238 F. 705 | 9th Cir. | 1917
The defendant in error entered into a contract with the Coast Bridge Company, whereby the latter was to construct á bridge across the Kootenai river at Rexford, Mont., a swift mountain stream more than 400 feet wide. The bridge was to be for highway purposes, to be 18 feet in floor width, to consist of two spans each 220 feet long, supported, by a central pier. The bridge company agreed to provide all material and labor and to build the bridge in a good, workmanlike, and substantial manner, “so as to make it a perfect bridge, according to the plans and specifications.” The bridge company was to furnish the plans and specifications. The bridge was completed and paid for late in the fall of 1912, and early in the spring of 1913 the central pier was undermined so that it overturned and the bridge fell. The loss was total. The defendant in error brought an action against the bridge company and the National Surety Company, the plaintiff in error, to recover the sum of $30,000, the penal sum of the surety company’s bond. The case was tried before the court, ■ a jury trial having been waived. The court reached the conclusion' that the piles of the center pier were not driven in accordance with the contract, and that because thereof the pier and the bridge fell, and made a general finding for the defendant in error, and entered judgment for $29,345 with interest and costs. No special findings were requested by either party. At the conclusion of the testimony, the plaintiff in- error moved for judgment in its favor, not on the ground that there was no evidence sufficient in law to sustain a judgment for the defendant in error, but upon the alleged insufficiency of the complaint to state a cause of action, and. upon certain specified
“The question, whether or not, at the close of the trial, there is substantial evidence to sustain a finding in favor of one of the parties to the action, is a question of law which arises in the progress of the trial. Where the trial is before a jury, that question is reviewable on exception to a ruling upon a request for a peremptory instruction for a verdict. Where the trial is before the court, it is reviewable upon a motion which presents that issue of law to the court for its determination at or-before the end of the trial.”
See, also, Mason v. Smith, 191 Fed. 502, 112 C. C. A. 146; National Surety Co. v. United States, 200 Fed. 142, 118 C. C. A. 360; New York Life Ins. Co. v. Dunlevy, 214 Fed. 1, 130 C. C. A. 473; Tiernan v. Chicago Life Ins. Co., 214 Fed. 238, 131 C. C. A. 284.
The court below in denying the motion was of the opinion that, since the contract to construct the bridge had been performed, it must be presumed that it was lawfully performed, and that the necessary approval was had, and that the obligation to secure the ap
The plaintiff in error relies upon Texarkana & Ft. S. Ry. Co. v. Parsons, 74 Fed. 408, 20 C. C. A. 481, in which it was held that those who seek to justify the erection or maintenance of a bridge across a navigable river, which obstructs its navigation, upon the ground that Congress authorized its erection and maintenance, must show that it was constructed and is maintained in accordance with the requirements of the act of Congress. In that case it was conceded that the bridge had not been constructed in accordance with the specified requirements of the War Department. Undoubtedly, if the defendant in error here had been sued for damages to a vessel, caused by collision with the pier of the bridge, and the plaintiff had alleged, as did the plaintiff in his complaint in the Texarkana Case, that the bridge was an unlawful structure, the defendant in error would have been required to allege and prove that it was built in accordance with the requirements of the War Department. But that is not the present case. Whether the bridge across the Kootenai was a lawful structure is not a question involved in the action. The question is whether the surety is liable for damages for the loss of a bridge which has been constructed presumably with the surety’s knowledge of all the preliminary facts. The act of constructing a bridge without the approval of the War Department is malum prohibitum and not malum in se, and a court would be going far if it indulged the presumption, in the absence of proof, that the bridge in question was unlawfully constructed.
“And. if a payment by the owner does not impair any security to tbe benefit of which- the surety is entitled, th'e latter is not discharged.”
