The Appellant, Multiplex, Inc., (“Multiplex”) appeals the March 24, 2010, order of the Circuit Court of Kanawha County dismissing its civil complaint against the Appellees, Raleigh County Board of Education (“Board of Education”) and School Building Authority of West Virginia (“SBA”). Having fully considered the record before us, the briefs and arguments of the рarties, we reverse the circuit court and remand this matter for further proceedings consistent with this Opinion.
I.
Facts and Background
In 2005, Multiplex entered into a construction contrаct with the Board of Education to build an extension to Independence High School in Raleigh County, West Virginia. The construction project was funded through the SBA At one of the pre-construction meetings, the Board of Education instructed Multiplex not to do any more work on the project until utility lines had been reloсated. Under the terms of the contract, the relocation of the utility lines was the responsibility of the Board of Education. More than six months later, the Boаrd of Education instructed Multiplex to recommence work on the project.
Multiplex did recommence its work on the project. However, in August 2006, it filed suit against the Board of Education seeking to terminate its contract and collect damages caused by the delay. Multiplex alleged in the 2006 civil comрlaint that Section 14.1.2 of the contract entitled it to terminate the contract because the Board of Education’s relocation of the utility lines сaused a delay of more than 120 days in any 365-day period and that Section 14.1.3 of the contract gave Multiplex a cause of action for damagеs caused by such delay. On April 25, 2007, a settlement agreement was reached in which the Board of Education agreed to pay Multiplex $183,143.00. A “Release in Full of Ml Claims” (“Release”) was executed reflecting the terms of the settlement agreement.
Key provisions of the Release included the following (emphasis added):
[Multiplex, Inc., in consideration of the payment of $183,143.00] do[es] hereby release and forever discharge the Board of Education ... of and from all claims, demands, damages, actions, causes of action, and suits at law or equity that [Multiplex] may have, including past, present and future, both known or unknown, of whatsoever kind or nature, for or arising out of those certain alleged wrongful acts alleged in the Complaint filed in Civil Action No. 06-C17-17 [.]
It is expressly understood and agreed that this Release is intended to extend to any and all claims, injuries and damages sustained by Multiplex, Inc., without exception arising out of the alleged wrongful acts set forth in the aforementioned Complaint, including claims for loss of service, business opportunities, past or future expenses or loses of any kind, pаst and future lost wages or earning capacity, punitive damages, and any and all other forms of recoverable compensation or damagеs, even to the extent that such injuries or damages may not be known or apparent at this time.
*366 Following the settlement agreement, Multiplex continued its work оn constructing the extension for Independence High School. However, in 2009, Multiplex filed a new civil action alleging that the Board of Education had cаused a “considerable delay” in the project (caused by the installation of tiles and roof top HVAC units) and that as a consequence of the delаy Multiplex was entitled to damages pursuant to the terms of the contract. The damages sought by Multiplex included $173,898.18 for delays associated with the roof top units, $11,326.66 for an unpaid change order, $80,298.88 reflecting the difference between the contract specified payment for tile work and the cost actually incurred as a result of delays, lost profit in the amount of $18,575.86, and approximately 122 days of additional office overhead at a cost of $140,298.88.
In response, the Board of Education moved to dismiss the complaint pursuant to Rule 12(b)(6) of the West Virginia Rules of Civil Procedure. In support of its motion, the Board of Education argued that Multiplex’s 2006 Relеase barred Multiplex from filing a lawsuit for damages based upon delays in the construction contract and that the circuit court should enforce the Release by dismissing Multiplex’s civil complaint. In response, Multiplex argued that the Board of Education was giving the Release too broad of a reading and that the Release pertained only to damages, known and unknown, it had incurred as a result of the Board of Education’s failure to timely relocate utility lines at the construction site, as alleged in the 2006 complaint, and did not bar suit for damages related to the new delays alleged in its 2009 civil suit.
The circuit court agreed with the Board of Education, finding that the Release signed by Multiplex barred future suits based on delays caused by the Board of Education and, based on that finding, dismissed Multiplex’s civil complaint in an order entered March 24, 2010.
II.
Standard of Review
We have previously held that “[a]ppellate review of a circuit court’s order granting a motion tо dismiss a complaint is
de novo.”
Syllabus Point 2,
State ex rel. McGraw v. Scott Runyan Pontiac-Buick, Inc.,
III.
Discussion
In dismissing Multiplex’s civil action, the circuit court found that:
... under the broad but clear and unambiguous meaning of the word used to describe the scoрe of the release to the Raleigh County BOE, a settlement between Multiplex and the Raleigh County BOE was struck as to all claims related to owner causеd delays on the Project that is binding and enforceable against Multiplex.
Based on this finding, the circuit court held that Multiplex was not entitled to repudiate its priоr settlement agreement by maintaining a new civil lawsuit based on allegations that it had been damaged by new and different wrongful delays caused by the Board of Eduсation. We find this conclusion to be in error.
A plain reading of the Release entered into by Multiplex clearly evidences that the scope of thе Release was limited to events “arising out of the alleged wrongful acts set forth in the aforementioned Complaint,” with the aforementioned complaint being that filed by Multiplex in 2006. The “alleged wrongful acts” in the 2006 complaint were that the Board of Education had failed to timely relocate utility lines which caused a delay in the construction project. In other words, the cause of action was a delay, and the factual circumstances giving rise to the cause of action was the failure to timely relocate the utility lines.
While the cause of action in Multiplex’s 2009 complaint was also based on a delаy in the construction project, the factual circumstances giving rise to that cause of action are completely different and are not events “arising out of the alleged wrongful acts set forth in the [2006] Complaint.” The events in the 2009 complaint are new delays constituting separate causes of аction that had not even *367 occurred at the time of the 2006 complaint, or at the time the Release was executed.
We have previously held that “[a] release ordinarily covers only such matters as may fairly be said to have been within the contemplation of the parties at the time of its execution.” Syllabus Point 2,
Conley v. Hill,
IV.
Conclusion
For the reasons set forth herein, we reverse the circuit court and remand this matter for further proceedings consistent with this Opinion.
Reversed and Remanded.
