[Re: ECF No. 71]
INTRODUCTION
In this action, several entities sued each other after a mierotunnel boring machine broke down while it was boring an underground tunnel on a construction project for the San Francisco Public Utilities Commission (“SFPUC”). Plaintiff Nada Pacific Corporation (“Nada”) leased and operated the machine as a subcontractor for the project’s general contractor, and Defendant/counter-defendant Besser Company (“Besser”) manufactured a component in the machine. Besser moves for summary judgment against Nada on three grounds: (1) Nada is judicially estopped from arguing that Besser’s allegedly defective component caused the boring machine to fail because Nada argued before a dispute resolution board established by its general contractor’s contract with the SFPUC that site conditions caused the machine to fail; (2) alternatively, Nada cannot use the collateral source rule to obtain a duplicate recovery of the amounts it recovered from its general contractor for the same damages it seeks in this case; and (3) alternatively, Nada has put forth evidence of only its economic losses and thus the economic loss rule bars its tort claims. Upon consideration of the parties’ papers and their arguments at the November 6, 2014 hearing, the court holds that (1) judicial estop-pel does not apply because the dispute resolution board did not decide the dispute, (2) Nada’s potential recovery is offset by the money it recovered from its general contractor, and the collateral source rule does not apply, and (3) the economic loss rule bars Nada’s tort claims against Bes-ser. The court thus GRANTS Besser’s motion.
STATEMENT
I. THE PARTIES AND THE PROJECT
This case arises out of the September 2010 failure of a microtunnel boring machine (“MTBM”) while it was boring an underground tunnel on a construction project referred to as the San Francisco Public Utilities Commission-Alameda Siphon Project No. 4, in Alameda County, California (the “Project”). Joint Statement of Undisputed Facts (“JSUF”), ECF No. 71-2 at 2.
To perform its work as a tunneling subcontractor on the Project, Nada leased an MTBM from third-party defendant, Ak-kerman, Inc. (“Akkerman”). Id. Because the leased MTBM had a 74" diameter and the Project required a 96" diameter, Nada separately leased an “increase kit” from non-party Walter C. Smith Co., Inc. to enlarge the diameter of the face of the MTBM to the required project dimensions. Id. at 2-3. Nada also installed on the leased MTBM a “cutter head” that Nada owned. Id. at 3. The cutter head is the front-most piece of an MTBM, which rotates to bore through the ground. Id.
II. THE MTBM’S IMMOBILAZATION, RESCUE, AND INVESTIGATION
In September of 2010, while Nada was operating the MTBM to bore a tunnel on the Project, the MTBM became immobilized underground. Id. The immobilization occurred roughly 254 feet into tunnel bore, and 12 lengths of 20-foot interconnected steel casing pipe had been installed behind the MTBM when it became immobilized. Id. With Nada unable to advance the MTBM forward or move it backwards because of the pipe sections that had been installed behind the MTBM, a rescue shaft (or “911 shaft”) was constructed above the MTBM to expose it and then raise it out of the ground with a crane. Id. at 3-4.
After the MTBM was removed from the ground, it was sent to Nada’s facility in Caruthers, California for examination and repair. Id. at 4. Upon examination, Nada discovered that the gearbox within the MTBM was cracked. Id. Nada subsequently obtained a replacement gearbox, performed other repairs to the MTBM, returned the MTBM to the site, lowered it into the tunnel bore alignment, restored the earthen cover removed to create the 911 shaft, and re-launched the MTBM on the Project, which Nada was then able to complete. Id.
The failed gearbox was sent to PEM’s facility where a non-destructive inspection was performed on or about November 16, 2010. Id. The Besser-manufactured planetary carrier within the gearbox then was sent to the University of Northern Iowa (“UNI”) in Cedar Falls, Iowa, where it underwent destructive testing on or about February 28, 2011 at PEM’s request. Id. Based on that destructive testing, UNI prepared a report dated March 31, 2011. Id. Structural Integrity Associates, Inc. then prepared a report dated April 12, 2011, which analyzed the UNI report. Id. Both reports were available to Nada prior to the Dispute Review Board proceeding discussed below. Id.
