Appellant National Foundation Company d/b/a Nicholson Construction Company (construction company) filed notice of appeal solely from the order of the trial court granting summary judgment to appellees Post, Buckley, Schuh & Jernigan, Inc. et al.
On June 25, 1990, John Wesley Murphy, a carpenter employed by the general contractor, E. R. Snell Contractor, Inc., fell from an unguarded walkway along a shoring wall at the Peachtree Road bridge-Georgia 400 construction project (project); as a result, he was rendered a brain-damaged quadriplegic. The shoring wall was part of a construction project designed by appellee Post, Buckley, Schuh & Jernigan, a professional engineering firm, under contract with the Georgia Department of Transportation. Appellees Stephen Hale, project manager, and Joseph McGrew, bridge designer, were professional engineers employed by appellee engineering firm.
On November 17, 1992, Kimber Fortner, legal guardian of Murphy, sued appellees and appellant construction company averring professional malpractice in the design, preparation and subsequent shop drawings for the shoring wall, and that appellant construction company was negligent in maintaining a safe work area. Appellant served as both the designer of the shoring wall and as the supervising contractor for its construction. The OCGA § 9-11-9.1 expert affidavit recites that appellee Hale was the engineer of record, certain of the drawings relating to the project were made by appellee McGrew, and the project plans were prepared by appellee engineering firm for whom Hale and McGrew acted as agents in designing, preparing and approving construction drawings for the project. The affidavit also recites that the details of the shoring wall from which Murphy fell were prepared in the form of shop drawings by an engineer-employee of appellant construction company as part of, and in implementation of, the overall project design prepared by appellee engineering firm. These shop drawings were submitted to appellee engineering firm and were reviewed and approved by their agent McGrew. The expert’s affidavit concluded that appellee engineering firm and its agents were negligent as follows: failing to design and show on the drawings a protective barrier or handrail for the top of the shoring wall; failing to provide for barriers at each end of the shoring wall to keep workers from the top of the wall; and failing when reviewing the shop drawings prepared by appellant construction company to require protective barriers or handrails on the top of the wall or barriers at each end thereof to keep workers from the wall top. The expert’s subsequent deposition testimony was not inconsistent with his affidavit. Appellee *432 engineering company submitted inter alia affidavits from McGrew and Hale in which they stated they were not negligent in connection with their design of the project or with the review of the shop drawings. They also claimed no responsibility or obligation to design barricades or handrails for the shoring wall, and that their review of appellant’s shop drawings did not require them to check for safety items such as barricades or handrails.
The trial court granted summary judgment to appellees and denied summary judgment to appellant. Thereafter, appellant and another defendant settled the case with plaintiff. As a material part of this settlement plaintiff, with consent of the trial court, dismissed its suit with prejudice after having executed a broad release of appellant and all persons and legal entities listed expressly by name in the release and settlement agreement document. Both appellant and appellees were among those entities expressly listed by name in the release and settlement agreement. Thereafter, appellant filed notice of appeal from the grant of summary judgment to appellees. See generally
Shackelford v. Green,
Appellant asserts the trial court erred in concluding there were no genuine issues of material fact presented by the evidence, and that appellees were not entitled to summary judgment; appellees contend inter alia that this appeal should be dismissed. Held:
1. “Direct appeals from orders granting partial or complete summary judgment may be taken either within 30 days of rendition of the judgment or after the rendition of the final judgment in the case.”
Studdard v. Satcher &c., Inc.,
As a general rule, voluntary dismissal with prejudice (particularly when entered with trial court approval) of an entire suit constitutes a form of “final judgment” under the appellate practice act.
Marchman & Sons v. Nelson,
Appellee engineering firm asserts, however, that because appellant secured the dismissal of all parties, including itself, from the case, no case or issue remains to be appealed. Appellant contends it is entitled to appeal the grant of summary judgment to the co-defendant, appellee engineering firm, based on the holding of this Court in
*433
Shackelford,
supra. In
Shackelford
at 618, it was opined that “[s]tatus as a losing party has been statutorily conferred upon a co-defendant who[, as in this case,] is being sued in the capacity of a joint tort-feasor and who wishes to appeal the grant of summary judgment in favor of one or more of his other co-defendants.” A co-defendant in a tort action, as a general rule, is deemed to have standing to appeal the grant of summary judgment to another co-defendant against whom he asserts a right of contribution. See
Shackelford,
supra; compare
Hussey &c. v. Ga. Ports Auth.,
Appellees, citing inter alia
Satcher &c., Inc.,
supra;
Mitchell v. Wyatt,
2. Applying the summary judgment standards of
Lau’s Corp. v. Haskins,
In malpractice cases, the breach of duty — that is, the element of failure of the professional to exercise ordinary care, skill, and diligence — must relate directly to the duty of the professional to perform the task for which he was employed.
Tante v. Herring,
Mere occurrence of an unfortunate event is not sufficient to authorize an inference of negligence.
Robertson v. MARTA,
Appellant relies substantially on the holding of this Court in
Samuelson v. Lord &c., Inc.,
We conclude as a matter of law that, under the attendant circumstances, appellees had no such legal duty toward appellant. The design and placement of handrails or barricades of a temporary nature in a work site area is primarily a safety measure rather than an inherent design requirement of the structure of the shoring wall. The duty for workers’ safety rested upon those contractors who exercised worker control and supervisory responsibility on the job site; appellees contractually exercised no such control or supervisory responsibility. Although not directly in point, under the attendant circumstances, we find the results of
Henry Roy Portwood, Inc. v. Smith,
Additionally, in determining the scope of appellees’ duty, as an issue of legal policy
(Meinken,
supra), we agree with the appellees that adoption of appellant’s position would generate an intolerable legal burden on the design community in this state, and could result in a blizzard of design litigation generated through a battle of experts. This in effect would remove the issue of legal duty from the breast of the court and vest it within the waiting grasp of the retained expert. Though appellant’s arguments in this regard are enticing, “[w]e cannot succumb to this siren’s call.”
Perryman v. Rosenbaum,
Judgment affirmed.
