OPINION OF THE COURT
Appellant National Iranian Oil Company (“NIOC”) petitioned the district court to compel arbitration of a contract dispute under section 4 of the Federal Arbitration Act, 9 U.S.C. § 4 (1988). The district court borrowed the Delaware statute of limitations for contract, claims and dismissed NIOC’s petition as untimely. NIOC contends that section 4 permits only the arbitrator, and not the district court, to adjudicate the timeliness of a petition to compel arbitration. NIOC also moves to dismiss this appeal and vacate the district court’s opinion on the grounds of mootness. We conclude that this appeal is not moot and that the district court properly dismissed NIOC’s petition for exceeding the applicable statute of limitations. We therefore will affirm.
I.
On April 23, 1979, plaintiff NIOC, an Iranian corporation, and defendant Mapco International, Inc. (“Mapco”), a Delaware corporation, entered into Crude Oil Sale/Purchase Contract No. 129, which contains the following arbitration clause:
Any dispute- between the parties arising out of this contract shall be settled by arbitration.
The party who wants to submit such a dispute to arbitration, shall advise the other party in writing, stating therein its claim and nominating its arbitrator. The other party shall nominate a second arbitrator within 30 days after receiving said advice.
The two arbitrators thus appointed shall appoint a third arbitrator who shall be the president of the board of arbitration. Should the other Party fail to ap *488 point and nominate the second arbitrator or should the two arbitrators fail to agree on the appointment of the third arbitrator within 30 days, the interested party may request the President of the Appeal Court of Tehran, Iran to appoint the second arbitrator or the third arbitrator as the case may be.
The award shall be governed by and interpreted according to the laws of Iran.
The seat of arbitration shall be in Tehran, unless otherwise agreed by the parties.
App. at 15-16. The contract also provided that it shall be governed and construed according to Iranian law.
In October and November of 1979, NIOC sold and delivered crude oil to Mapco in Iran pursuant to the contract’s terms. Mapco has not paid the contract price of $8,598,987.10.
On June 25, 1984, NIOC notified Mapco of its demand for arbitration and its appointment of an arbitrator. At Mapco’s request, NIOC granted an extension until September 30, 1984 to appoint an arbitrator, but Mapco never did so. On October 4, 1984, Mapco telexed NIOC, stating that it no longer considered itself bound by the arbitration agreement because of changed conditions in Iran. The parties continued to communicate until early 1987 without resolution.
On November 21, 1990, NIOC filed its petition to compel arbitration under 9 U.S.C. § 4 in the United States District Court for the District of Delaware (Civ. No. 90-682). The petition requests that the court order arbitration in the District of Delaware. Mapco moved for judgment on the pleadings and for summary judgment on three grounds. First, Mapco argued that the petition is barred by the statute of limitations. Second, Mapco argued that NIOC is collaterally estopped from seeking to compel arbitration because of the judgment in
National Iranian Oil Co. v. Ashland Oil, Inc.,
NIOC also has two related lawsuits presently pending. On May 7, 1991, NIOC filed a complaint against Mapco in the United States District Court for the District of Delaware (Civ. No. 91-269), alleging breach of the same oil supply contract which is the subject of NIOC’s petition to compel arbitration. On May 22, 1991, NIOC filed a complaint against Mapco in the United States District Court for the Western District of Oklahoma (Civ. No. 91-731-R), alleging breach of the same contract.
On March 9, 1992, Mapco filed a voluntary petition under Chapter 11 of the Bankruptcy Code in the United States District Court for the Northern District of Oklahoma. The schedules filed by Mapco in the bankruptcy court list as assets a claim in arbitration valued at $383,036 and $994 in cash. Total liabilities are listed as $28,375,-565.
The bankruptcy court lifted the automatic stay with regard to this appeal. NIOC has moved to dismiss its appeal and vacate the district court’s judgment on the *489 grounds of mootness because Mapco allegedly lacks the assets to satisfy a judgment.