III. NADA’S REQUEST FOR CHANGE ORDER
In connection with the costs Nada incurred to rescue and repair the immobilized MTBM, Nada submitted a Request for Change Order to Rados on September 6, 2011 and Rados passed that Request for Change on to the SFPUC. Id. Nada’s Request for Change sought compensation for additional costs as follows:
[[Image here]]
IV. THE DISPUTE REVIEW BOARD PROCEEDINGS
After the SFPUC refused to execute a change order on Nada’s Request for Change, the SFPUC, Rados, and Nada, in accordance with the prime contract between the SFPUC and Rados, submitted the dispute to a Dispute Review Board (“DRB”). Id. The DRB, which was established by the prime contract between the SFPUC and Rados and whose purpose was “to assist the parties by facilitating the timely resolution of disputes relating to” work on the Project, consisted of one member selected by the SFPUC, one member selected by Rados, and a third member selected by the other two members. Id., Ex. G (“DRB Specification”), ECF No. 71-9 ¶¶1.1, 2-3. Each DRB member was required to hold a certification or pre-qualification from the Dispute Resolution Board Foundation or the American Arbitration Association evidencing that the member received training the DRB process and meets the requirements for DRB members. Id. ¶ 3.2.
The DRB review process proceeds as follows. Either party to the prime contract could initiate the DRB’s review of a dispute. Id. 117.2. The DRB then sets deadlines for the parties to provide pre-hearing submittals, which are position papers supported by evidence, and for a hearing. Id. ¶ 7.3, 7.4. The pre-hearing submittal contains a brief statement of the dispute, a summary of the party’s position and the basis and justification for that position (with reference to contractual language and other evidence), and cost details. Id. ¶ 7.4.
The DRB then conducts a formal hearing that is attended by the parties. Id. ¶ 2.2. Attorneys are not allowed to attend the DRB hearing without prior written approval, and if they are granted such approved, they may only observe. Id. ¶ 8.4. The party who referred the dispute to the DRB presents, its position first, followed by the other party. Id. ¶8.5. Both parties are then allowed successive rebuttals until the DRB believes that all aspects of the dispute have been fully and fairly covered. Id. The DRB members may ask questions, request clarification, or ask for additional information. Id. Either party may request that the DRB direct a question to, or request a clarification from, the other party, although the DRB will not allow one party to be directly questioned by the other party. Id. The DRB, in its sole discretion, may allow the introduction of arguments, exhibits, handouts, or documentary evidence that were not included in a party’s pre-hearing submittal or were not previously given to the other party. Id. In the latter circumstance, the other party is given time to review the new material and prepare a rebuttal. Id. With prior disclosure, a party may also offer an analysis of an outside expert. Id. ¶¶ 8.8, 8.9. In difficult or complex cases, the DRB may find an additional hearing to be necessary. Id. at ¶ 8.5.
After the formal hearing, the DRB issues a nonbinding, written recommendation (the “DRB Report”), which is admissible in subsequent litigation or other dispute resolution proceedings. Id. ¶ 2.5. The recommendation in the DRB Report is based on the pertinent contractual provisions, applicable laws and regulations, and facts and circumstances of the dispute. Id. ¶ 9.1. It includes an explanation of the DRB’s reasoning in reaching the recommendation. Id. The recommendation must be consistent with the application provisions of the prime contract between the SFPUC and Rados. Id. Within 10 days of receiving the DRB Report, either party may request clarification or reconsideration. Id. ¶¶ 9.5, 9.6. Within 30 days of receiving the DRB Report, the parties must submit their writ
In accordance with the procedures outlined above, the parties submitted a factual record of “Common Reference Documents” relevant to the Project and the MTBM’s immobilization. JSUF, ECF No. 71-2 at 5. On November 14, 2011, Nada submitted a Pre-Hearing Submittal to the DRB, executed by Nada’s president, Cal Terassas, explaining Nada’s position as to the cause of the MTBM’s immobilization (essentially, site conditions). Id. Nada also provided an Appendix of separate documents to the DRB. Id. Among other analyses and reports provided in the Appendix, Nada provided the DRB with expert reports authored by David Mathy and David Bennett, “two very respected industry professionals who devote their careers to geotechnical issues and most substantively to microtunnelling.” Id. Nada also created PowerPoint presentations that it submitted to the DRB on November 28, 2011 and in rebuttal on December 1, 2011, after the DRB’s hearing. Id. at 6.
The DRB conducted a hearing on November 29, 2011 and issued its recommendation on January 6, 2012. Id. The DRB’s decision made recommendations concerning Nada’s entitlement to the costs requested in Nada’s Request for Change. Id.
