Lead Opinion
Opinion for the Court filed by Circuit Judge KAVANAUGH, with whom Circuit Judge GRIFFITH joins.
Opinion concurring in the judgment filed by Circuit Judge HENDERSON.
Petitioners are champing at the bit to challenge EPA’s anticipated rule restricting carbon dioxide emissions from existing power plants. But EPA has not yet issued a final rule. It has issued only a proposed rule. Petitioners nonetheless ask the Court to jump into the fray now. They want us to do something that they candidly acknowledge we have never done before: review the legality of a proposed rule. But
* * *
On June 18, 2014, as part of the Executive Branch’s efforts to tackle global warming, EPA proposed a rule to restrict carbon dioxide emissions from existing coal-fired and natural gas-fired power plants. See 79 Fed.Reg. 34,830, 34,830 (June 18, 2014). In the preamble to the proposed rule and in other statements about the proposed rule, EPA has that Section 111(d) of the Clean Air Act supplies legal authority for EPA to restrict those emissions. See, e.g., id. at 34,852-53; see also 42 U.S.C. § 7411(d) (codifying Section 111(d) of the Clean Air Act).
EPA published the proposed rule in the Federal Register and invited “further input through public comment on all aspects of this proposal.” Id. at 34,835. The period has now closed, and EPA has received over two million comments. EPA has not yet issued a final rule but intends to do so this summer.
Petitioners here are Murray Energy Corporation, which is a coal company whose business would be negatively affected by a restriction on carbon dioxide emissions from coal-fired power plants, and the States of West Virginia, Alabama, Indiana, Kansas, Kentucky, Louisiana, Nebraska, Ohio, Oklahoma, South Carolina, South Dakota, and Wyoming. Shortly after EPA issued its proposed rule, petitioners filed suit. According to petitioners, Section 111(d) of the Clean Air Act does not grant EPA authority to limit carbon dioxide emissions from existing power plants. For (i) that reason, petitioners ask the Court to enjoin EPA from issuing a final rule limiting those carbon dioxide emissions.
In effect, petitioners are asking us to review the legality of a proposed EPA rule so as to prevent EPA from issuing a final rule. But as this Court has stated, a proposed EPA rule “is not final agency action subject to judicial review.” Las Brisas Energy Center, LLC v. EPA, No. 12-1248,
Proposed rules meet neither of the two requirements for final agency action: (i) They are not the “consummation of the agency’s decisionmaking process,” and (ii) they do not determine “rights or obligations,” or impose “legal consequences.” Bennett v. Spear,
In an attempt to clear this hurdle to their suit, petitioners advance three different arguments. None is persuasive.
First, petitioners contend that this Court has authority under the All Writs Act to consider their challenge now, even before EPA issues a final rule. The All Writs Act provides that “all courts established by Act of Congress may issue all writs necessary or appropriate in aid of their respective jurisdictions and agreeable to the usages and principles of law.” 28 U.S.C. § 1651(a). Although “the All Writs Act authorizes employment of extraordinary writs, it confines the authority to the issuance” of writs “in aid of the issuing court’s jurisdiction.” In re Tennant,
In this case, a writ is not necessary or appropriate to aid the Court’s jurisdiction. After EPA issues a final rule, parties with standing will be able to challenge that rule in a pre-enforcement suit, as well as to seek a stay of the rule pending judicial review. At that time (which will not be very long from now, according to EPA), the Court will have an opportunity to review the legality of the rule.
Petitioners contend, however, that we should consider their challenge now because they are already incurring costs in preparing for the anticipated final rule. And petitioners say that the Court will not be able to fully remedy that injury if we do not hear the case at this time. But courts have never reviewed proposed rules, notwithstanding the costs that parties may routinely incur in preparing for anticipated final rules. We recognize that prudent organizations and individuals may alter their behavior (and thereby incur costs) based on what they think is likely to come in the form of new regulations. But that reality has never been a justification for allowing courts to review proposed agency rules. We see no persuasive reason to blaze a new trail here.