The district court had jurisdiction under 28 U.S.C. § 1332(a)(4) (1988), and we have jurisdiction under 28 U.S.C. § 1291 (1988). This appeal raises pure questions of law subject to plenary review.
Ballay v. Legg Mason Wood Walker, Inc.,
II.
NIOC claims that its appeal is moot because Mapco lacks assets with which to satisfy a judgment. If this appeal is moot, the district court’s judgment must be vacated and will have no res judicata or collateral estoppel effect.
See United States v. Munsingwear, Inc.,
Under Article III of the Constitution, federal courts cannot decide moot cases because the exercise of judicial power depends upon the existence of a case or controversy.
DeFunis v. Odegaard,
A case is saved from mootness if a viable claim for damages exists.
Durkin v. National Bank of Oliphant,
In this case, the defendant Mapco has about $394,000 in assets and $28,000,000 in liabilities. Plaintiff NIOC is suing for approximately $8,600,000 in damages plus interest accrued over thirteen years. It is unlikely that NIOC will ever be able to recover more than a small fraction of the relief requested. Nonetheless, we cannot say with confidence that the plaintiff will never be able to collect any money damages from the defendant. A viable damages claim exists and therefore this case is not moot.
NIOC’s reliance on
Adams v. Resolution Trust Corp.,
We also note that if a trial court’s order will have possible collateral legal consequences, a ease is not moot.
See Sibron v. New York,
Finally, the mootness doctrine incorporates not only the threshold constitutional requirement of a live case or controversy, but also prudential concerns such as judicial economy.
See Kelly,
In conclusion, this case is not moot because Mapco possibly will have some assets to satisfy a judgment, the district court’s order may have collateral legal consequences, and the parties are reasonably likely to relitigate the same issues. We have jurisdiction over NIOC’s appeal.
III.
We now consider whether the district court, rather than an arbitrator, must adjudicate a statute of limitations defense to a petition to compel arbitration, and if so, what limitations period would apply. Title 9 U.S.C. § 4 provides:
A party aggrieved by the alleged failure, neglect, or refusal of another to arbitrate under a written agreement for arbitration may petition any United States district court ... for an order directing that such arbitration pro- *491 ceed_ The court shall hear the parties, and upon being satisfied that the making of the agreement for arbitration or the failure to comply therewith is not in issue, the court shall make an order directing the parties to proceed in arbitration in accordance with the terms of the agreement.... If the making of the arbitration agreement or the failure, neglect, or refusal to perform the same be in issue, the court shall proceed summarily to the trial thereof.
The district court must order arbitration if it determines that the making and performance of the arbitration agreement are not in issue. Id. NIOC argues that because the statute does not expressly authorize the adjudication of any other issues, it was an error for the court to consider the timeliness of the petition. NIOC reads the Arbitration Act too narrowly.
The Arbitration Act authorizes a district court to adjudicate the substantive issues of the making and performance of an arbitration agreement.
See
9 U.S.C. § 4. By implication, the statute authorizes the district court to adjudicate any procedural issues, such as timeliness under a statute of limitations, which pertain to the substantive issues within its jurisdiction. If a district court has the power to hear a claim, it does not also need an explicit statutory basis to determine the timeliness of that claim.
Cf. Gavlik Constr. Corp. v. H.F. Campbell Co.,
In their briefs and oral arguments, both parties argued that three Second Circuit cases construing section 4 support their respective positions.
See Reconstruction Finance Corp. v. Harrisons & Crosfield,
In
PaineWebber, Inc. v. Hartmann,
We now must determine if a limitations period can be imposed on section 4. The Arbitration Act does not mention any statute of limitations. The general rule is that when a federal statute does not specify a statute of limitations, a court must borrow the most closely analogous one from state law.
DelCostello v. International Bhd. of Teamsters,
The Arbitration Act reflects a strong federal policy favoring arbitration,
Moses H. Cone Memorial Hosp. v. Mercury Constr. Corp.,
Statutes of limitations protect defendants from having to confront controversies in which the search for truth may be thwarted by the loss of evidence, the fading of memories, or the disappearance of witnesses.