V. THE SETTLEMENT OF THE CHANGE ORDER DISPUTE
As a result of the DRB’s January 6, 2012 recommendation, the SFPUC agreed to pay Rados the sum of $850,000. JSUF, ECF No. 71-2 at 6. Rados then agreed to pay Nada $481,755.49 ($850,000 less deductions for a $350,000 Rados back charge and $18,244.51 in DRB charges). Id. Nada’s final progress billing to Rados reflects a line item credit of $850,000 to Nada and debits for the Rados back charge and DRB costs for net billing of $481,755.49 and a net balance due under the Nada-Rados subcontract of $847,383.74. Id. Rados paid Nada the $847,383.74 outstanding on the subcontract by check dated July 10, 2012. Id. The $850,000 credit (and net payment of $481,755.49) that Nada received from Rados compensated Nada for no costs other than the costs categorized as items A-F on the chart shown above. Id.
Nada has no obligation — existing, inchoate, contingent, or otherwise — to repay either Rados or the SFPUC for the $850,000 credit or $481,755.49 net payment that Nada received in settlement of its Request for Change. Id. Nada did not purchase insurance or pay insurance premiums to either Rados or the SFPUC in exchange for the credit and payment it received in settlement of its Request for Change. Id. at 6-7.
VI. THE DAMAGES NADA SEEKS IN THIS LITIGATION
In this litigation, Nada seeks to recover the following categories of costs in the amounts shown below:
[[Image here]]
Id. at 7. The categories and amounts of costs listed in items A-F of Nada’s damages disclosures are identical to the categories and amounts of costs listed in items A-F of Nada’s Request for Change as-summarized in the previous chart, except that Nada deducted from item C of Nada’s damage disclosures costs that Nada incurred for cutter head repairs and deducted from item F additional costs that Nada incurred after the MTBM had been relaunched. Id. ■
VII. NADA’S CLAIMED PROPERTY DAMAGE
For purposes of California’s economic loss rule, Nada claims that it suffered four items of damage to property other than the MTBM as a result of the MTBM’s immobilization:
First, Nada claims that it suffered damage to the cutter head in that the MTBM’s immobilization caused the cutter head to be “effectively ‘lost’ underground unless and until the MTBM could be rescued.” Id. at 7-8.
Second, Nada claims that it suffered damage to the pipe lengths installed in the tunnel at the time the MBTM failed in that the MTBM’s immobilization caused the pipe lengths to be “effectively ‘lost’ underground unless and until the MTBM could be rescued since they could not be used for their intended purpose (or any purpose).” Id. at 8.
Third, Nada claims that it suffered damage to its “license to use the property of SFPUC” in that “Nada was unable to use its contractual license to use the real property owned by SFPUC unless and until the MTBM could be rescued, and Nada had a contractual duty to promptly remedy and/or repair the immobilized MTBM’s interference with the tunnel profile.” Id.
Fourth, and finally, Nada claims that it suffered damage to its “lease obligations to Walter C. Smith and Akkerman” in that “when the MTBM became immobilized due to a gear box failure, the MTBM that Nada had leased from Akkerman, and the increase kit. that Nada had leased from Walter C. Smith, were effectively ‘lost’ un
Nada claims no other elements of damage to “other property” within the meaning of California’s economic loss rule. Id.
VIII. PROCEDURAL HISTORY
Nada filed its original complaint, which named only Besser as a defendant, on September 18, 2013. Nada Original Complaint, ECF No. 1. On October 4, 2013, Nada filed its First Amended Complaint, which added PEM as a defendant. Nada Complaint, ECF No. 6. Against Besser, Nada brings claims for strict liability based on a manufacturing defect, negligence in the context of products liability, equitable indemnity, fraud, and negligent misrepresentation. See id. ¶¶ 43-87.
On September 11, 2014, Besser filed the instant motion for summary judgment. Motion, ECF No. 71. Nada filed an opposition on September 25, 2014, and Besser filed a reply on October 2, 2014. Opposition, ECF No. 84; Reply, ECF No. 89. The court held a hearing on the matter on November 6, 2014. 11/6/14 Minute Order, ECF No. 100.
