Munroe v. Sedro Lumber & Shingle Co.

16 Wash. 694 | Wash. | 1897

The opinion of the court was delivered by

Scott, C. J.

The appellants brought suit against Kirby, Hightower & Co. to recover on two notes, and caused a writ of garnishment to be issued and served on the receiver for the Sedro Lumber & Shingle Company. Said last company had been engaged in the manufacture of shingles from shingle bolts furnished it by Kirby, Hightower & Co. The shingles on hand were converted into money and the court found that Kirby, Hightower & Co. were entitled to receive $794.26 thereof. A large number of laborers for Kirby, Hightower & Co., who had performed labor in getting out the shingle bolts, sought to enforce liens against the shingles, and the court found that they were entitled to liens, the amount thereof being largely in excess of the amount aforesaid awarded to Kirby, Hightower & Co., and the court found that the laborers were entitled to such proceeds, to be paid to them upon their claims pro rata.

*696One of the contentions upon the part of the appellants is that such laborers were not entitled to any lien against the shingles; that at most they could only enforce a lien against the shingle bolts while in the possession of Kirby, Hightower & Co., under the statute, Laws 1893, p. 428, § 2. But whatever the law may be generally, under this statute, where possession of such property has been transferred, we are ‘of the opinion that the rule contended for ought not to apply in this case, for these shingle bolts were being manufactured by Kirby, Hightower & Co. for the Sedro Lumber & Shingle Company under an existing contract whereby Kirby, Hightower & Co. were to furnish to the Sedro Lumber & Shingle Company shingle blocks sufficient from which to manufacture shingles at the rate of 140,000 a day for twenty-two days in each month at a stated price. The contract provided that the Sedro Lumber & Shingle Company should cut said blocks into shingles at the rate of 140,000 a day for twenty-two days in each month during the continuance of the contract, and should pay to Kirby, Hightower & Co. on the 5th day of each month the amount due on all shingles shipped the previous month, manufactured from said shingle blocks. The contract also seemed to contemplate a division of certain of the shingles between said parties, and it does not appear from the findings just what shingles the particular moneys, the court found Kirby, Hightower & Co. were entitled to under the contract, were the proceeds of. But, independent of this, and conceding that the shingles belonged to the Sedro Lumber & Shingle Co., in view of the existing contract, we are of the opinion that the laborers who got out the shingle blocks, although under the employment of Kirby, Hightower & Co., could enforce a lien *697against the shingles while the same were at the mill where they were manufactured, as these were, and were also under the control of the manufacturer or its receiver.

It also appears that certain of the laborers aforesaid served a notice under § 3124, Gen. Stat., of their claims for labor performed, within sixty days prior to said garnishment, and one of the points the appellants seek to raise is that this statute will not allow the payment of such claims in cases of garnishment, as it cannot be considered a writ of a similar nature to an execution or an attachment. A number of the respondents appear here by one firm of attorneys, and certain of them by other attorneys, and they have filed separate briefs. One of them contends that this point is not raised by the record, and furthermore that, while the court found that such a notice had been served, it nowhere directed the payment of any of the proceeds to such laborers. However this may be, we regard the point as immaterial so far as these appellants are concerned, and none of the laborers have appealed. For, if it were conceded that none of the laborers could proceed under the statute in question to enforce their claims by such notice, it yet appears that there is not enough left of the proceeds to pay the lien claims of the other laborers. So the appellants could get nothing in any event, and of course the appellants are not interested as to whether the money is distributed among the greater or lesser number of the employees of Kirby, Hightower & Co.

Affirmed.

Gordon, Anders, Reavis and Dunbar, JJ.. concur.