185 Pa. 250 | Pa. | 1898
Opinion by
The contract between the parties to this litigation was executed on August 9, 1894, and it called for the erection and completion of the building provided for therein, on January 1, 1895. It contained a stipulation to the effect that, for each day subsequent to the last mentioned date, and before the completion of the building, there should be deducted from the contract price twenty-five dollars. The plaintiffs’ contention is that the building was finished in accordance with the contract early in May, 1895, while the defendants contend that it was not completed until some time in June of that year. The character of the work done and materials furnished by the plaintiffs in and about the erection and construction of the building is not complained of. The material dispute between the parties relates to and arises from the failure of the plaintiffs to complete the building within the time stipulated in the contract. The plaintiffs allege that the delay in the completion of the building
The plaintiffs’ showing of the causes of the delay in the completion of the building was not fully met or answered by the evidence presented by the defendants. They alleged, however, and introduced evidence to show that the plaintiffs’ claim as to the time of the completion of the building was incorrect. On this point there was a difference between the parties of a month or more. Remington testified that when he came to Pittsburg
Upon the whole evidence in the case the single question presented for the determination of the jury was whether the delay in the completion of the building was caused by the acts and orders of the defendants or their agents. If it was, the plaintiffs were entitled to the balance of the contract price. If it was not, and all or any part of the delay was attributable to the plaintiffs, there should be a deduction of twenty-five dollars for each day covered by or included in it. The question was submitted by the court in a charge that was impartial and free from error, and the jury found that the plaintiffs were not in default.
We do not find in the admission of exhibit No. 3 any warrant for the reversal of the judgment, nor any reasonable ground for the contention that the defendants were injured by it. The undisputed evidence was that it was not a final certificate, and the jury were plainly instructed that, for any delay for which the plaintiffs were responsible, there should be a deduction from the balance appearing thereon, in accordance with the terms of the contract.
We cannot sustain the defendants’ contention that the dis
All of the assignments are overruled.
Judgment affirmed.