ANALYSIS
I. THE SUMMARY JUDGMENT LEGAL STANDARD
The court must grant a motion for summary judgment if the movant shows that there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a); Anderson v. Liberty Lobby, Inc.,
The party moving for summary judgment bears the initial burden of informing the court of the basis for the motion, and identifying portions of the pleadings, depositions, answers to interrogatories, admissions, or affidavits which demonstrate the absence of a triable issue of material fact. Celotex Corp. v. Catrett,
If the moving party meets its initial burden, the burden shifts to the non-moving party to produce evidence supporting its claims or defenses. Nissan Fire & Marine Ins. Co., Ltd.,
In ruling on a motion for summary judgment, inferences drawn from the underlying facts are viewed in the light most
II. JUDICIAL ESTOPPEL
Besser first argues that Nada should be judicially estopped from asserting any of its claims against Besser because its factual allegations and theory of recovery in this action contradict the factual allegations and theory of recovery that it presented to the DRB and which led to a settlement in its favor. See Motion, ECF No. 71 at 7, 9-16. If Nada is estopped from asserting its current theory, then it will not be able to prove that the cast iron planetary carrier manufactured by Besser caused the harm for which it seeks relief, and therefore its claims against Besser necessarily fail. See id. at 7,16.
Federal law on judicial estoppel governs cases in federal courts regardless of whether they involve state law claims. Johnson v. Oregon Dep’t of Human Res. Rehab. Div.,
Judicial estoppel may be invoked by the court at its discretion. Morris v. California,
But before the court applies these (and other) factors, it must determine whether judicial estoppel can be applied when the allegedly inconsistent position was taken before the DRB. The Ninth Circuit has made clear that the doctrine of judicial estoppel applies not only where prior inconsistent statements were made to a court, but also where those statements were made in an administrative proceeding. See Rissetto,
Besser cites many of these opinions and argues that the DMB proceeding likewise is a “quasi-judicial” proceeding such that judicial estoppel may be applied. See Reply, ECF No. 89 at 8-9. The court disagrees. It is true that the DRB proceeding had many of the hallmarks of a judicial or quasi-judicial-proceeding: it was adversarial; the parties submitted briefs making arguments and citing to evidence; the parties could respond to each other’s arguments; the parties could submit the opinions of experts; etc. But it lacked the most important hallmark — the
The DRB had no such power. Instead, it was empowered “to assist the parties by facilitating the timely resolution of disputes” and was limited to issuing a nonbinding (albeit written) recommendation that the SFPUC, Rados, and Nada could accept or reject. DRB Specification, ECF No. 71-9 ¶¶ 1.1, 2.5, 9.7. The DRB Specification itself even recognized that possibility that the DRB process might not result in a resolution of the dispute. Id. ¶ 10.1. If the DRB process itself might not result in a resolution of the dispute, it certainly cannot be considered to have adjudicated it. Besser cites no authority holding, or even suggesting, that the doctrine of judicial estoppel may be applied in the context of a body with no power to make a decision that is binding on the parties before it. Without it, and after considering the authority on this issue, the court will not judicially estop Nada from asserting its claims against Besser.
Besser next argues that Nada’s potential recovery must be offset by the money is received from the settlement with the SFPUC and Rados. See Motion, ECF No. 71 at 16-20. Besser asserts that because Nada (according to Nada’s own calculations) received $680,627.07 from Rados (which received the payment from SFPUC), it is limited to recovering $688,927.70 from Besser in this action. See Reply, ECF No. 89 at ll.
Normally, a plaintiff is “entitled to no more than a single recovery for each distinct item of compensable damages supported by the evidence,” “[r]egardless of the nature and number of legal theories advanced by the plaintiff.” Tavaglione v. Billings,
In Helfend, the plaintiff was injured by a tortfeasor during an automobile collision. Id. at 4,
The superior court rejected the tortfea-sor’s argument, and the California Supreme Court affirmed that decision. Id. at 14,
The collateral source rule expresses a policy judgment in favor of encouraging citizens to purchase and maintain insurance for personal injuries and for other eventualities. Courts consider insurance a form of investment, the benefits of which become payable without respect to any other possible source of funds. If we were to permit a tortfeasor to mitigate damages with payments from plaintiff’s insurance, plaintiff would be in a position inferior to that of having bought no insurance, because his payment of premiums would have earned no benefit. Defendant should not be able to avoid payment of full compensation for the injury inflicted merely because the victim has had the foresight to provide himself with insurance.
