Lead Opinion
Thе government appeals the decision of the United States Court of Federal Claims
BACKGROUND
National Surety furnished performance and payment bonds in connection with a contract between Dugdale Construction Company and the Department of Veterans Affairs, for construction of a water distribution system at Fort Harrison, Montana. The construction contract provided that the gоvernment would retain ten percent of all progress payments until Dugdale submitted, and the contracting officer approved, a “complete project arrow diagram,” which is a detailed schedule of the critical path for performing the contract. The retainage provision was as follows:
Clause G-7(A). Payment to Contractor Clause 7 of the General Provisions (Contractor Contract) is supplemented to include the following:
Retainage: This contract shall have 10 percent retainage withheld on each progress voucher until the complete project arrow diagram has been approved. Once the schedule has been approved and the Contracting Officer has determined that the Contrаctor’s progress is satisfactory, the Contracting Officer may elect not to withhold any additional retainage. Previous retainage will not be reduced and future payments will be made in full. If during subsequent project updates the Contracting Officer determines that the Contractor’s progress is unsatisfactory, he may withhold 10 percent retainage on the current payment request and subsequent payments to protect the interests of the Government and until he again determines that the Contractor’s progress is satisfactory.
Dugdale did not provide the requisite project arrow diagram. Nonetheless, the government did not withhold the ten percent retain-
Dugdale abandoned the project before its completion, and the government then terminated the contract for default. National Surety completed the construction in accordance "with its performance bond, and was paid the difference between the contract price and the payments that had been made to Dugdale, ie., $126,333, less liquidated damages for late completion. National Surety then filed a claim for the funds that were required to have been retained by the government from the progress payments to Dugdale. The contracting officer did not act on the claim within the statutory period, and National Surety brought suit in the Court of Federal Claims.
On cross motions for summary judgment, the Court of Federal Claims held that National Surety was a third party beneficiary of the contract between Dugdale and the government and that the government breached this obligation when it improperly paid the retainage to Dugdale, thereby incurring liability to National Surety. The court awarded as damages the amount that should have been retained ($97,742) plus statutory interest. This appeal followed.
DISCUSSION
In the Court of Federal Claims the parties offered alternative theories of their legal relationships and ensuing liabilities. Although we affirm the court’s conclusion as to liability, we do so on application of suretyship principles.
A
The view that the surety is a third party beneficiary of the contract whose performance it assures is not the usual premise of surety claims against an obligee, although, to be sure, the surety’s obligations are affected by that performance. See Arthur Adelbert Stearns, The Law of Suretyship § 1.1 (1951) (“Suretyship may be defined as a contractual relation whereby one person engages to be answerable for the debt or default of another”); Balboa Ins. Co. v. United States,
Suretyship law derives from a different legal premise than whether the bonded contract, or any provision thereof, was made for the surety’s direct benefit. The surety bond embodies the principle that any material change in the bonded contract, that increases the surety’s risk or obligation without the surety’s consent, affects the surety relationship. The principles are set forth in, e.g., Gritz Harvestore, Inc. v. A.O. Smith Harvestore Prods., Inc.,
Where, without the surety’s consent, the principal and the creditor modify their contract otherwise than by extension of time fоr payment
(b) the compensated surety is
(i) discharged if the modification materially increases his risk, and
(ii) not discharged if the risk is not materially increased, but his obligation is reduced to the extent of loss due to the modification.
(citing Restatement, Security § 128 at 340-41 (1941)). These principles have been elaborated upon in the Third Restatement, including a synthesis of the circumstances under which the surety is entitled to relief against the obligee based on impairment of suretyship status. See Restatement (Third) of Suretyship & Guaranty § 37 (1996). Extensive precedent illustrates the discharge or pro tanto reduction of the surety’s obligation, varying in implementation based on the particular facts. The general rule with respect to retainage in construction contracts is the subject of the following example in the Third Restatement:
1. S has issued а performance bond with respect to P’s contract to construct a house for 0 for $100,000. Pursuant to the contract between O and P, O is to pay P monthly for the portion of the work completed that month minus a 15 percent “retainage.” After completing 60 percent of the project and receiving $51,000 ($60,000 minus the $9,000 retainage) from O, P defaults. S completes the project at a cost to S of $40,000. After S completes the*1545 project, 0 pays the $9,000 retainage to P, who, despite this payment, is insolvent. Had 0 paid the retainage to P before S completed the project, S would have been discharged to the extent of $9,000 by application of § 38 (impairment of collateral). S has a claim against O for $9,000 because the payment to P would have discharged S from the secondary obligation to that extent.
