94 Tenn. 356 | Tenn. | 1895
This is an action by Sutherland & Co. against the city of Nashville for damages. There was a trial before the Court below and a jury, and a verdict and judgment for' $1,768, and the city has appealed.
Sutherland & Co., in 1888, were the owners of certain property in Nashville, situated on the east side of the Cumberland River, on which was located a lumber yard and planing mill. Adjacent to this property was a pool or pond of stagnant water, which the Mayor and City Council, through the Board of Public Works and Affairs, desired to drain by means of a sewer-pipe, leading to the river through plaintiffs’ premises. Specifications and plans of a suitable sewer, showing size and quality of pipe, means of connection at the river, and the manner in which the work was to be done, were prepared by the city engineer, and filed in his office. The Mayor, etc., did not condemn a right of way across the property in question, but an easement was purchased by the Board* of Public Works and Affairs in the following contract, to wit:
“For and in consideration of one hundred and fifty dollars, cash to us in hand paid, the receipt of which is acknowledged, and other valuable considerations by us received from the Mayor and City*358 Council of Nashville, we, William Sutherland and Charles A. Graves, do hereby sell and grant unto the said Mayor and City Council of Nashville the right, power, authority, and privilege to enter upon the realty owned by us between Bridge Avenue and Main Street, and First Street and the Cumberland River, to construct, keep up, and maintain a sewer or drain, commencing at or near the west end of an alley, that is now in existence on said property, about midway between Bridge Avenue and Main Street, and which runs parallel to said streets to First Street. The said sewer or drain to be constructed according to the plans and specifications now on file in the city engineer’s office, to which reference is expressly made, and the same is adopted as a part hereof as fully as if expressly set out and described in detail. So far as may be necessary in constructing and keeping up and in repair said sewer, an interest is hereby conveyed in said realty. We covenant, agree, and bind ourselves that we are lawfully seized and possessed • of said realty, have a good right to convey it for such purposes, and that the same is unincumbered, and that we will warrant and defend the title against all lawful claims whatsoever.
ult is further agreed, and the city of Nashville binds itself to have said sewer so constructed with a sioitable valme as will prevent, in case of high rise of rimer, the "flowing of water from the rimer bach through said pipe or sewer into the lot or premises*359 of said Sutherland and Granes, to their injury oi' damage.
“The city further agrees to place the roadways of said parties back in as good condition as before the same is disturbed by the laying of said sewer-pipe; and, should said sewer have to be repaired at any time, the city will likewise put said roadway back in good and first-class condition. This the fifteenth day of June, 1888. Wm. SUTHERLAND,
“Chas. A. Graves.”
Subsequently, on the eighteenth of June, 1888, the Board of Public Works and Affairs entered into a contract with Ryan & Shea, contractors, to construct the sewer according to the specifications filed in the city engineer’s office, being the same referred to in the contract purchasing the right of way. This contract, with the specifications attached, is fully set out in the record. This contract was executed by the said Ryan & Shea, and the work was completed sometime in the summer or fall of the year 1888.
In March, 1890, something more than eighteen months after the sewer had been completed, there was a high rise in the Cumberland River, which overflowed Sutherland & Co.’s property. There was at that time a quantity of lumber stacked on the lot, *a portion of which was overflowed and seriously damaged. Eor this damage Sutherland & Co. brought suit against the Mayor and City Council of Nashville.
In the first trial of the case, the Circuit Judge charged the jury that that portion of the contract set out above in • italics was an absolute guarantee on the part of the city against injury. There was a verdict against the city, and, upon appeal to this Honorable Court, a new trial was granted, upon the ground that the provision insuring Sutherland & Co. against damage was ultra vires, so far as it under-, took to make the city a guarantor against injury in any contingency. Nashville v. Sutherland & Co., 8 Pickle, 335.
The first count in the original declaration is based upon the contract and the further allegation that, in constructing the sewer, worthless and unsuitable valve material was used, and that the sewer joints and valve connected therewith were constructed, laid, and joined together in a careless, negligent, improper, and unworkmanlike manner,' which caused great quantities of water, during a freshet, to be forced back through the valve and pipes and sewer until it covered plaintiffs’ lot and damaged their lumber stacked thereon with water and mud, and plaintiffs were put to great expense in trying to pump the water off the lot in order to prevent the same.
The second count is substantially the same, and
The third count sets out the contract, and alleges as a breach that unsuitable material was used, and the workmanship' was defective, which caused the damage.-
After the cause was remanded from the Supreme Court, an amended declaration was filed charging unsuitableness of the valve and other material used, and careless, negligent, and improper and unwork-manlike manner of construction and joining together, the result of which was the damage sued for without mentioning the contract. To this amended declaration the defendant filed a plea of not guiltjr, and the statute of limitations of three years. On the trial, and after the proof was all in, the trial Judge sustained the plea of the statute of limitations, the effect of which was to strike out the amended declaration.
It is claimed by the defendants in error that this flood caused them damage to lumber in the sum of $1,750, and expense in preventing increased damage, by way of employing engineers and firemen, $150; and for hauling to the premises a pump, and operating the same, $150; and for use of boilers, for fuel and oil, and for removing and replacing machinery, $250.
The first assignment of error is that there is no evidence to sustain the verdict.
The second assignment is that the Court erred in charging as follows:
*362 £ c (a) The question for you to solve, so far as that (the valve) is concerned, is: Did the city use ordinary care in providing a backwater trap at that point? Was it reasonably sufficient, and reasonably adapted to the purpose for which it was designed? If so, there can be no liability accruing against the city on that account.
