment against Bradshaw.4 (Doc. No. 17.) The Motion included an affidavit in which Affiant Heather L. Leibowitz, a product lead for National Union, averred that damages in the amount of $4,956,267 had been incurred. (Doc. No. 17-2.) On September 24, 2024, this Court issued an Order requiring Plaintiff to supplement its Motion with financial records or other supporting documentation substantiating this damages amount, and ordering Bradshaw to file her reply brief, if any, within 30 days of Plaintiff‘s supplemental filing.5 (See ECF 9/24/2024 Entry.)
On September 25, 2024, Plaintiff filed its Supplemental Brief in Support of its Motion (“Supplemental Brief“).6 (Doc. No. 19.) Plaintiff‘s Supplemental Brief included the notification of claim submitted by its insured client U.S. Cotton, LLC (“USC“) (Doc. No. 19-1), a forensic accounting report prepared by Grant Thornton LLP quantifying USC‘s loss (“Loss Report“) (Doc. No. 19-2), and the assignment and release of rights between Plaintiff, USC, and USC‘s parent company, Parkdale, Incorporated (“Parkdale“) (Doc. No. 19-3). On November 5, 2024, following the filing of Plaintiff‘s Supplemental Brief, the Court entered Default Judgment in favor of Plaintiff against Bradshaw in the amount of $4,956,267 as compensatory damages and an additional $405 as costs for the filing of Plaintiff‘s Complaint. (Doc. No. 27.)
On January 2, 2025, Negron filed an Application to Clerk for Entry of Default against Bradshaw. (Doc. No. 40.) On January 6, 2025, the Clerk entered default against Bradshaw as to Negron‘s Crossclaim. (Doc. No. 41.) That same day, a copy of that Default was mailed to Bradshaw. (See ECF 1/6/2025 Entry.)
On February 6, 2025, the Court issued another Order to Show Cause indicating that Default had been entered against Bradshaw as to Negron‘s Crossclaim, but that Negron had not filed a Motion for Default Judgment. (Doc. No. 50.) Therein, the Court ordered Negron to either file a motion for default judgment within thirty (30) days or show cause why his Crossclaim against Bradshaw should not be dismissed. (Id.) On March 7, 2025, Negron filed the instant Motion for Default Judgment against Bradshaw. (Doc. No. 56.) That same day, Negron sent a copy of the Motion to Bradshaw via U.S. mail. (Id. at PageID #309.) To date, Bradshaw has not filed a response to Negron‘s Motion.
B. Allegations in Complaint and Crossclaim7
Plaintiff‘s Complaint sets forth the following allegations. Plaintiff is an insurance company that issued a policy of insurance (the “Policy“) to Parkdale in which Plaintiff agreed to insure Parkdale and its subsidiaries for losses sustained due to employee dishonesty. (Doc. No. 1, Compl. ¶¶ 1, 23.) USC is a subsidiary of Parkdale. (Id. at ¶ 8.)
Bradshaw was employed by USC as a warehouse lead at USC‘s facility in Cleveland, Ohio until April 2021. (Id. at ¶ 9.) In her role, Bradshaw was responsible for ordering pallets for use in USC‘s warehouse and confirming that pallet deliveries received by USC were accurate. (Id. at ¶ 10.) Negron was employed by USC as a warehouse employee at the same facility until June 2020. (Id. at ¶ 11.) Plaintiff alleges that Negron was responsible for unloading pallet deliveries and confirming that pallet deliveries received by USC were accurate. (Id. at ¶ 12.)
Plaintiff alleges that from August 2014 through April 2021, Bradshaw, in her role as warehouse lead for USC, ordered hundreds of thousands of pallets from Rosen. (Id. at ¶ 13.) According to Plaintiff, the pallets that Bradshaw ordered were in excessive quantities and far more than USC needed. (Id. at ¶ 14.) Plaintiff alleges that Rosen delivered the pallets to USC‘s facility and provided fraudulent delivery tickets to Bradshaw and Negron at the time of delivery. (Id. at ¶ 15.) The fraudulent delivery tickets allegedly indicated that Rosen delivered far more pallets than he had actually delivered. (Id. at ¶ 15.) For example, the fraudulent delivery tickets would represent
Plaintiff contends that Bradshaw and Negron approved the fraudulent delivery tickets, thereby representing to USC that the number of pallets listed on the delivery ticket had been delivered. (Id. at ¶ 17.) Plaintiff asserts that based on Bradshaw and Negron‘s approvals, USC issued payments for pallets it never received. (Id. at ¶ 18.) Plaintiff submits that Rosen, upon receiving payment pursuant to the false delivery tickets, provided kickbacks to Bradshaw and Negron in the form of cash. (Id. at ¶ 19.)
Plaintiff asserts that on June 23, 2021, USC finally discovered the scheme after the Defendants had concealed it for several years. (Id. at ¶ 20.) Plaintiff contends that the Defendants’ conduct caused damages of no less than $4,956,267, and the Defendants have not returned any portion thereof of despite demand. (Id. at ¶¶ 21-22.) Pursuant to the Policy, Plaintiff indemnified Parkdale for the losses sustained. (Id. at ¶ 24.) As a result, Parkdale and USC assigned Plaintiff all the rights, claims, and causes of action that they had against the Defendants and others related to the Defendants’ scheme, and Plaintiff has become subrogated to Parkdale and USC in seeking judgment against the Defendants, jointly and severally on Counts 1 through 4, for damages incurred. (Id. at ¶¶ 25-26.)
