67 F. 633 | 6th Cir. | 1895
(after stating the facts). The controversy
which the complainants seek to make in this case is whether proper measurements and classifications of the excavation and embankment done by the complainants under the contract entitle them to uocover a large sum from the railroad company. One of the terms of the contract is that the measurements and classifications of the chief engineer of the defendant, as contained in his final estimate, shall be conclusive of the amount to be paid by the company to the contractors, in the absence of fraud or mistake. It is conceded by both parties that the amount due according to the final estimate has been paid to the contractors, or their order, except §5,581.03, and this sum the company expresses its willingness to pay to those who may be now entitled to have it The authorities leave no doubt that construction contracts, in which the contractor stipulates that the engineer or architect of the owner shall finally and conclusively decide, as between Mm and the owner, what amount of work has been done, and its character, and the amount to be paid therefor under the contract, are legal, and should be enforced. In such cases, after the work has been done, the contractor can recover nothing in excess of the amount found due by the engineer, unless he can make it appear that the engineer’s decision was fraudulently made, or was founded on palpable mistake. Railroad Co. v. Price, 138 U. S. 185, 11 Sup. Ct. 290; Railroad Co. v. March, 114 U. S. 549, 5 Sup. Ct. 1035; Sweeney v. U. S., 109 U. S. 618, 3 Sup. Ct. 344; Kihlborg v. U. S., 97 U. S. 398; Fox v. Railroad Co., 3 Wall. Jr. 243, 9 Fed. Cas. 627 (Case No. 5,010); Lewis v. Railroad Co., 49 Fed. 708; Ranger v. Railway Co., 5 H. L. Cas. 72; Waring v. Railway Co., 7 Hare, 482; McIntosh v. Railway Co., 2 De Gex & S. 758; Hill v. Railway Co., 11 Jur. (N. S.) 192; Scott v. Corporation of Liverpool, 28 Law J. Ch. 230; Herrick v. Railroad Co., 27 Vt. 673; 2 Wood, R. R. 1138 et seq., and cases cited.
Another circumstance relied upon by the complainants to show that the final estimate of Cobb should not be regarded as conclusive is that he made a material reduction in the measurements, and a material change in the classifications, as they appeared in the monthly estimates for July and August. Each monthly estimate contained a statement of the entire work done under the contract, in units of quantity and class, from the beginning. Deducting the amount shown in the previous monthly estimate gave the work done during the current month. The record shows that the amount of work credited to the contractors by the estimate given at the end of July, 1891, was greater in money value by some §20,000 than that allowed in the final estimate; and this although the work done in August, 1891, to complete the job, was not inconsiderable. This calls for explanation. The line was divided into three residencies or divisions. The south end and the Vanieer Spur were in charge of Assistant Engineer Neblett. The north end was divided between Assistant Engineers Grundy and Mills. When the July estimate was returned, Cobb says that ho became convinced that the loose rock returned on the north end was an over classification. He (hereupon went over Grundy’s residency with him, and in detail discussed his classification, learning from him that he had not adhered to the specifications, in deciding what was to be classed as loose rock, but had exercised what he regarded as an equitable discretion to soften the harshness of the specifications in the contractor’s favor. He returned 55,608 yards of loose rock and 102,581 yards of earth excavated on his residency. Cobb reduced the loose rock to 29,585 yards, and increased the earth to 128,331,-—a reduction in money earned by the contractor of about $6,565. In the case of Mills, Gobi) went over his division with him, and in comparing amounts, Mills admitted that he had overclassified the loose rock in the “big cut” which was on his residency, and that he had
On the whole case, there is nothing at all to impeach the good faith of Cobb in making his final estimate. He did say to the contractors that he would recommend the payment of some $16,000 more than his final estimate by the company to them, because the specifications worked harshly against them, on condition that they would accept it as a finality. He says this was in accordance with his practice of requiring the contractors to live up to the specifications, and of then relieving them from any hardship by recommending to the company the payment of a lump sum in addition to the estimate made according to the contract,—a practice much more reasonable and safe than the one which the complainants here seek to establish as a custom. The contract specifically provided that the engineer, in making his final estimate, should not be bound by quantities in the monthly estimates; so that, in revising the entire work, Cobb was only doing what the contract contemplated; and, as no bad faith or palpable error appears in his measurements and classification, we think that the final estimate must be regarded as conclusive, except in the respects now to be discussed..
In the course of the work, Mundy, one of the complainants, who was also a subcontractor, absconded, leaving many creditors. Complainants gave a chattel mortgage to secure a considerable indebtedness. Both occurrences led to attachments and injunctions, which much embarrassed’ complainants in the fulfillment of the contract. In an adjustment between the attaching creditors, the company, and the complainants, it was arranged that Cobb should draw the amount due on each monthly estimate, and then pay out the same to the subcontractors, material men, and other creditors, on the order of complainants. This was done. It was very important to the company that the subcontractors and laborers should be paid, so that the work might progress, and several provisions of the original contract were evidently inserted to prevent interruptions from a failure of the principal contractors to pay their debts. Thus the principal contractors, to promote good order among the laborers, bound themselves in the contract to give assurance to the laborers
It is suggested that the principal contractors knew of the over-classification and overmeasurement. There is nothing to show this. They claimed then, and they claim now, that justice was not done them, even in the monthly estimates, in respect either of classification or measurement,
Again, it is pressed upon us that in returning the final estimate the engineer was an arbitrator; that he did not more represent the company than the contractor in making it; and, therefore, that the company could not be estopped by his act in the capacity of arbi
It appears to be conceded that, by a mistake, the complainants were not allowed, in the final estimate, $170 for clearing the middle division of the line, upon which their work was subsequently stopped, and $675.42 for extra work not covered by the contract. Only $200 was claimed for extra work in the bill; but the complainants should have leave from the circuit court to amend their bill to accord with the undisputed evidence.
The amounts due the complainants, therefore, are as follows:
Due by final estimate.......................................... $ 5,531 03
Clearing ...................................................... 170 00
Extra work.................................................... 675 42
Overpayments to subcontractors................................ 12,114 72
$18,491 17
These amounts should bear interest from the date of the final estimate. It is claimed by the respondent company that notices of attachments and assignments served upon them make it dangerous for them to pay this sum to complainants. They may be protected by bringing in all persons claiming an interest in the fund as parties to the action; and the decree to be entered below should provide that a payment of the sum due into the registry of the court, with interest until the day of payment, will satisfy the same. The de
13 C. C. A. 284.