54 S.W. 412 | Tex. App. | 1899
J.E. Nading sued the railway company for $1200 damages alleged to have been caused by the negligent and improper construction of its road along and adjoining his property, lots 14 and 15, block 10, Dumas' addition to the city of Denison. The road was constructed in 1895.
The defendant denied generally, and specially pleaded that for a valuable consideration plaintiff had conveyed to it a strip off of said lot 14 along which the road was constructed for that specific purpose, and that a part of the consideration paid was the conveyance of lot 15 by it to plaintiff, and that he was not the owner of lot 15 until thus acquired.
The case was tried and resulted in a verdict and judgment for plaintiff in the sum of $250.
1. The court below should have granted a new trial in this case. The evidence clearly showed that the road was constructed in a negligent manner, resulting in damage to plaintiff's property, and each and all of the witnesses who testified as to the amount of damages sustained showed the damages to be greater than that awarded by the verdict of the jury. This will require a reversal of the judgment.
2. The injury to the property is shown to have been occasioned by the caving in of the walls of a deep cut excavated by the railway company, and it was shown that this could have been prevented by the use of sufficient bracing of the walls. The caving extended to and embraced the lots of the plaintiff and threatened to take the foundations from his houses and cause them to tumble into the cut, extended by such caving. Plaintiff offered to prove that he incurred expense in preventing the extension of the injury, and in repairing the injury which was caused by such caving. This evidence, on objection, was excluded on the ground that such expense was not a proper element of damages to be recovered in the case. Plaintiff is entitled to be reimbursed to the extent to which he suffered damage by reason of the negligent and improper construction by the defendant. It was proper and right for him to prevent the *175 damage as far as he could; it was his privilege to repair that which was done, and he should be made whole by the recovery.
"If one's property is taken, injured, or put in jeopardy by another's neglect of duty imposed by contract, or by his wrongful act, any necessary expense incurred for its recovery, repair, or protection is an element of the injury. It is often the legal duty of the injured party to incur such expense to prevent or limit the damages; and if it is judicious and made in good faith, it is recoverable though abortive." 1 Suth. on Dam., 2 ed., 132; City of Nashville v. Sutherland, 29 S.W. Rep., 228. Care should be taken, however, not to allow a double recovery for this element of damage. It may be questioned whether this element of damage was pleaded with sufficient certainty, but no exception to the pleading upon this ground was sustained by the court, and this objection was not urged against the introduction of the evidence.
3. The court in its charge correctly stated to the jury that the plaintiff would not be entitled to recover for any damage in the way of the decreased value of the property which a careful and proper construction would have produced, but would be confined, in relation to such decreased value, to the damage caused by the negligent manner of construction, causing the caving of the walls of the cut, etc. Plaintiff had sold to the railroad company a strip off lot 14 for the purpose of its road and in contemplation of its construction, and no recovery could be had for damages resulting from a proper construction. In addition to the special element of damage heretofore considered, the true inquiry is, how much damage was done to the property by the failure of the company to exercise proper care to prevent the caving of the walls of the cut? This may be determined by ascertaining what would have been the value of the property with a proper construction of the cut, at the time when it was constructed, and what was its value just after its construction and the caving of the walls, including the value of the repairs made by the plaintiff, if any, and taking the difference between such values, — it not appearing that any material change in the value of such property occurred from other causes within the period of time intervening between the construction and the caving of the walls of the cut which could affect the question. The court refused to allow the plaintiff to testify as to the value of his property, without reference to the construction, just before the construction, and its value just after. As independent evidence, this would not have furnished a correct criterion of the damage done the property. The court did permit the defendant, however, to offer this character of evidence. Of course it was not proper to shut out the plaintiff from this inquiry and open it to the defendant. It may be, as is sometimes the case, that the record does not correctly reflect the action of the court as to this particular matter.
The judgment is reversed and the cause remanded.
Reversed and remanded. *176
Overruled.