149 N.Y.S. 967 | N.Y. App. Div. | 1914
Lead Opinion
The defendant, hereinafter referred to as the contractor, had a contract with the State of New York for the improvement of a portion of the Erie canal, under contract No. 62, and sublet a portion of said work on September 28, 1910, to Gabriel Bros. Construction Company, hereinafter called the sub-contractor. The sub-contractor, being unable to complete its agreement with the contractor, on August 2, 1912, entered into an agreement in writing with it by which, among other things, it was agreed that the contract between them should be terminated and canceled as of July 1, 1912; that the sub-contractor transferred and conveyed to the contractor the plant and personal property set forth in the schedule thereunto attached, together with all right, title and interest to the retained percentage still held by the contractor and all claims against the State for delays caused in the carrying out of said contract. Included in said schedule was the following provision: “* * * All Steel Forms upon the site of the contract to be used by the contractor until the contract "or work is completed. (The rent for the same to be paid by sub-contractor.)” The sub-contractor and the contractor mutually released each other from all claims and demands of every kind. The contractor agreed to pay the sub-contractor $45,000, in the manner provided by said agreement, $16,119.67 being paid in cash on the execution thereof. After certain other payments were provided for a balance remained of $20,000, payable as follows: $15,000 in three promissory notes of $5,000 each with interest, due May 20, 1913, and the remainder of $5,000 to be paid in cash as soon as the contractor was satisfied that there were no liens against the sub-contractor which remained unpaid or could be filed, and that the State had no claim against the contractor for the failure of the sub-contractor to comply with the contract and specifications on the work already performed. Then followed this paragraph: “6th. The sub-contractor agrees that if any liens • are filed against ■ the sub-contract he will forthwith discharge the same either by payment thereof or by giving a bond as provided by statute and that he will settle and adjust any claim that may be made by the State against the contractor for failure of the sub-contractor in the proper
We think, therefore, that the right to set up any damages sustained by a breach of the contract between them was not limited to such damages as the contractor sustained by the happening of either of the two specific contingencies as a protection against which this fund was held, but as well to any breach by the sub-contractor of his agreement of August 2, 1912, with the contractor. The failure to furnish the use of these steel forms to the contractor was an undoubted breach by the subcontractor of that agreement. But here we are met with the impossibility of determining upon this record what the damage was which the contractor sustained by reason of such breach. Ordinarily it would be the rent which it was required to pay in order to secure to itself the contracted right to use these steel forms. The record does not show for what period the unpaid rent was due which formed the basis of the replevin action. There is nothing to show that the defendant could not have secured the right to continue to retain and use these steel forms in its work by continuing to pay the rent stipulated by the subcontractor. If the defendant could have continued the use of the forms by paying the stipulated rent, it was its duty to have done so, rather than incur the expense of removing them and substituting others. If, on the other hand, the defendant for some undisclosed reason could not possibly have secured from the owners the right to continue to use the forms, then its damage would be the sum it was required to pay to remove the same and install the substitutes therefor, with the incidental loss due to delay in the completion of the contract. Under these conditions, and in this state of the record, we are unable to direct a final judgment. The judgment appealed from will, therefore, be reversed and a new trial ordered, with costs to the appellant to abide the event.
Ingraham, P. J., Clarke and Hotchkiss, JJ., concurred; Scott, J., dissented.
Dissenting Opinion
I agree with Mr. Justice Dowling that the $5,000 held under the contract between the sub-contractor and defendant was so held specifically as a fund to insure the contracts against the two contingencies especially provided for by the assignment, neither of which contingencies has happened. Consequently, that deposit should be ignored in this discussion, and the case considered as if no such reservation had been made.
What we should have then would be the simple case of the assignment to plaintiff of an amount still remaining unpaid by the defendant to Gabriel Brothers, plaintiff’s assignor, and the attempt to set up against the collection of this amount by the assignee, a claim against Gabriel Brothers, the assignor, not existing at the time of the assignment to plaintiff. This, as it seems to me, brings the case squarely outside section 502 of the Code of Civil Procedure, and subdivision 3 of section 41 of the Personal Property Law (Consol. Laws, chap. 41; Laws of 1909, chap. 45), which re-enacted section 1909 of the Code of Civil Procedure. By section 502 in a case like the present, a demand existing at the time of the assignment, and belonging to the defendant in good faith before notice of the assignment, must be allowed as a counterclaim, and by section 1909 as re-enacted {supra), an assigned demand may be enforced “ subject to any defense or counter-claim, existing against the transferrer, before notice of the transfer, or against the transferee.”
In each case the test as to whether or not a cross demand may be asserted against the assignee of a claim is whether or not the cross demand existed at the time of the transfer, or of notice thereof.
In the present case the assignment to plaintiff was made on October 9, 1912, and notice thereof given to defendant on October 17, 1912. At that time the claim now sought to be interposed as a counterclaim had not arisen, and it did not arise for months afterwards. It is true that the assigned claim did not become collectible until after the claim which it is sought to interpose as a counterclaim had arisen. This was not, however, because the $5,000 was not owed by defendant, but because its payment was deferred for reasons having no relation to this controversy. That I think makes no difference. The test pre
In my opinion the judgment should be affirmed, with costs.
Judgment reversed, new trial ordered, costs to appellant to abide event. Order to be settled on notice.