283 F. 569 | D. Idaho | 1922
In accordance with the expressed desire of the parties, the averments of the complaint are given a liberal construction, to the end that the merits of the controversy may be adjudged
1. Our discussion may be clarified by having at the outset a just understanding of the plaintiff’s relation to the subject-matter of the suit. Whatever may be its formal legal status under its contract with* the government, it is. not the real party in interest. In practical effect it is but an intermediary, an agency, resorted to by the real parties in interest, for convenience, in the distribution of water and the collection of charges on account thereof. Back of it, as the real plaintiffs, are the project lands within its borders; they are the sole beneficiaries.
2. Originally these lands had precisely the same status as all other lands on the project.
3. This status was not materially altered by the contract between the district and the government. The contract concerns procedure, and relates to form rather than substance. It clearly discloses the intent of the parties thereto that in effect all project lands, both within and without the district, were to continue to be upon the same footing, sharing ratably in the benefits and burdens of the irrigation system.
5. In fairness and equity, then, what can be said in defense of the position for which the plaintiff lands now contend? During the earlier part of the operation of the system, when they were threatened with destruction or injury from the rising ground water, they sought and were given protection by the construction of a drainage system, the cost of which was included in the general construction charge, and as such was, of course, ratably apportioned to all the lands in the project. Now, when, as a result of the further operation of the system, for their use and benefit, as well as for the balance of the project, other lands are menaced in the same way and from the same source, they seek to shift the entire burden of similar protective measures to the lands to be directly benefited. When they were threatened, they did not, as now, invoke the doctrine of assessment of benefits; at least, no such doctrine was recognized or applied in distributing the cost of the drainage facilities created for their protection.
6. Though there is no equity in the position, we are asked to sustain it because of certain considerations of technical law. In substance, as I understand it, the reasoning is that the plaintiff lands are in an irrigation district, that the charges must be collected by assessments under the state law, that before such assessments can be made there must be
When the drainage ditches within the plaintiff - district were constructed for the plaintiff lands, they were correctly treated as a part of the irrigation system, and quite as correctly their cost was distributed ratably to all the lands without consideration of the question of direct benefit, it follows that, by the apportionment already made in the district of the benefits of the system as a whole, pursuant to the state statutes, the basis of distributing cost has been fixed once for all; not the cost of constructing or maintaining any single unit, but the entire system, including every feature thereof, whether primary or auxiliary. It is the apportionment of the burden of constructing the entire project in accordance with the benefits received by the several tracts of land from the project as a whole.
True, the expenditure under consideration is relatively large, but it is to be borne in mind that it is to meet a condition which has gradually grown up as a result of the continued operation of the system. If each year there had been a collection and expenditure of an amount commensurate with the result of that year’s operation, the case would present a different aspect, but would involve the same principle. By express admission the condition to be overcome is the direct result of operation, and is an incident thereof, and if the project is to be “maintained” the expenditure must be made. If in the course of operation the management incurred a liability for injury to land by flooding or for destruction of crops, undoubtedly the expense of discharging such a liability would be borne as an operating expense. May it not take the less expensive course of providing safeguards against such flooding and charge the expense thereof to maintenance and operation? With knowledge that the operation of the system without drainage facilities will inevitably swamp large areas of land, rendering the same worthless, and destroying the crops and trees growing thereon, must the plaintiff stand by until confronted with claims for damage?
Plaintiff frankly concedes that the condition against which the government seeks to provide is a direct result of operating its irrigating system. It also concedes that, while ground water is always a possible, if not a probable, contingency, drainage facilities to take care of it cannot safely be provided in advance, for there can be no intelligent prognosis of just where such waters will rise and do or threaten injur}'. If, however, the cost of such facilities is chargeable only to construction, the government is in this dilemma: Until it has completed its irrigation system and sold water rights, and has delivered water to supply them, it cannot include such cost in the cost of construction, for there are no possible data upon which to base an intelligent estimate of the amounts. But it must fix the “construction charge” before it can sell water rights. Hence such charge cannot be included in tire construction cost as declared in the public notice, and the amount fixed in the public notice cannot thereafter be increased without the consent of
It is not thought that Congress could have intended that the terms “operation” and “maintenance” would be construed so strictly as thus to render the Reclamation Service impotent to protect the government investment and the interests of the settlers. A reclamation project is for the reclamation, and not the destruction, of lands, and it is expected that the reclaimed lands will return the investment and maintain the project as a going and fruitful concern. Here is an operation result highly injurious to the project. If the proposed protective measures are not taken, admittedly a large area of the project lands will be rendered worthless. If they are thus made worthless, they, will not only be incapable of returning to the government their ratable and apportioned part ofjhe construction cost, but they will also necessarily fail to carry any part of current maintenance and operation, and thus will be shifted their proper burden to the remaining lands on the project, including the plaintiff lands. But this is not all. If in principle the pláintiff’s contention is right, it is equally applicable to a case where the ground water rises uniformly over the entire project, and threatens the destruction of all the lands at the same time. In such a case the project as a whole cannot be “maintained,” but is to be destroyed, as a result of “operation,” because an admittedly sensible expenditure, by which such self-destruction can be avoided, may not be charged as an expense of either operation or maintenance. In other words, the cost of self-preservation from an ordinary and necessary incident of operation is not chargeable to either maintenance or operation. To state the proposition is to reject it.
8. Finally, it is suggested that until recently it has been customary with the Reclamation Service to carry drainage as a part of construction. I do not stop to inquire touching the correctness of the statement. The facts are not expressly pleaded, and if, so far as concerns this project, we go to the sources from which the facts are to be gotten, we find that, at the time the drainage expenditures covered by the plaintiff’s contract were made, the service also included in “construction” cost what are admittedly expenses of operation and maintenance; that is to say, during the long period prior to the giving of formal public notice the partially completed system was operated, and in the course of such operation large expenses were incurred over and above the rentals and other income for the same period, and this balance was covered into and charged against construction cost. It follows that a like disposition of the drainage expenditure has little interpretative significance.
It being thought that the proposed method of providing protective means, admitted to be necessary, against a menace, conceded to be the direct result of operating the system, is fair and equitable, and contravenes no statutory or contractual right, the motion to dismiss will be allowed.