154 P. 25 | Cal. Ct. App. | 1915
Action to foreclose an alleged lien for materials sold by plaintiff to defendant Miller for use in the construction by him, as contractor, of a building for defendant Kennedy.
Miller made default. Kennedy answered, and upon trial judgment was entered for said defendant. The appeal is by plaintiff from an order overruling its motion for a new trial.
No record was made of the contract, which was for a sum exceeding one thousand dollars.
Two questions are presented: First, was the lien filed within the time required after the completion of the building, as provided in section 1187, Code of Civil Procedure? If not, did *781 the acts and conduct of Kennedy as owner of the building estop him from urging such ground as a defense to the action?
The court found that the building was fully completed on October 15, 1909, but that no notice of its completion was ever at any time filed with the county recorder; that plaintiff's claim and notice of lien was not filed until March 15, 1910, which was one hundred and fifty-one days after the completion of the building; that Kennedy did not, between November 3 and November 15, 1909, as alleged in the complaint, or at any time, state to plaintiff that said building was not complete according to the plans and specifications; nor is it true that plaintiff delayed filing its claim of lien because of any statements or representations made by Kennedy.
As we understand appellant's brief, it attacks all of these findings, except that as to defendant's failure to file a notice of the completion of the building.
That the building was fully complete and occupied on October 15, 1909, is conclusively shown by the evidence. The only reason suggested for claiming otherwise is the fact that a skylight put in by the contractor proved defective and later, some time in January, 1910, the defendant's tenant, being authorized so to do, employed another workman who installed a skylight in place of the one originally put in under the terms of the contract by Miller, the cost of which substituted skylight was, some time in March, paid for by Kennedy.
Appellant, basing its contention upon the case ofHubbard v. Lee,
Appellant next insists that, notwithstanding the expiration of more than ninety days, to wit: one hundred and fifty-one days, following the completion of the building, it nevertheless was entitled to file its notice of lien by reason of the provisions of section 1187, Code of Civil Procedure, to the effect that the owner may, within ten days after completion of any contract, or within forty days after cessation from labor thereon, file for record in the office of the county recorder of the county where the property is situated, a notice setting forth the date when the same was completed, or on which cessation from labor occurred. The section further provides that "in case such notice be not so filed then the said owner and all persons deraigning title from or claiming any interest through him shall be estopped in any proceedings for the foreclosure of any lien provided for in this chapter from maintaining any defense therein based on the ground that said *783
lien was not filed within the time provided in this chapter";followed by this proviso: "That all claims of lien must be filed within ninety days after the completion of any building, improvement, or structure." In support of its contention, appellant cites the case of Robison v. Mitchel,
Since the plaintiff was not entitled in any event to enforce its claim of lien, the alleged errors due to rulings upon the admission and rejection of testimony could in no event have been prejudicial to the rights of plaintiff.
The order appealed from is affirmed.
*784Conrey, P. J., and James, J., concurred.