Id. For these reasons, the Court “reaffirm[ed] our adherence to the collateral source rule in tort eases in which the plaintiff has been compensated by an independent collateral source — such as insurance, pension, continued wages, or disability payments — for which he had actually or constructively ... paid or in cases in which the collateral source would be recompensed from the tort recovery through subrogation, refund of benefits, or some other arrangement.” Id. at 13-14,
Besser rightly points out that this case has none of the characteristics of the cases in which the collateral source rule has been applied. “While commonly applied to exclude evidence of insurance payments, over the years, a variety of benefits provided to plaintiffs have been held to be collateral sources of compensation that should not be considered in mitigation of a plaintiff s damages.” Smock v. State,
For its part, Nada cites no authority holding or even suggesting that the collateral source rule should be applied in the circumstances present here. Instead, it
It also tries to analogize this case to Helfend by arguing that the SFPUC and Rados cannot be considered “other tortfea-sors” for purposes of the collateral source rule and were “wholly independent” from Besser (the alleged tortfeasor) because SFPUC and Rados had to pay Nada Pacific pursuant to California Public Contracts Code § 7104. That statute provides:
Any public works contract of a local public entity which involves digging trenches or other excavations that extend deeper than four feet below the surface shall contain a clause which provides the following:
(a)' That the contractor shall promptly, and before the following conditions are disturbed, notify the local public entity, in writing, of any:
(1) Material that the contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
(2) Subsurface or latent physical conditions at the site differing from those indicated by information about the site made available to bidders pri- or to the deadline for submitting bids.
(3) Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract.
(b) That the local public entity shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in the contractor’s cost of, or the time required for, performance of any part of the work shall issue a change order under the procedures described in the contract.
(c) That, in the event that a dispute arises between the local public entity and the contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor’s cost of, or time required for, performance of any part of the work, the contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. The contractor shall retain any and all rightsprovided either by contract. or by law which pertain to the resolution of disputes and protests between the contracting parties.
Cal. Pub. Contracts Code § 7104. In other words, Nada Pacific received money from the SFPUC and Rados under statutory/contract theory, not a tort theory.
Even so, the larger point is that the facts of this simply are different from the situations where courts have applied the collateral source rule. Nada, was not “compensated by an independent collateral source — such as insurance, pension, continued wages, or disability payments — for which he had actually or constructively ... paid,” and the SFPUC will not be “recompensed from the tort recovery through subrogation, refund of benefits, or some other arrangement.” Helfend,
Accordingly, the court finds that Nada is limited to recovering $688,927.70 from Besser in this action.
IV. ECONOMIC LOSS RULE
Finally, Besser argues that California’s so-called “economic loss rule” bars the tort claims that Nada brings against it. See Motion, ECF No. 71 at 20-23.
In California, “[t]he economic loss rule requires a purchaser to recover in contract for purely economic loss due to disappointed expectations, unless he can demonstrate harm above and beyond a broken contractual promise.” Robinson Helicopter Co., Inc. v. Dana Corp.,
Nada asserts only tort claims against Besser, and through this action it seeks only economic damages that cannot be recovered through them. It is undisputed that the damages to “other property” that Nada seeks are based on its inability to use the MTBM’s cutter head, the pipe lengths installed in the tunnel behind the MTBM, its “license to use the property of SFPUC,” and its “lease obligations to Walter C. Smith and Akkerman” while the MTBM was stuck underground. Nada cites several opinions that make clear that,
With the exception of W./Scott Fetzer, Nada ignores the authorities cited by Besser. See Opposition, ECF No. 84 at 22-29. As for W./Scott Fetzer, Nada says that the escaped oxygen at issue there was gone forever, while here it contends that the “other property” was “physically restrained and/or blocked.” Id. at 23. The court fails to see a meaningful distinction; in both instances, the “other property” was made unusable.
