Opinion for the court filed by Circuit Judge HENDERSON.
The appellant organizations, the National Association of Home Builders, National Stone, Sand and Gravel Association, American Road and Transportation Builders Association and the Nationwide Public Projects Coalition, (collectively, Industry) brought these actions in the district court to challenge a regulation jointly promulgated by the United States Environmental Protection Agency (EPA) and the United States Army Corps of Engineers (Corps) to implement the Clean Water Act (CWA).
See
Further Revisions to the Clean Water Act Regulatory Definition of “Discharge of Dredged Material,” 66 Fed.Reg. 4550, 4575 (Jan. 17, 2001) (codified at 33 C.F.R. § 323.3 and 40 C.F.R. § 232.2).
1
Section 404(a) of the CWA authorizes the Corps to issue permits to discharge “dredged or fill material” into navigable waters. 33 U.S.C. § 1344(a). Under the Corps’ regulations, permits are “required for the discharge of dredged or fill material into waters of the United States.” 33 C.F.R. § 323.3(a). The challenged portions of the regulation provide that the Corps will “regard the use of mechanized earth-moving equipment” in waters as resulting in such “a discharge” (requiring a permit) unless “project-specific evidence” shows that the dredging results in “only incidental fallback” and defines “[incidental fallback” as “redeposit of small volumes of dredged material incidental to excavation activity” if the material “falls back to substantially the same place as the initial removal.” Id. § 323.2(d)(2)(f), (ii); see also 40 C.F.R. § 232.2(2)(i), (ii). Industry objects to the two cited provisions of section 323.2 on the grounds that (1) the first creates an impermissible rebuttable presumption that all dredging results in unlawful discharge and (2) the second defines “incidental fallback” in terms of volume and thereby exceeds the scope of the Corps’ authority under CWA section 404. The district court dismissed the actions for lack of ripeness.
Nat’l Ass’n of Home Builders v. U.S. Army Corps of Eng’rs,
I.
Section 301 of the CWA generally prohibits “the discharge of any pollutant,” 33 U.S.C. § 1311(a), which is defined in relevant respect as “any addition of any pollutant to navigable waters from any point source,” id. § 1362(12). The Congress created an exception to the general prohibition for a discharge that is “in compliance with [section 1311] and sections 1312, 1316, 1317, 1328, 1342, and 1344 of [Title 33].” Id. § 1311(a). Section 404 of the CWA (referenced in the statutory excep-
*462 tion as section 1344 of Title 33) provides that the Corps “may issue permits, after notice and opportunity for public hearings[,] for the discharge of dredged or fill material into the navigable waters at specified disposal sites.” Id. § 1344 (alteration added). In 1986 the Corps issued a regulation which defined “discharge of dredged material” as “any addition of dredged material into the waters of the United States” but stipulated that “[t]he term does not include de minimis, incidental soil movement occurring during normal dredging operations.” Final Rule for Regulatory Programs of the Corps of Engineers, 51 Fed.Reg. 41,206, 41,232 (Nov. 13, 1986) (to be codified at 33 C.F.R. § 323.2(d)). Thus, a permit was required only for dredging activity that resulted in a “discharge” under this definition. In 1993, as part of a settlement agreement in North Carolina Wildlife Fed’n v. Tulloch, No. C90-713-CIV-5-BO (E.D.N.C.) (stipulated dismissal Mar. 4, 1992), the Corps and EPA amended the regulation to define “discharge of dredged material” as “any addition of dredged material into, including any redeposit of dredged material within, the waters of the United States,” without the de minimis exception. Clean Water Act Regulatory Programs, 58 Fed.Reg. 45,008, 45,035 (Aug. 25, 1993) (codified at 33 C.F.R. § 323.2(d)(1) and 40 C.F.R. § 232.2(1); emphasis added). 2 This expanded definition of “discharge” in the regulation, commonly called the “Tulloeh Rule” or “Tulloeh I,” broadened the scope of activity for which a dredging permit was required.
Industry trade associations immediately filed an action challenging the amended definition and the district court issued a decision invalidating the regulation.
Am. Mining Cong. v. U.S. Army Corps of Eng’rs,
In 2000 the Corps and EPA proposed a new rule which added the following language to the definition:
A discharge of dredged material shall be presumed to result from mechanized landclearing, ditching, channelization, in-stream mining, or other mechanized excavation activity in waters of the United States. This presumption is rebutted if the party proposing such an activity demonstrates that only incidental fallback will result from its activity.
Further Revisions to the Clean Water Act Regulatory Definition of “Discharge of Dredged Material,” 65 Fed.Reg. 50,108, 50,117 (Aug. 16, 2000) (to be codified at 33 C.F.R. § 323.2(d)(2) and 40 C.F.R. § 232.2(i)). In 2001 the Corps and EPA issued a final rule, known as “Tulloch II,” which replaced the rebuttable presumption framework with the following provision:
The Corps' and EPA regard the use of mechanized earth-moving equipment to conduct landclearing, ditching, channeli *463 zation, in-stream mining or other earth-moving activity in waters of the United States as resulting in a discharge of dredged material unless ‘project-specific evidence shoivs that the activity results in only incidental fallback. This paragraph (i) does not and is not intended to shift any burden in any administrative or judicial proceeding under the CWA.