Id. § 37, illus. 1. See, e.g., Home Indem. Co. v. United States,
The surety’s rights and obligations are not based on third-party beneficiary concepts, but on principles of suretyship law. Applying these principles we conclude, as did the Court of Federal Claims, that the government has incurred liability to the surety. However, on the facts of this case we conclude that damages are fairly measured not by the calculated amount of the required retention, but by the injury, loss, or prejudice to the surety due to the government’s failure to imрlement the required retention.
B
National Surety argued at trial that, based on principles of suretyship and the doctrine of subrogation, it was entitled to the retainage security that was required to have been withheld from the contractor. We agree that this is the appropriate theory of liability. The Supreme Court explained the subrogation right in an early case concerning retainage in a construction contract with the government:
[The surety’s] right of subrogation, when it became capable of enforcement, was a right to resort to the securities and remedies which the creditor (the United States) was capable of asserting against its debtor, had the security not satisfied the obligation of the contractors; and one of such remedies was the right, based upon the original contract, to appropriate the 10 per cent, retained in its hands. If the United States had been compelled to complete the work, its right to forfeit the 10 per cent., and apply the accumulations in reduction of the damage sustained, remained. The right of [the surety] to subrogation, therefore, would clearly entitle him, when, as surety, he fulfilled the obligation of [the contractor] to the government, to be substituted to the rights which the United States might have asserted against the fund.
Prairie State Nat’l Bank v. United States,
The retainage provision in a bonded construction contract serves to protect the surety as well as the government, and is an interest of the surety that can not be disregarded or diminished by a party to the contract:
That a stipulation in a building contract for the retention, until the completion of the work, of a certain portion of the consideration, is as much for the indemnity of him who may be guarantor of the performance of the work, as for him for whom the work is to be performed, that it raises an equity in the surety in the fund to be created, and that a disregard of such stipulation by the voluntary act of the creditor operates to release the sureties, is amply sustained by authority.
Prairie State,
These two cases [Prairie State and Henning sen v. U.S. Fidelity & Guar. Co.,208 U.S. 404 ,28 S.Ct. 389 ,52 L.Ed. 547 (1908) ] therefore, together with other cases that have followed them, establish the surety’s right to subrogation in such a fund whether its bond be for performance or payment.
The Court of Claims, by whose precedent we are bound, has long recognized the surety’s right to subrogation in the security held by the government. E.g., Continental Cas. Co. v. United States,
[T]he surety’s rights of subrogation relate back to the date of the execution of the surety bonds, and the contractor can give no one a greater right in the retained percentages than that of the surety.
The duty devolves upon the government to administer the contract, during the course of its performance, in a way that does not materially increase the risk that was assumed by the surety when the contract was bonded. U.S. Fidelity & Guar. Co. v. United States,
During the performance of the contract, the Government has a duty to exercise its discretion responsibly and to consider the surety’s interest in conjunction with other problems encountered in the administration of the contract.
The ten percent retainage provision was in the contract between Dugdale and the government when National Surety set the price for and executed its surety bonds. The retainage requirement served as security for performance of the bonded contract, and this requirement contributed to the surety’s assessment of the risk involved. The surety was entitled to rely on the government’s obligation to retаin this percentage in accordance with the terms of the bonded contract, and on its right of subrogation to this security. National Surety’s right was fixed upon execution of the surety bonds, and was not dissolved or altered when the government failed to implement the retainage required by the contract. See Balboa Insurance,
The government argued at trial that the contract was “implicitly” modified by its release of the retainage, and that the surety was bound thereby. The Court of Federal Claims disсussed this theory, and found that the parties “did not even attempt to properly modify the contract.” Although the contract requires that modifications be made by written change order (clause 3(a)), that oral modifications are ineffective unless confirmed in writing (clause 3(b)), and that under no other circumstances would the contracting officer’s conduct be treated as modifying the contract (clause 3(c)), thé government presented no evidence, either to the Court of Federal Claims or to this court, of the requisite procedures. See Mil-Spec Contractors, Inc. v. United States,
As a general rule a surety will be discharged where the bonded contract is materially altered or changed without the surety’s knowledge or consent. In addition, where, as here, a compensated surety seeks exoneration, it must show that the alteration caused prejudice or damage. [Citations omitted.]
Trinity Universal Ins. Co. v. Gould,
*1547 It is of course almost axiomatic that any change or modification of the construction contract which materially increases a compensated surety’s risk discharges the obligation.
Surety bonds are integral to the government contracting process, for through the surety system the government enters into arrangements with reduced risk, by drawing on the responsibility and resources of the surety. Contract terms that provide security for the bonded performance can not be ignored, waived, or modified without consideration of the surety’s interests. Great American Ins. Co. v. United States,
C
The Court of Federal Claims rejected National Surety’s subrogation theory, based on the Federal Circuit’s statement in Fireman’s Fund Ins. Co. v. United States,
In Fireman’s Fund the surety was held to have been required to notify the government that it wished the retainage to be preserved or payments withheld, for absent such notice the government could, in its discretion, authorize such payment to be made in full without retention of a percentage.”