In short, the All Writs Act does not authorize a court to circumvent bedrock finality principles in order to review proposed agency rules. See Pennsylvania Bureau of Correction v. U.S. Marshals Service,
Second, petitioners argue that EPA’s public statements about its legal authority to regulate carbon dioxide emissions constitute final agency action subject to judicial review. As petitioners correctly note, EPA has repeatedly and unequivocally asserted that it has authority under Section 111(d) to restrict carbon dioxide emissions from existing power plants. EPA has made such statements in the preamble to the proposed rule, in a legal memorandum accompanying the proposed rule, and in other public remarks discussing the proposed rule. See, e.g.,
But those EPA statements are not final agency action. As noted above, to be final an agency action must meet two requirements. First, the agency action must constitute “the consummation of the agency’s decisionmaking process.” Bennett, 520
Here, neither of those standard finality requirements is met.
In the context of an ongoing rulemaking, an agency’s statement about its legal authority to adopt a proposed rule is not the “consummation” of the agency’s decision-making process. Formally speaking, such a statement is a proposed view of the law. Indeed, EPA recognized as much in this instance when it asked for “further input through public comment on all aspects” of the agency’s proposal. 79 Fed.Reg. at 34,-835 (emphasis added). Put simply, the consummation of the agency’s decision-making process with respect to a rule occurs when the agency issues the rule.
Moreover, even if EPA’s position on its legal authority is set in stone, the agency’s statements about its legal authority — unconnected to any final rule or other final agency action — do not impose any legal obligations or prohibitions on petitioners. Any such legal obligations or prohibitions will be established, and any legal consequences for violating those obligations or prohibitions will be imposed, only after EPA finalizes a rule.
In short, EPA’s statements about its legal authority under Section 111(d) meet neither of the requirements for final agency action.
Third, no doubt recognizing the problems with their attempt to challenge a proposed rule (including the lack of precedent supporting judicial review of a proposed rule), the State petitioners separately challenge a 2011 settlement agreement that EPA reached with several other States and environmental groups. By challenging that settlement agreement, the State petitioners hope to obtain a backdoor ruling from the Court that EPA lacks legal authority under Section 111(d) to regulate carbon dioxide emissions from existing power plants. But the settlement agreement did not obligate EPA to issue a final rule restricting carbon dioxide emissions from existing power plants. It simply set a timeline for EPA to decide whether to do so. As our precedent makes clear, a settlement agreement that does nothing more than set a timeline for agency action, without dictating the content of that action, does not impose an injury in fact on entities that are not parties to the settlement agreement. See Defenders of Wildlife v. Perciasepe,
* * *
We deny the petitions for review and the petition for a writ of prohibition.
So ordered.
Concurrence Opinion
concurring in the judgment:
I agree that the petitioners in No. 14-1146 do not have standing to challenge the settlement agreement. I also agree that we do not have jurisdiction to hear the petition for review in No. 14-1151 because the proposed rule that the petitioners challenge is non-final agency action. And while I too would deny the application for a writ of prohibition in No. 14-1112, I
The All Writs Act gives this Court the power to issue “all writs necessary or appropriate in aid of [its] respective jurisdiction[] and agreeable to the usages and principles of law.” 28 U.S.C. § 1651(a). The Act confines the power to grant writs “to the issuance of process ‘in aid of the issuing court’s jurisdiction. The Act does not enlarge that jurisdiction.” In re Tennant,
We have jurisdiction here to issue a -writ of prohibition. The EPA initiated a rule-making by publishing a proposed rule. See generally 79 Fed.Reg. 34,830 (June 18, 2014). This proceeding will result in a final rule that may be challenged on direct review in this Court. See id. at 34,838 (“[T]he EPA expects to finalize this rule-making by June 1, 2015.”); 42 U.S.C. § 7607(b)(1) (“A petition for review of ... any standard of performance or requirement under section 7411 of this title ... may be filed only in the United States Court of Appeals for the District of Columbia.” (footnote omitted)). Consequently, because this Court “would have authority to review the agency’s final decision,” we have authority to issue a writ of prohibition in the interim. Tennant,
We retain jurisdiction to issue writs despite the Clean Air Act’s limitation on judicial review. See 42 U.S.C. § 7607(e). “The All Writs Act invests a court with a power essentially equitable.” Clinton v. Goldsmith,
The Clean Air Act provides that “[n]othing in this chapter shall be construed to
Moreover, we noted in Ganem that the Congress “knows how to withdraw a particular remedy,” such as the right to a writ of prohibition, when it wants to do so.