“ (p) You will, then, gentlemen, consider all the circumstances of the case — location of the pipe, the method by which it opened into the pond and the method by which it was discharged into the river, the means provided by the city to prevent the flow of the backwater into the pipe, the manner in which the joints were constructed — and from all this you are to determine whether or not the city did or did not exercise ordinary diligence in doing this work. If it did exercise ordinary care, and, notwithstanding that fact, and without fault on its part, the plaintiff was injured, then your verdict should be for the defendants; but if • they did fail to exer-. cise ordinary care, and by reason thereof the plaintiff was injured, then your duty would be to find for the plaintiff.
‘ ‘ (c) In regard to damages : The damages which any party is entitled to recover must be such as are the natural and proximate result of the wrong complained of. Now, by natural is meant, simply, according to the natural course of events. Hy proximate is meant that which directly flows as an effect from some cause which is the sole, responsible, and*363 efficient cause of the injury. In other words, if the negligence of the city, in this case, was the responsible cause of the damage to the plaintiffs, the cause without which the injury would not have occurred, that would be the proximate cause.
“(d) The Court will charge you further, at the request of the plaintiffs, that it was the duty of the city, in providing a valve, or backwater trap, to make it reasonably safe and well adapted for the purposes for which it was designed.”
The fifth assignment may be considered in connection with the second, and is that the charge, taken as a whole, was misleading and confusing to the jury, as follows: The jury is told that the suit is for a breach of contract, and then, subsequently, they are instructed, in arriving at the city’s liability, to consider whether or not it exercised ordinary care in making the improvement; whereas, the principle which measures its liability is whether or not it did what it contracted to do. It is insisted that, under the original declaration, the suit being based upon the contract, the jury should have been instructed that the question was not whether the city exercised ordinary care, so as to escape common law liability, but did it construct the sewer according to the contract; and that the specifications of the contract furnish the limits to the rights and responsibilities of the parties.
The contract in this case makes the specifications of the city engineer a part of the contract, and it
It is evident from its terms that this contract obligates the city to condemn all defective or unsuitable material or work, or, what is the same thing, to use only suitable material, and have the work carefully and properly done. It is also apparent that the plaintiffs were then relying upon the city’s guarantee, and it was but natural that they should feel disposed to leave the selection of material and mode of construction to the superior knowledge and skill of the city engineer.
It will be noticed that the backwater trap is not in any way described in the specifications, 'but the joints and pipes were to be laid in cement, and the
Conceding that the city could not be held as a guarantor, and that, so far as material and mode of construction were specifically set out in the engineer’s specifications, the plaintiffs could insist upon nothing different, still, it is true that, under this contract, the kind of a water trap was left to the discretion of the city engineer; and the charge of the Court was, in substance, that, in selecting such valve or trap, and in constructing the sewer, laying the pipe, and cementing the joints, the city must use ordinary care, and would be responsible for the want of such care; and this is correct, both under the contract and the idea of a common law liability. Burton v. Chattanooga, 7 Lea, 739; Jones on Negligence of Municipal Corp., Secs. 139, 143, 144.
It is insisted that the plaintiffs, with full knowledge, acquiesced in the manner in which the work was executed, and made no objection to the kind of water valve or trap furnished, or to the manner in which the pipes were laid, for more than a year after the work was completed, and until the damage was done, and hence they are estopped to claim damages.
In this connection, the Circuit Judge was requested to charge the following propositions: ■
*366 “1. If you find from the evidence that the plaintiffs, or either of them, were present, from time to time, when the sewer was being constructed, and knew that the joints of pipe were not being laid in cement, as the plans and specifications required, and made no complaint to the officers and agents of the city on account thereof, but permitted the city, or its contractors, to lay said pipes across their property without laying the joints in cement, then they cannot hold the city liable for any damages resulting from a variation from' the specifications as to cemented joints.
“2. If you find from the evidence that the plaintiffs knew that the joints were not being laid in cement, as the specifications required, made no complaint on account thereof, and acquiesced in the variation from the specifications, then the city is not liable for a suit for a breach of contract from any damages resulting from such variation.
“3. If you find from the evidence that the plaintiff's knew, as the work progressed through their property, that the joints were not cemented, then the measure of damages for a breach of contract for a failure to cement the joints is the cost of cementing said joints, for plaintiffs could have done tjiis, and it was their duty to have it done, if they believed it necessary to the protection of their property.
‘ ‘ 4. If you find from the evidence that the plaintiffs knew when the water valve was put in that it*367 was ineffectual for the purpose for which it was intended, and that such a valve would subject their property to overflow, then it was their duty, in' order to protect their property, to procure a suitable valve; and, if they failed to do this, they were guilty of contributory negligence, and therefore cannot recover from any damage resulting on account of the valve used.
“5. The defendants, the Mayor and City Council of Nashville, cannot, by contract, destroy the discretion and judgment- of its officers and agents in carrying out public improvements. It has no right, by its officers and agents, to bind itself to carry out public improvements upon an impossible and impracticable plan. If, therefore,, you find that the agents and officers bound themselves to the plaintiffs to cement the joints in the sewer in question, and that it has been proved in evidence by experts that it developed in the prosecution of the work that it was impossible or impracticable to cement said joints, then the contract binding the city to cement the same is void, and of no effect.” All of which were refused, and no charge was given upon the question of acquiescence or estoppel.
It must be borne in mind that this work was being d,one for the benefit of the city, and not for the plaintiffs, or at their request, and their premises were being used simply as a convenient, if not indispensable, way to reach the river and effect the drainage. The contract to build the sewer was be
We think these are legitimate items of damage, and the jury, from the proof, was well warranted in so finding.
The judgment is affirmed with costs.