66 Fed.Reg. at 4575 (codified at 33 C.F.R. § 323.2(d)(2)® and 40 C.F.R. § 232.2(2)® (emphasis added)). The final rule further added a definition of “incidental fallback” (with examples):
Incidental fallback is the redeposit of small volumes of dredged material that is incidental to excavation activity in waters of the United States when such material falls back to substantially the same place as the initial removal. Examples of incidental fallback include soil that is disturbed when dirt is shoveled and the back-spill that comes off a bucket when such small volume of soil or dirt falls into substantially the same place from which it was initially removed.
Id. (codified at 33 C.F.R. § 323.2(d)(2)(ii) and 40 C.F.R. § 232.2(2)(ii) (emphasis added)).
On February 6, 2001 Industry filed this action under the Administrative Procedure Act, 5 U.S.C. §§ 551 et seq., (APA) challenging “Tulloch II” as exceeding the Corps’ and EPA’s statutory authority. 3 In a decision dated March 31, 2004, the district court (treating the agencies’ summary judgment motion as a motion to dismiss) granted the motion, concluding that Industry’s challenge was not ripe because (1) the issues would not be fit for review until the Corps actually applied them ■ in concrete factual situations and (2) delaying review would impose no hardship on Industry members. Industry filed timely notices of appeal of the order of dismissal.
II.
“Ripeness is a justiciability doctrine designed ‘to prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agencies from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.’ ”
Nat’l Park Hospitality Ass’n v. Dep’t of Interior,
Under the [ripeness] doctrine’s first prong, “we look to see whether the issue *464 is purely legal, whether consideration of the issue would benefit from a more concrete setting, and whether the agency’s action is sufficiently final.” Clean Air Implementation Project v. EPA,150 F.3d 1200 , 1204 (D.C.Cir.1998) (internal quotation marks omitted), cert. denied sub nom. Appalachian Power Co. v. EPA527 U.S. 1021 ,119 S.Ct. 2366 ,144 L.Ed.2d 770 (1999). And under the second, we consider “not whether [the parties] have suffered any ‘direct hardship,’ but rather whether postponing judicial review would impose an undue burden on them or would benefit the court.” Harris [v. FAA,353 F.3d 1006 , 1012 (D.C.Cir.2004) ]; see also Ohio Forestry Ass’n v. Sierra Club,523 U.S. 726 , 733,118 S.Ct. 1665 ,140 L.Ed.2d 921 (1998); AT&T v. FCC,349 F.3d 692 , 700, 702 (D.C.Cir.2003).
Village of Bensenville v. FAA,
The district court acknowledged that the issues raised are “purely legal” and “[f|i~ nality is not a problem” but concluded Industry’s challenge was not fit for review because “both the court and the agencies would benefit from letting the questions presented here ‘arise in some more concrete and final form.’”
[T]he determination of whether an activity results in a regulable discharge of dredged material or produces only incidental fallback involves consideration of the location and the amount of the redeposit. Because of the fact-specific nature of the assessment of these factors, and their interrelated nature, we do not believe it to be feasible or appropriate to establish hard and fast cut-off points for each of these factors. Rather, the totality of the factors will be considered in each case.
66 Fed.Reg. at 4553. We conclude that the district court’s reasoning does not support postponing review for lack of ripeness.
While the final determination of whether to require a permit in a given case will, as is usual in an agency adjudication, rest on case-specific findings, this fact does not diminish the fitness of “Tulloch II” for review. Industry objects to two features of the regulation: (1) the decision to “regard” any earth-moving activity in United States waters “as resulting in a discharge of dredged material unless project-specific evidence shows” otherwise, which Industry claims simply restates (rather than deleting) the allegedly impermissible rebuttable presumption framework included in the proposed rule, and (2) the focus on volume to determine whether or not activity resulting in fallback is “incidental,”
cf. Nat’l Mining Ass’n,
Turning to the hardship prong of the ripeness test, we find that it poses no obstacle to Industry. It is true that if the court “ ‘ha[s] doubts about the fitness of the issue for judicial resolution,’ ” it will “ ‘balance the institutional interests in postponing review against the hardship to the parties that will result from delay.’ ”
Nat’l Mining Ass’n v. Fowler,
For the foregoing reasons, we conclude that Industry’s challenge is ripe for review. Accordingly, we reverse the district court’s order of dismissal and remand for review of the merits of Industry’s challenge.
So ordered.
Notes
. The Corps has jurisdiction under CWA section 404, 33 U.S.C. § 1344, over discharge of dredged and fill material; EPA has jurisdiction under CWA section 402, 33 U.S.C. § 1342, over discharge of other pollutants.
. The amended regulation did provide an exemption for "any incidental addition, including redeposit, of dredged material associated with any activity that does not have or would not have the effect of destroying or degrading an area of waters of the United States." 58 Fed.Reg. at 45,036 (codified at 33 C.F.R. § 323.2(d)(4)(i) and 40 C.F.R. § 232.2(3)(i)).
. The intervenor-appellees, three environmental organizations, contend the district court lacked jurisdiction under the APA because section 323.2(d)(2) implements section 301(a) rather than section 404 of the CWA and therefore exclusive jurisdiction to decide a challenge lies with the courts of appeals under CWA section 509(b)(1)(E), 33 U.S.C. § 1369(b)(1)(E) (vesting jurisdiction in courts of appeals for "[rjeview of the Administrator’s action ... in approving or. promulgating any effluent limitation or other limitation under section 1311 [of Title 33]”). "Tulloch II,” like "Tulloch I,” plainly implements section 404 in prescribing when a permit is required and is therefore properly challenged in the district court under the APA, as occurred in
National Mining Ass’n. See