Nevertheless, simply because we have jurisdiction to grant a writ of prohibition
(1) the mandamus petitioner must have no other adequate means to attain the relief he desires, (2) the mandamus petitioner must show that his right to the issuance of the writ is clear and indisputable, and (3) the court, in the exercise of its discretion, must be satisfied that the writ is appropriate under the circumstances.
In re Kellogg Brown & Root, Inc.,
The third factor in the three-part test evaluates whether a writ is appropriate given the circumstances of the case. This factor is grounded in equitable principles: “The common-law writs, like equitable remedies, may be granted or withheld in the sound discretion of the court.” Roche v. Evaporated Milk Ass’n,
Granting the writ would be inappropriate in this instance because the EPA has represented that it will promulgate a final rule before this opinion issues. In the proposed rule, the EPA stated that it “expects to finalize this rulemaking by June 1, 2015” due to “the urgent need for actions to reduce [greenhouse gas] emissions.” 79 Fed.Reg. at 34,838. Counsel for the EPA at oral argument again stated that the proposed rule “might not be [promulgated in] June” but “will be [promulgated] this summer.” Oral Arg. Tr. 77-78. Thus, by the time the majority opinion and this concurrence issue — or shortly thereafter— the petitioners will have a final rule that can be challenged as final agency action in this Court. See Ass’n of Irritated Residents v. EPA, 494 F.3d 1027, 1030 (D.C.Cir.2007) (“final agency actions[ ] includ[e] an agency’s promulgation of a rule”). Assuming at least one petitioner has standing, we will then adjudicate the same questions raised here. Keeping in mind that the common law writs are “drastic and extraordinary remedies] reserved for really extraordinary causes,” Cheney v. U.S. Dist. Court for the Dist. of Columbia, 542 U.S. 367, 380,
The petitioners believe that a writ of prohibition is appropriate because waiting to challenge the final rule is inconvenient and costly. But that alone does not justify an extraordinary remedy. See Nat’l Right to Work Legal Defense v. Richey,
In sum, although we have the authority to issue a writ of prohibition, I would decline to do so because the passage of time has rendered the issuance all but academic.
Notes
. The following is a non-exhaustive list of statutes that take away the court’s authority. 5 U.S.C. § 8128(b)(2) (“The action of the Secretary [of Labor] or his designee ... is not subject to review by another official of the United States or by a court by mandamus or otherwise.”); 8 U.S.C. § 1252(a)(2)(A) ("[Notwithstanding any other provision of law (statutory or nonstatutory) ... or ... [the All Writs Act], no court shall have jurisdiction to review” various immigration orders); 38 U.S.C. § 511(a) (”[T]he decision of the Secretary [of Veterans Affairs] .,. shall be final and conclusive and may not be reviewed by any other official or by any court, whether by an action in the nature of mandamus or otherwise.”); 42 U.S.C. § 1715 (“The action of the Secretary [of Labor] ... shall be final and conclusive on all questions of law and fact and not subject to review by any other official of the United States or by any court by mandamus or otherwise"). We have assumed that extraordinary relief is available vis-á-vis the EPA in a number of unpublished dispositions. See New York v. EPA, No. 02-1387 et al.,