Nada also cites Catalyst Old River Hydroelectric Ltd. P’ship v. Ingram Barge Co.,
In addition, Nada cites Shade Foods, Inc. v. Innovative Prods. Sales & Mktg., Inc.,
Finally, Nada argues that, even if the economic loss rale bars its claims against Besser for strict liability, negligence, equitable indemnity, and negligent misrepresentation, it does not bar its claim for fraud. Opposition, ECF No. 84 at 22. Nada makes this argument in a single sentence in its opposition, stating that “the courts have held that the economic loss rule does not bar fraud and intentional misrepresentation claims.” Id. (citing Robinson,
When the plaintiff found out what happened, it sued the defendant for breach of contract, breach of warranty, and negligent and intentional misrepresentation. Id. at 987,
...' By issuing false certificates of conformance, [the defendant] unquestionably made affirmative representations that [the plaintiff] justifiably relied on to its detriment. But for [the defendant’s] affirmative misrepresentations by supplying the false certificates of conformance, [the plaintiff] would not have accepted delivery and used the nonconforming clutches over the course of several years, nor would it have incurred the cost of investigating the cause of the faulty clutches. Accordingly, [the defendant’s] tortious conduct was separate from the breach itself, which involved [the defendant’s] provision of the nonconforming clutches. In addition, [the defendant’s] provision of faulty clutches exposed [the plaintiff] to liability for personal damages if a helicopter crashed and to disciplinary action by the FAA. Thus, [the defendant’s] fraud is a tort independent of the breach. (Erlich v. Menezes, supra, 21 Cal.4th [543] at pp. 553-554,87 Cal.Rptr.2d 886 ,981 P.2d 978 [ (1999) ].)
We hold the economic loss rule does not bar [the plaintiffs] fraud and intentional misrepresentation claims because they were independent of [the defendant’s] breach of contract. (See Erlich v. Menezes, supra, 21 Cal.4th at pp. 552-554,87 Cal.Rptr.2d 886 ,981 P.2d 978 .)
Id. (footnote omitted). In a footnote accompanying its holding, the Court further explained that
... [i]n contrast [to cases dealing with the economic loss rule in products liability or negligence contexts], [the plaintiffs] claims are based on [the defendant’s] intentional and affirmative misrepresentations that risked physical harm to persons. [The plaintiffs] helicopters are flown by and carry people. A properly functioning sprag clutch is vital to the safe performance of the aircraft, and compliance with the certificate requirement is part of an integrated regulatory scheme intended to ensure their safe operation. The economic loss rule is designed to limit liability in commercial activities that negligently or inadvertently go awry, not to reward malefactors who affirmatively misrepresent and put people at risk.
Id. at n. 7. Careful not to extend the economic loss rule too far, the Court went on to make clear that its holding “is narrow in scope and limited to a defendant’s affirmative misrepresentations on which a plaintiff relies and which expose a plaintiff to liability for personal damages independent of the plaintiffs economic loss.” Id. at 993,
Accordingly, the court concludes that the economic loss rule applies and bars Nada’s tort claims against Besser.
CONCLUSION
Based on the foregoing, the court GRANTS Besser’s motion for summary judgment.
IT IS SO ORDERED.
Notes
. Citations are to the Electronic Case File with pin cites to the electronically generated gage numbers at the top of the page.
. A party may assert the doctrine of judicial estoppel in a motion for summary judgment to bar a claim based on an inconsistent position. See Elston v. Westport Ins. Co.,
. Although there does not appear to be an opinion holding that judicial estoppel applies only to instances where the prior, allegedly inconsistent position was taken before a quasi-judicial body that has decision-making authority, opinions in other contexts certainly suggest that the ability to make a decision is critical to determining whether that body is acting in quasi-judicial capacity. See United States v. MacDonald,
. Because the court finds that the doctrine of judicial estoppel does not apply in this context, the court has no occasion to address the parties’ arguments about whether the judicial estoppel factors support its exercise here.
. In its motion, Besser argued that, because the SFPUC paid $850,000 to Rados (which in turn paid $481,755.49 to Nada because Rados deducted $350,000 for a back charge and $18,244.51 in DRB charges), Nada’s recovery in this action must be offset by $850,000 and thus was limited to $519,554.77. See Motion, ECF No. 71 at 17, 19-20. In its opposition, Nada argued that the amount of any offset was disputed issue of material fact and stated that not all of the $850,000 was duplicative of amounts it claims in this action. See Opposi-lion, ECF No. 84 at 21. It further stated that only $680,627.07 of the $850,000 was received for damages that Nada also claims in this action, leaving a potential recovery of at least $688,927.70. See id. at 22. In its reply, to avoid the disputed issue of material fact, Besser adopted Nada’s calculations and argued that Nada’s recovery in this action is limited to $688,927.70. See Reply, ECF No. 89 at 11. Neither party mentioned this issue at the hearing.
. Nada also cites Tasion Comm’cns, Inc. v. Ubiquiti Networks, Inc., No. C-13-1803 EMC,
