52 Conn. App. 367 | Conn. App. Ct. | 1999
Opinion
The plaintiff, Naek Construction Company, Inc., appeals from the judgment of the trial court denying the plaintiffs motion to vacate an arbitration award rendered in favor of the defendant, Wilcox Excavating Construction Company, Inc., and granting the cross application to confirm the award. We affirm the judgment of the trial court.
The following facts are relevant to this appeal. The plaintiff, as general contractor, entered into a contract (prime contract) with the state of Connecticut to construct barracks for Troop C of the state police in Tolland (project). The plaintiff subsequently entered into a subcontract with the defendant, who was to perform the site excavation for the project. Thereafter, disputes arose between the parties and the subcontract was terminated.
On appeal, the plaintiff claims
“In determining whether a submission is unrestricted, we look at the authority of the arbitrator. The authority of the arbitrator to adjudicate the controversy is limited only if the agreement contains express language restricting the breadth of issues, reserving explicit
The following additional facts and procedural histoiy are necessary for our resolution of this appeal. During the arbitration proceedings, the parties submitted joint exhibits to the arbitrator. Although one of the exhibits purported to be a copy of the prime contract, it was incomplete and not signed. After the arbitrator issued his award, the plaintiff asked that the arbitrator conform his award to § 4-61 (e). The arbitrator denied the request. The plaintiff then moved to vacate the award claiming that (1) the award did not conform to the contract requirement to follow § 4-61 (e), (2) the arbitrator was guilty of misconduct in accepting evidence after the close of the proceedings and (3) the arbitrator imperfectly executed his powers in not providing a mutual, final and definite award.
The trial court heard oral argument on the parties’ motions on several days. On December 30, 1996, with the consent of the parties and with their agreement as to the language of the request, the trial court asked the arbitrator for an articulation of his award. The arbitrator responded to the trial court on March 14, 1997. The articulation consisted of several attachments or tabs; tab B sets forth how the defendant’s award was computed and tab C sets forth how the plaintiffs award was computed. The plaintiff renewed its application to
The trial court determined that the submission to the arbitrator was the subcontract between the parties and that article I of the subcontract provides that “the subcontract documents consist of . . . (2) the Prime Contract, consisting of the Agreement between the [state and the plaintiff] . . . .” Article 6.1 of the subcontract provides that arbitration “shall be conducted in the same manner and under the same procedure as provided in the Prime Contract with respect to claims between the [state and the plaintiff] .... If the Prime Contract does not provide for arbitration or fails to specify the manner and procedure for arbitration, it shall be conducted in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. . . .’’The trial court found that the prime contract between the state and the plaintiff was never in evidence before the arbitrator. In response to the plaintiffs claim that the prime contract was incorporated by reference, the trial court reasoned that, assuming the plaintiffs argument is correct, the original or a copy of the executed prime contract should have been submitted to the arbitrator to ensure its accuracy and to advise the arbitrator of its provisions. Without the provisions of the prime contract before him, the arbitrator properly concluded that the submission was made pursuant to the construction industry arbitration rules of the American Arbitration Association. The trial court, therefore, concluded that the submission to the arbitrator was unrestricted and that the award conformed with the submission. We agree with the trial court’s reasoning.
As we have stated, the parties determine the scope of the arbitration submission by the terms of their
Because the submission was unrestricted, the trial court properly confirmed the arbitration award, and we need not consider the issues subsumed in the plaintiffs main claim.
In this opinion the other judges concurred.
Some of the disputes allegedly arose due to changes requested by the state.
The award also included the following language: “In accordance with the request of the parties, included in the [defendant’s] award are the following: Tomlco Electric Company’s claim $6625, MPH’s claim $1325.”
The plaintiff framed the issue as follows: “Did the trial court err in not finding that the arbitrator failed to perform his duties in failing to issue findings of fact pursuant to General Statutes § 4-61?” The following issues are subsumed in the plaintiffs primary claim: (1) the contract specified that the provisions of any submittal to arbitration would be pursuant to the same rules and procedures as set forth in § 4-61; (2) the rendition of the arbitration award was restricted to the terms of § 4-61 and thus findings of fact were mandated by these procedures; and (3) the arbitrator did not perform his duties as specified and in violation of General Statutes § 52-414.
Section 6.1 of the subcontract provides: “Any controversy or claim between the Contractor and Subcontractor arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration, which shall be conducted in the same manner and under the same procedure as provided in the Prime Contract with respect to claims between the Owner and the Contractor, except that a decision by the Architect shall not be a condition precedent to arbitration. If the Prime Contract does not provide for arbitration or fails to specify the manner and procedure for arbitration, it shall be conducted in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise.”
The plaintiff claims that the prime contract provides that, pursuant to state mandate, arbitration proceedings are to be controlled by subsections (d) and (e) of General Statutes § 4-61, which is entitled “Actions against the state on highway and public works contracts. Arbitration.” The plaintiff claims that the arbitrator’s factual determinations are necessary in order for it to present its claims against the state.
General Statutes § 4-61 provides in relevant part: “(d) Hearings shall be scheduled for arbitration in a manner that shall ensure that each party shall have reasonable time and opportunity to prepare and present its case, taking into consideration the size and complexity of the claims presented. . . .
These issues are subsumed in the plaintiffs appeal to this court.
The trial court also determined that to confirm the award it need not address the plaintiffs additional claims, but it did address them in its memorandum of decision. Even if we were to assume that § 4-61 applies to the proceedings, the trial court found in its memorandum of decision that the award was in compliance with the statute: “There is no question that a written award was made on June 5, 1996. Findings of fact were clearly set out in the award and in the arbitrator’s articulation dated March 14, 1997, in which he broke down the amounts awarded and described them. The descriptions in tabs B and C, i.e., ‘surveyor’s mistakes, additional cost for protection due to project hold-up, cost to correct work not acceptable, cost to complete the Mizzy contract less Wilcox remaining,’ clearly show to those in the construction industry the basis of the awards as they are applicable to the terms of the contract.” (Emphasis added.)
The trial court also found that the plaintiff did not sustain its burden of proof that the arbitrator accepted and used evidence from the defendant submitted after the close of evidence. The defendant claimed that what the