81 So. 856 | Ala. Ct. App. | 1919
Plaintiff shipped to defendant one-half barrel of boiler compound, "Guaranteed, ninety-day trial, same, if not satisfactory, to be returned and no charges made." The character of the compound was such that to be used it had to be consumed, and, if the whole of the shipment was used within the 90 days, then a return of any part of the shipment became impossible. The acceptance of the compound was subject to the approval of defendant after a test of 90 days. Under the contract the shipment could not have been rejected without this test (Manchester Sawmill Co. v. Arundel Co.,
The evidence was in conflict, and therefore the general affirmative charge as requested by the plaintiff was properly refused.
There is no error in the record, and the judgment is affirmed.
Affirmed.