Negron‘s Crossclaim against Bradshaw sets forth the following allegations. Negron denies all involvement in, and knowledge of, all alleged schemes and unlawful conduct asserted in Plaintiff‘s Complaint. (Crossclaim, Doc. No. 13 at PageID #62, ¶ 5.) Negron alleges that Bradshaw is the party liable for damages, if any, as set forth in Plaintiff‘s Complaint and sought by Plaintiff in its Complaint. (Id. at ¶ 6.)
Accordingly, Negron “requests judgment and an order of contribution ... and an order of indemnification against Defendant Bradshaw as to Defendant Negron,” and that “any liability for Defendant Bradshaw‘s purported wrongdoing must be indemnified by Defendant Bradshaw.” (Id. at ¶¶ 20-22.)
II. Standard of Review
Following the clerk‘s entry of default pursuant to
III. Analysis
A. Defendant Bradshaw‘s Liability
Upon review of the record in this case, the Court finds that default judgment is warranted. Bradshaw was duly served with proper summons and the Crossclaim but has failed to plead or otherwise defend. Bradshaw‘s failure to respond to the Crossclaim, entry of default, or Negron‘s Motion has made it clear that she has no intention of defending this action. Based on the allegations in the Crossclaim, which the Court accepts as true, see Zinganything, LLC v. Import Store, 158 F. Supp. 3d 668, 672 (N.D. Ohio 2016), and the averments in the Affidavit of Alexandra C. Eckrich, appended to Negron‘s Motion, the Court finds that Bradshaw is liable to Negron for indemnification and contribution as to any amounts sought and proven by Plaintiff as set out in the Complaint based on Bradshaw‘s conduct of approving fraudulent delivery tickets for pallets that were never delivered and receiving kickbacks in the form of cash. (See Doc. Nos. 1, 13, 17-2.)
Plaintiff filed the instant lawsuit based on the alleged fraudulent scheme conducted by the Defendants. (See generally Doc. No. 1, Compl.) In relevant part, Bradshaw ordered hundreds of thousands of pallets from Rosen in excess quantities of the amount USC needed. (Id. at ¶¶ 13-14.) Despite Rosen consistently delivering either partial truckloads or no pallets at all, Bradshaw repeatedly approved fraudulent delivery tickets representing that the full amount of pallets had been delivered. (Id. at ¶¶ 15-17.) Based on these fraudulent delivery tickets, USC was deceived into issuing payments to Rosen for pallets that it never received, and Rosen subsequently provided Bradshaw with cash kickbacks from those payments. (Id. at ¶¶ 18-19.)
Negron had no knowledge of any alleged schemes and/or alleged wrongful conduct at all times during the alleged wrongful conduct set forth in Plaintiff‘s Complaint. (Crossclaim, Doc. No. 13 at PageID #62, ¶ 11.) Rather, Negron was employed to unload trucks and was not responsible for ensuring the accuracy of what he unloaded—that was the job of Bradshaw. (Id. at ¶¶ 12-13.) Negron simply followed the orders of his direct supervisor, Bradshaw, who was the warehouse manager and lead at the Cleveland facility. (Id. at ¶¶ 8-9.) Accordingly, Bradshaw is responsible for the alleged conduct contained in Plaintiff‘s Complaint, and any liability against Negron for Bradshaw‘s purported wrongdoing must be indemnified by Bradshaw. (Id. at ¶¶ 22-23.)
B. Damages and Costs
With liability established, the Court must determine the extent of the damages. The Court finds that a determination as to the amount of damages is premature. In his Crossclaim, Negron seeks indemnification and contribution from Bradshaw as to any amounts sought and proven by Plaintiff as to Defendant Negron‘s liability. (Id.) However, Plaintiff has not yet proven any liability or damages against Negron. Because Bradshaw is only liable to Negron in the amount that Negron is liable to Plaintiff—which has not yet been determined—it is not appropriate to order an exact amount of damages for indemnification and contribution at this stage. See, e.g., Sinmier, LLC v. Everest Indemnity Ins. Co., 2021 WL 5961625, at *2 (N.D. Ohio Dec. 16, 2021) (granting default judgment on liability for indemnification but finding that damages “cannot be determined until this matter has substantially concluded“); BE&K Building Group, LLC v. Evergreen National Indemnity Co., Case No. 1:20-cv-00638, Doc. No. 53, at PageID #604 (N.D. Ohio Dec. 18, 2020) (granting default judgment on liability and ordering that “upon the resolution of the underlying dispute between [Plaintiff] and [Defendant/Third-Party Plaintiff] ... [Third-Party Plaintiff] may apply pursuant to
Accordingly, the Court declines to issue an order of indemnification or contribution in the amount of $4,956,267 at this time. Upon the resolution of the underlying dispute between Plaintiff and Negron, or upon further order of the Court, Negron may apply pursuant to
IV. Conclusion
Defendant Negron‘s Motion for Entry of Default Judgment against Bradshaw is GRANTED IN PART and DENIED IN PART. Default judgment is entered in Negron‘s favor against Bradshaw, and Bradshaw is liable to Negron for indemnification and contribution for any liability established by Plaintiff against Negron. Upon the resolution of the underlying dispute between Plaintiff and Negron, or upon further order of the Court, Negron may apply pursuant to
IT IS SO ORDERED.
s/Pamela A. Barker
PAMELA A. BARKER
U. S. DISTRICT JUDGE
Date: April 14, 2025