In contrast, Dugdale’s bonded contract gave no discretion to the government to depart from the requirement of the ten percent retainage until after the complete project arrow diagram was submitted and approved. That condition was never met.
We conclude that National Surety’s right of subrogation was not defeated by the government’s release of the retainage in contravention of the terms of the bonded contract. On this ground, we affirm the decision of the
D
The Court of Federal Claims awarded, as damages, the full amount of the contractually required retainage. We conclude that National Surety is not automatically entitled to this measure of damages, but that the surety’s recovery should be measured by its actual damages attributable to the release of the retainage.
Courts and commentators have recognized the difficulties in measuring such damages, and perhaps for this reason there are significant differences among the states and even within states in the extent to which changes in a bonded contract have been held to release the surety or, variously, provide a partial discharge. The trend, particularly for compensated commercial (as compared with personal) sureties, is in the direction of pro tanto discharge measured as set forth in the Restatement (Third) § 42 (Impairment of Collateral):
(1) If the underlying obligation is secured by a security interest in collateral and the obligee impairs the value of that interest, the secondary obligation is discharged to the extent that such impairment would otherwise increase the difference between the maximum amount recoverable by the secondary obligor pursuant to its subrogation rights (§§ 27-31) and the value of the secondary obligor’s interest in the collateral.
Several jurisdictions require that for pro tan-to dischаrge there must have been some injury, loss, or prejudice to the surety following impairment of the security. In Argonaut Ins. Co. v. Town of Cloverdale,
The Federal Circuit and its predecessor Court of Claims have recognized that subrogation is governed by equitable principles rather than by strict rules of law. See Balboa Insurance,
No costs.
AFFIRMED IN PART, VACATED IN PART, AND REMANDED.
Notes
. National Surety Corp. v. United States,
. The dissent argues that it was not necessary for the government to require the submission of the "complete project arrow diagram” (required by clause G-7(A) of the contract) because the contractor submitted and the government accepted a "progress curve” (independently required by clause G-8(A)). We are not told how meeting this lesser performance condition relieved the contractor of its obligation concerning the greater one, compliance with which was a condition to release of the retainage requirement.
Dissenting Opinion
dissenting.
Although I agree with the majority that National Surety cannot recover under a third-party beneficiary claim, I respéctfully
I
THIRD-PARTY BENEFICIARY STATUS
The majority affirms the judgment of the Court of Federal Claims on a different ground and implicitly rejects that court’s third-party beneficiary approach. I believe the rejection of this approach merits further discussion. Although decisions of this court have left the door open to a third-party beneficiary claim by a surety, see Fireman’s Fund Ins. Co. v. United States,
Under the law of contracts, there are two types of third-party beneficiaries to a contract, intended and incidental.
Third-party beneficiary status has been characterized as an “exceptional privilege.” Montana v. United States,
In this case, the Court of Federal Claims found support for its holding that National Surety was a third-party beneficiary in Prairie State Bank v. United States,
The law upon this subject seems to be, the reserved per cent to be withheld until the completion of the work to be done is as much for the indemnity of him who may be a guarantor of the performance of the contract as for him for whom it is to be performed.
Id. at 239,
Because the first sentence of the G-7(A) clause does not expressly state that protection of the government was the purpose of the retainage, National Surety argued, and the Court of Federal Claims found, that this demonstrated an intent by the parties to protect the interest of National Surety instead of the government. This analysis,
The Court of Federal Claims also indicated in its opinion that the government’s promise to withhold the retainage was inconsistent with the usual retainage clause where the government has discretion over the timing for release of the retained amounts. The court cited Fireman’s Fund Insurance Co. v. United States,
II
As recognized by the majority, “the traditional means of asserting a surety’s claim is under the equitable doctrine of subrogation.” Balboa,
In contrast, the discharge doctrine excuses, to the extent of the prejudice to the surety, the obligation of the surety to perform under the bond when there has been an impairment of the surety’s rights under the contract through, for example, modification of the bonded contract or impairment of collateral. See National Union Indem. Co. v. G.E. Bass and Co.,
A. Equitable Subrogation
Under equitable subrogation, a surety is entitled to a retainage held by the government because “[i]f the United States had been compelled to complete the work, its right to forfeit [the retainage], and apply the accumulations in reduction of the damage sustained, remained. The right of [the surety] to subrogation, therefore, would clearly entitle him, when, as surety, he fulfilled the obligation of [the contractor] to the government, to be substituted to the rights which the United States might have asserted against that fund.” Prairie State,
Because the surety stands in the place of the government, however, its recovery under equitable subrogation is limited to funds presently in the possession of the government. See Balboa,
A surety may be able to recover funds already paid if the disbursement was improperly made, but only after notice to the government. See, e.g., Home Indem. Co. v. United States,
Only when the surety may be called upon to perform, that is, only when it may become a party to the bonded contract, should the government owe it any duty. The surety knows best when this may occur; consequently, only notice by the surety triggers the government’s equitable duty.
