The United States appeals a September 6, 2006, decision by the United States Court of Federal Claims granting summary judgment that the government violated its duty as stakeholder in a Miller Act payment bond case by making final
*1303
payment to a government contractor after being notified by the payment bond surety, National American Insurance Company (“NAICO”), that it was asserting a right to contract funds after having fully discharged the debt of the contractor.
Nat’l Am. Ins. Co. v. United States,
I. BACKGROUND
On June 11, 1996, Innovative PBX Services, Inc. (“IPBX”) contracted with the United States Small Business Administration to replace the telephone system at the Department of Veterans Affairs Medical Center in Palo Alto, California. IPBX subcontracted part of this work to Nortel Communications Systems, Inc., which was succeeded by Wiltel Communications, LLC (“Wiltel”). As required by the Miller Act, 40 U.S.C. § 3131(b), IPBX executed payment and performance bonds in favor of the United States, with NAICO as the surety. 1
After completion of its contract work, Wiltel notified NAICO that it was owed approximately $675,000 for labor and materials that IPBX had failed to pay. Wiltel then asserted a Miller Act claim under the payment bond issued to NAICO. NAICO settled Wiltel’s claim, notified the government that no additional payments were to be made to IPBX due to the Miller Act claim, and requested that all remaining contract funds be held for NAICO’s benefit. The government, however, did not follow NAICO’s request and made its final contract payment to IPBX. As a result, NAICO filed a complaint in the Court of Federal Claims seeking damages of approximately $280,000 from the government. The Court of Federal Claims granted summary judgment in favor of NAICO, holding that: (1) NAICO, as a surety that had made payments on a payment bond and satisfied all outstanding claims, was equitably subrogated to the rights of IPBX; (2) the Tucker Act’s waiver of sovereign immunity extended to NAICO as an equitable subrogee of IPBX; and (3) the government violated its duty as stakeholder in the payment bond by making final payment to IPBX after being notified by NAICO that it was asserting a right to contract funds. The United States appeals to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).
II. DISCUSSION
A. Standard of Review
Summary judgment is properly granted when, viewing the evidence in the light most favorable to the non-movant, the record indicates there is “no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c);
Celotex Corp. v. Catrett,
B. Payment Bond Surety Subrogation Rights
On appeal, the United States asserts that NAICO can only stand in the shoes of the subcontractor whom it paid, and since the subcontractor has no privity with the United States, there can be no Tucker Act waiver of sovereign immunity. If we disagree, the United States does not contest its liability to NAICO on the facts of this case. Thus, this case involves only the subrogation rights of a payment bond surety. Generally, “[a] surety bond creates a three-party relationship, in which the surety becomes liable for the principal’s debt or duty to the third party obligee (here, the government).”
Ins. Co. of the W. v. United States,
In 1896, the Supreme Court held that a surety could apply the doctrine of equitable subrogation in seeking retained funds from the government for completing performance of a government contract under a performance bond.
Prairie State Nat’l Bank v. United States,
In
United States v. Munsey Trust Co.,
Fifteen years later, the Supreme Court again addressed the rights of sureties to recover funds retained by the government in
Pearlman v. Reliance Insurance Co.,
Subsequently, our predecessor court, the Court of Claims, analyzed the holdings of
Munsey Trust
and
Pearlman
in
United States Fidelity & Guaranty Co. v. United States,
Subsequent opinions of the Court of Claims and this court have reaffirmed, either explicitly or implicitly, the decision in
United States Fidelity & Guaranty. See Dependable Ins. Co. v. United States,
Nonetheless, on appeal, the government argues that the Court of Federal Claims erred by declining to follow a passage in
ICW
that states “a surety who discharges a contractor’s obligation to pay subcontractors is subrogated only to the rights of the subcontractor” and “has no enforceable rights against the government.”
Dicta, as defined by this court, are “statements made by a court that are ‘unnecessary to the decision in the case, and therefore!,] not precedential (although [they] may be considered persuasive).’ ”
Co-Steel Raritan, Inc. v. Int’l Trade Comm’n,
Of course, the fact that we are not bound by that portion of ICW does not mean that its discussion of payment bond sureties’ subrogation rights is incorrect. In this instance, however, we agree with the Court of Federal Claims that the government’s reliance on ICW and Munsey Trust is misplaced. 2
As discussed above,
Munsey Trust
involved a surety that claimed it was equitably subrogated to either the rights of the subcontractor whom it had paid or the rights of the government.
Nonetheless, the government argues that
Department of the Army v. Blue Fox, Inc.,
III. CONCLUSION
Because the Court of Federal Claims correctly held that NAICO was equitably subrogated to the rights of the contractor whose debt it discharged, we affirm.
AFFIRMED
Notes
. Pursuant to the Miller Act, a contractor awarded a contract of more than $100,000 with the United States is required to furnish two bonds: a performance bond "for the protection of the Government," and a payment bond "for the protection of all persons supplying labor and material in carrying out the work." 40 U.S.C. § 3131(b). The payment bond provision was designed to provide an alternative remedy to the mechanics’ liens ordinarily available on private construction projects.
F.D. Rich Co. v. United States ex rel. Indus. Lumber Co.,
. Because ICW relies on Munsey Trust for the proposition that "a surety who discharges a contractor’s obligation to pay subcontractors is subrogated only to the rights of the subcontractor,” we focus our analysis on Munsey Trust.
