13 Or. Tax 147 | Or. T.C. | 1994
This matter is before the court on plaintiffs' Motion for Summary Judgment. Intervenor has opposed the motion.1 The parties have stipulated the material facts and the court's ruling on the legal issues will be determinative. Of concern is whether intervenor's apartment project qualifies for property tax exemption as a commercial property under construction.
Intervenor's predecessor in interest constructed an apartment project on a steep hillside. The site is on a rocky promontory in the Northwest Portland Hills near the downtown business district. The sole access to the property is by a steep (21-degree) concrete bridge/roadway from West Burnside Street. The site contains 16 separate apartment buildings and parking areas. Since the time involved in construction is one of the important issues, the following chronology is set forth:
*149Late June, 1989 Clearing and grading of site begun.
July 3, 1989 Entrance excavated, holes drilled and steel rods grouted into rock as anchors for underpinnings of the bridge/roadway.
July 7, 1989 Concrete poured to hold the anchors.
July 12, 1989 The first portion of the concrete bridge/roadway abutment poured.
July 26, 1989 The remainder of the concrete bridge/roadway poured.
August 7, 1989 Building permits for construction of the apartment buildings issued.
August 16, 1989 The building inspector inspected the footing forms for two buildings.
July 6, 1990 City of Portland issued seventeen separate certificates of occupancy, one for each apartment building and one for the bridge/roadway.
July 8, 1990 The first apartment units occupied.
None of the units were in use or occupied on or before January 1, 1990. The apartments were constructed in furtherance of the production of income.
The relevant portions of ORS
"(1) * * * each new building or structure or addition to an existing building or structure is exempt from taxation for each year of not more than two consecutive years if the building, structure or addition:
"(a) Is in the process of construction on January 1;
"(b) Is not in use or occupancy on January 1;
*150"(c) Has not been in use or occupancy at any time prior to such January 1 date;
"(d) Is being constructed in furtherance of the production of income; and
"(e) Is, in the case of nonmanufacturing facilities, to be first used or occupied not less than one year from the time construction commences. Construction shall not be deemed to have commenced until after demolition, if any, is completed."
Intervenor maintains that the only issue before the court is whether construction of the property took one year or more. Intervenor relies on the fact that defendant's opinion and order indicates "there appears to be no dispute between the parties as to the Uptown Heights Apartments satisfying the first four of the five criteria." However, plaintiffs do not agree and challenge the claimed exemption on additional grounds. ORS
"All proceedings before the court shall be original, independent proceedings and shall be tried without a jury and de novo."
Accordingly, the court will consider all points of disagreement between the parties which relate to issues raised before the department in the administrative hearing.
One of the first issues to be addressed is the status of the bridge/roadway. There is no question that its construction was necessary to access the site. Plaintiffs contend that the structure is more roadway than bridge because only a short portion of it spans a culvert. Plaintiffs assert that the construction of the bridge/roadway was just site preparation and as such should be assessed as part of the land value. Plaintiffs point to OAR
1. The court finds the bridge/roadway is a "related improvement" which qualifies as exempt under ORS
The fundamental point of dispute between the parties is whether the subject improvements must be viewed as an integrated project or as individual buildings. Intervenor contends that, due to the unique location and nature of the *151 development, the subject is an integrated project which could not be used until all aspects of it were completed. In opposition, plaintiffs maintain that the apartments are individual buildings separate from each other and the bridge/roadway. Both parties are partially correct.
2. The exemption is provided for each building or structure. This suggests that each building or structure must separately and independently meet the tests involved. However, where the nature of the building or the structure is such that it is interdependent with another building or structure and requires completion of the whole to be usable, then the test is applied to the interdependent parts as a whole.
"The legislature, in using 'structure,' is deemed to have contemplated the situation in which a plant, designed for a very specific use and not adaptable for any other purpose, could be regarded as useless until the whole structure is basically operable." Collier Carbon v. Dept. of Rev.,
5 Or. Tax 7 (1972).
3. The court finds that the individual apartment buildings are not interdependent with each other but can be rented separately. Consequently, there can be no tacking or adding of one building's construction time to that of another. However, none of the apartment buildings could be used without the bridge/roadway. Consequently, the court finds that the measure of construction time for each apartment building will begin with construction of the bridge/roadway and end when each building is ready for occupancy. The parties have stipulated that bridge/roadway was started July 3, 1989, the apartments were not completed until July 6, 1990, and actual occupancy started July 8, 1990. Therefore, all of the subject apartment buildings are exempt.
Plaintiffs argue that if the bridge/roadway is considered a structure under ORS
In summary, the court finds that the subject property was in the process of construction on January 1, 1990, was not in use or occupancy on or before January 1, 1990, was being constructed in the furtherance of the production of income, and was first used or occupied not less than one year from the time construction commenced. Department's Opinion and Order No. 90-4202 must be sustained. Now, therefore,
IT IS ORDERED that plaintiffs' Motion for Summary Judgment is denied, and
IT IS FURTHER ORDERED that judgment be entered in favor of intervenor against plaintiffs. Costs to neither party.