182 Mass. 12 | Mass. | 1902
After a rescript from this court overruling certain demurrers (174 Mass. 335), this case was heard upon its merits by three judges of the Superior Court, who found for the petitioner in the sum of §4,254.68; and on April 9, 1901, a final decree was there entered for the petitioner for that amount and costs. The case is now before us upon appeals by the respondent Casparis from this finding and from the decree.
The first objection made by the appellant is that the petitioner before selling the cement to Smith and Burden gave no notice that he intended to claim a lien. In support of this objection, the appellant argues that the statute was passed for the protection and convenience of the Commonwealth; that it is a part of the laws relating to finance; that in'1878, when the statute was first passed, it was probably thought that possibly public liens might be maintained against public works, or at least that claims of such a nature might be made; that the purpose of the statute was to protect the Commonwealth against such claims and to provide it with security against possible loss ; and that there is no indication in the statute or in the context that it was intended to furnish an absolute guaranty of payment for all material used in public works. The appellant insists that from this view of the statute it follows that in order to prevail the petitioner must show that he gave notice, as would have been necessary if the aqueduct had belonged to a private person.
We cannot assent to this general view of the purpose of the statute. It first appeared as St. 1878, c. 209, entitled “An Act to insure payment of wages earned and for materials used in constructing public buildings and public works.” It speaks of “public buildings or other public works . . . upon which liens might attach for labor or materials if they belonged to private persons,” and it provides that it shall be the duty of the officers contracting in behalf of the Commonwealth to provide security for the payment of certain laborers and material-men. The title would seem to indicate that the purpose of the act was not to protect the Commonwealth as a property owner against lienors, but to provide a way in which laborers and materialmen in certain cases could be made more secure as to
Even if it be assumed that the statute provides only for the payment of such claims as could have been enforced against the property of a private person, it by no means follows that the lienor should have taken the steps required by Pub. Sts. c. 191, to fix the lien as in the case of private ownership. Under the last named statute the materialman before furnishing the materials must give notice to the owner (if he is not the purchaser) that he intends to claim a lien, and within thirty days from the time he ceases to furnish them must file the certificate required by § 16, and within ninety days must begin a suit for enforcing the lien. The mere recital of these steps is sufficient-to show that it was not intended that they all should apply. Indeed none of them applies. By virtue of the contract with Smith and Burden the petitioner was bound to furnish cement for the work, and if the property had been that of a private owner lie stood in a position to make his lien complete. It was possible for him to take the steps, namely, to give the notice before furnishing the cement, to file the certificate and to begin the suit within the required time. A lien might therefore have attached. When the contract to furnish the cement was made, the time had come when the petitioner had it in his power by his own act to take the necessary steps if the property was that of a private owner to attach a lien. He was no more required to take the first step than the second or third. By virtue of his contract he was placed where the lien might attach for materials furnished, and the public work was of such a kind that if the owner had been a private person a lien might attach; and even if the statute covers only those claims which by the act of the lienor may as against the property of a private person finally ripen into a lien, it is plain that the claim of the petitioner is within that class. There was no need for notice before the materials were furnished that he intended to claim a lien.
The notice filed in the office of the water board in compliance with article 19 of the contracts was sufficient to cover all the cement furnished by the petitioner. Casparis had contracted to build sections five and six by two separate contracts, both of
It is strongly urged by the appellant that the petitioner has been guilty of loches. We think however that there has been no delay which, as matter of law, should bar the petitioner. Casparis knew the nature of the contracts between himself and the Commonwealth, and between himself and Smith and Burden, and in the exercise of reasonable diligence might have known that the latter had bought cement from the petitioner which had been delivered at the site of the work and had not been paid for. He must be held to have known that whoever had furnished to Smith and Burden materials for which payment had not been made might make a claim to be paid out of the fund reserved by the Commonwealth for the laborers and materialmen under the contracts. .If under the circumstances disclosed in this case he chose to settle in full with Smith and Burden, he must be held to have done it at his own risk.
The only remaining question relates to the amount for which judgment should be entered. All of the cement was sold to Smith and Burden and delivered to them at the site of the work, and it was all accepted by the Commonwealth and subsequently was used in the work. Only a part of it, however, was used by them. They failed in December, 1896, and abandoned their contract. At that time more than one half of the cement was still unused. Upon this failure, Casparis, under his contract
Decree affirmed.