Gould v. United States Dep’t of Health and Human Services,
This case does not involve exceptional circumstances which would compel us to borrow a limitations period from federal law, instead of state law, to avoid interfering with or frustrating a national policy.
DelCostello,
We must now determine which state statute of limitations is most appropriate for an action to enforce an arbitration agreement. Arbitration is an action on a contract obligation,
AT & T Tech., Inc. v. Communications Workers,
The Arbitration Act does not confer federal-question jurisdiction. The district court must have an independent basis of jurisdiction.
See
9 U.S.C. § 4;
Moses H. Cone Memorial Hosp.,
*494
The district court applied the Delaware statute of limitations because it concluded that statutes of limitations are procedural, and forum law governs procedural matters. Some authorities support the district court’s position,
see White v. Govatos,
Where a cause of action arises outside of this State, an action cannot be brought in a court of this State to enforce such a cause of action after the expiration of whichever is shorter, the time limited by the law of this State, or the time limited by the law of the state or country where the cause of action arose, for bringing an action upon such cause of action.
Del.Code Ann. tit. 10, § 8121. None of the events giving rise to this suit occurred in Delaware, and the parties argue only that either Delaware or Iranian law applies. Giving NIOC the benefit of the doubt, we will assume that its claim for breach of contract accrued in Iran. The borrowing statute requires the application of the three-year Delaware statute of limitations because it is shorter than the Iranian ten-year statute of limitations. The contract specifies that it is to be interpreted and governed according to Iranian law, but the choice of law clause probably would not cause a Delaware state court to apply the Iranian statute of limitations.
See Ontario Hydro v. Zallea Systems, Inc.,
NIOC made its demand for arbitration on June 25, 1984, and Mapco failed to appoint its arbitrator within thirty days as provided in the agreement. The district court therefore held that the cause of action accrued on July 25, 1984. NIOC and Mapco agreed to extend the time for Mapco to appoint an arbitrator until September 30, 1984. It is not necessary for us to determine whether the cause of action accrued on July 25 or September 30, 1984. NIOC did not file its petition to compel arbitration until November 21, 1990, more than six years after its demand for arbitration and more than three years after the statute of limitations would have expired.
Because we conclude that the district court correctly dismissed NIOC’s petition for exceeding the applicable statute of limitations, we need not address the other potential grounds for dismissal raised by the parties.
IV.
For all of the foregoing reasons, we hold that this appeal is not moot, and that the district court correctly applied the most analogous state law statute of limitations to determine that NIOC’s petition to compel arbitration under 9 U.S.C. § 4 was time-barred. We will affirm the order of the district court dismissing the petition.
Notes
. Because of political factors, the district court could not order arbitration in Iran.
. NIOC asserts that when the contract was made in 1979, Iran had a 10-year statute of limitations for contract claims, while at the present time it has no statute of limitations. See Appellant’s Brief at 14-15 & n. 15; App. 34-47 (Declaration of Mahmoud Katirai, expert on Iranian law). For purposes of this appeal, we will assume arguendo that a 10-year statute of limitations would apply under Iranian law.
. We offer no opinion as to when NIOC’s breach of contract claims began to accrue. We observe only that if some statute of limitations other than Iran’s should apply, NIOC's claims possibly will be time-barred.
. If, however, the arbitration clause provides a substantive timeliness limitation on claims to be submitted to arbitration, in contrast to a statute of limitations, the timeliness of the demand for arbitration or of the underlying claims is a question for the district court because it concerns what claims the parties have contractually agreed to submit to arbitration.
See Paine-Webber, Inc. v. Hartmann,
. NIOC also relies on
Shearson Lehman Hutton, Inc. v. Wagoner,
. Before the district court, NIOC argued inter alia that the statute of limitations for breach of a sale of goods (U.C.C.) contract should apply. Though the underlying claim is for a breach of a sale of goods contract, the district court should be concerned only with enforcing the agreement to arbitrate. The court therefore should apply the limitations period for breach of non-U.C.C. contracts.