The majority offers no reason why notice is not required and instead attempts to limit Fireman’s Fund to its facts by, again, confusing equitable subrogation with discharge. According to the majority, this case differs from Fireman’s Fund because the government “never met”
“Apart from the pro tanto discharge rule — which, again, we find no occasion to peruse today — the government as obligee owes no equitable duty to a surety like Fireman’s Fund unless the surety notifies that the principal has defaulted on the bond. ... [Njotice by the surety is essential before any governmental duty exists.”
Fireman’s Fund,
It is undisputed both that no funds remained in the government’s possession and that National Surety failed to provide the government with notice of Dugdale’s default. Thus, National Surety cannot recover under a claim of equitable subrogation.
B. Discharge
The facts in this ease seem to fit more appropriately a claim for pro tanto discharge. Under the rule of pro tanto discharge,
The first problem with affording National Surety recovery under a pro tanto discharge claim, however, is that it never made this claim in the Court of Federal Claims. Although a court may affirm a judgment “on any ground which the law and the record permit that would not expand the relief [the prevailing party] has been granted,” United States v. New York Tel. Co.,
Moreover, the record does not support such a claim. To begin, I disagree with the majority’s characterization of the facts in this case. The majority states that, although Dugdale did not furnish a project arrow diagram, “Nonetheless, the government did not withhold the ten percent retainage from the progress payments, as the contract required.” The contracting officer, however, received a progress curve as required by clause G-8(A) prior to release of the funds. In so doing, the requirement of clause G-7(A) of the contract for submitting a project arrow diagram was not enforced.
It is not improper, however, for the government to fail to enforce a provision in a contract which is for its own benefit and to accept lesser performance. See Restatement (Second) of Contracts § 84 (1981); see, e.g., Gresham & Co. v. United States,
In this case, clause G-7(A) sets forth a prescribed procedure for the release of the retainage requirement. The action of the contracting officer in not insisting on this precise procedural requirement but instead accepting one that was less onerous to the contractor does not mean that the contract was brеached. Instead, the contracting officer’s release of the retainage after acceptance of the progress curve effected a waiver of the G-7(A) requirement.
Admittedly, under suretyship law, a surety can recover under the pro tanto discharge
The record, however, does not reveal the extent of the prejudice, if any, to National Surety or whether the government’s waiver is material. Any possible prejudice is likely de minimis because nothing in the record demonstrates that the substitution of the progress curve for the project arrow diagram significantly increased the surety’s risk. The evidence also fails to demonstrate that the differences between these diagrams are substantial enough to rise to the level of a material alteration. See Ramada Dev. Co. v. United States Fidelity & Guaranty Co., 626 F.2d 517, 521 (6th Cir.1980) (“Mere immaterial or technical departures from the contract, not resulting in any damage to the surety, will not release the surety.”); Argonaut Ins. Co. v. Town of Cloverdale,
Additionally, there is no evidence in the record to suggest that the funds released to Dugdale were used for any other purрose than the contract or that Dugdale’s default was in any way tied to its failure to provide the diagram or the release of the funds:
[t]he principal’s default may be and usually is unrelated to any slackening off due to unauthorized advances and may indeed be retarded rather than accelerated by them. And whether the advances increase the surety’s risk depends on what the principal did with them; if he used them on the project the amount at risk to the surety may be unaffected.
Argonaut,
Accordingly, I respectfully dissent from the majority opinion and would reverse the judgment of the Court of Federal Claims.
. Within the category of intended beneficiaries, there is also a distinction made between creditor and donee beneficiaries. 2 Walter H.E. Jaeger, Williston on Contracts § 356, at 826-27 (3d ed.1959). This distinction, however, is not relevant to this discussion.
. In such cases, the impropriety of the government’s release is based in equity and not on a contractual obligation to retain the funds. The release is equitably improper because the government, although it had no other duty to retain the money, released the money after receiving notice of the surety’s interest and thus put the surety’s subrogation rights at risk. See Fireman's Fund,
. As discussed below, I believe that the government unilaterally waived the requirement that the contractor submit the project arrow diagram and relied instead on a less detailed diagram.
. The majority characterizes the effect of the release of the retainage as an impairment of collateral. See Restatement (Third) of Suretyship and Guaranty § 42 (1996). I believe the proper approach to be one of a modification of the underlying obligation. See id. § 41. This difference, however, is irrelevant because the measure of damages under either would be the same — the extent of the prejudice to the surety. See id. § 37(3).