The plaintiff in error was a compensated surety. As to such sureties, the strictness of the old rule has b$en relaxed, and it is now held that such a company must show that it suffered some injury by reason of the alteration of the terms of the contract before it can be discharged from its liability. Williams v. Pacific Surety Co., 77 Or. 210, 146 Pac. 147, 149 Pac. 524; Leiter v. Dwyer Plumbing Co., 66 Or. 474, 133 Pac. 1180; Manhattan Co. v. United States F. & G. Co., 77 Wash. 405, 137 Pac. 1003; Atlantic Trust & Deposit Co. v. Laurinberg, 163 Fed. 690, 90 C. C. A. 274; Baglin v. Title Guaranty & Surety Co. (C. C.) 166 Fed. 356, affirmed in 178 Fed. 682, 102 C. C. A. 182; United States Fidelity & Guaranty Co. v. United States, 178 Fed. 692, 102 C. C. A. 192; Pittsburg-Buffalo Co. v. American Fidelity Co., 219 Fed. 818, 135 C. C. A. 488; American Bonding Co. v. United States, 233 Fed. 364, 147 C. C. A. 300; Guaranty Co. v. Pressed Brick Co., 191 U. S. 416, 24 Sup. Ct. 142, 48 L. Ed. 242. And such is the rule in Montana as to all sureties whether compensated or not. Dodd v. Vucovich, 38 Mont. 188, 99 Pac. 296. In that case the court gave effect to section 5686, Revised Codes of Montana, which provided:
“A surety is exonerated: (1) In like manner with a guarantor; (2) to the extent to which he is prejudiced by any act of the creditor which would naturally prove injurious to the remedies of the surety or inconsistent with his rights, or which lessens his security; or (3> to the extent to which he is prejudiced by an omission of the creditor to do anything, when required by the surety, which it is his duty to do.”
And the court said:
“In the absence of any showing that the surety was, or, indeed, could have been, injured or prejudiced by these changes, he was not released from-liability.”
The plaintiff in error contends that the effect of the Montana statutes is to give to surety companies in that state all “the rights and liabilities of private persons,” and refers to section 3 of the act of March 10, 1909 (Session Daws of 1909, p. 209), which provides that:
“Such company may be released from its liability on a bond on the same terms and conditions that are by law prescribed for the release of individual sureties.”
That section, however, relates only to the manner in which a surety may be relieved from an official bond, a manner which is specified in sections 403, 404, et seq., of the Montana Codes. It has nothing to do with sureties on construction contracts. Nor is the fact that in Montana surety’companies are given all the “rights and liabilities” of private persons material to the present controversy. It should be con
“A guarantor is exonerated, except so far as lie may be Indemnified by tbe principal, if by any act of tbe creditor, without tbe consent of the guarantor, tbe original obligation of tbe principal is altered in any respect, or tbe remedies or rights of the creditor against tbe principal, in respect thereto, in any wise impaired or suspended”
The contention is thát, since under section 5686 a surety is exonerated in like manner with a guarantor, the strict rule of section 5673 is applicable here. We think, however, that the second and third subsections of section 5686 are controlling, and that such is the effect of the decision of the Supreme Court of Montana in the case above cited. It may be added that on the trial the defendant in error offered proof that the surety company had béen indemnified by the bridge company. The testimony was excluded by the court, but there was received in evidence a letter of March 14, 1914, from the Assistant General Solicitor of the plaintiff in error to the attorneys for the defendant in error, stating that:
“This company was merely surety on the bond in question, and, of course, must be governed by the instructions and directions of its indemnitors in all matters arising under it.”
“After excavation is made to tlie full depth, piles shall be driven- inside, if so ordered by the engineer.”
This must have, referred to an engineer of bridge construction, and it should be considered in connection with the undisputed testimony that the bridge company represented to the county:
“That they, were competent bridge engineers, competent construction engineers, and that if pilings were necessary they would so advise us, and, if it were necessary to drive pilings, they would drive them.”
But there was no provision requiring that the county be represented by, an engineer, and the fact that; the county had no such engineer tends in no degree to excuse the bridge company for its failure to carry out its contract.
We find no error in the denial of the motion of plaintiff in error for judgment.
The judgment is affirmed.
Gc^For other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes
@r»For other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes
<gz»For other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & indexes