Mugan v. Regan, Soper, Wells & Co.

48 Mo. App. 461 | Mo. Ct. App. | 1892

Gill, J.

In the fall of 1889, the defendants were contractors engaged in paving Grand avenue from Twentieth street to the city limits of Kansas City. They had an agreement with plaintiff Mugan to furnish the necessary crushed stone, which was to be paid for at the rate of eighty-nine cents per cubic yard ; “ payments to be made on the first of each month for all stone delivered up to that time; and, in case it becomes necessary, the party of the first part (Mugan) may draw fifty per cent, on the fifteenth of each month.” Plaintiff began, the delivery of the stone the latter part of September, and continued till about November 25 following, when she refused to go further, or to deliver any more, for the alleged reason that defendants had failed to pay her as stipulated in the contract. She thereupon abandoned the work, and sued for the balance alleged to be *463due on the stone delivered. On a trial by jury in the circuit court plaintiff had a verdict and judgment for the sum of $1,632.67, and defendants appealed.

Defendants’ counsel thus pithily states the matter for decision: “The sole proposition which is submitted as a reason for reversing the judgment of the trial court is, that the evidence of the respondent showed that the respondent was herself in default under the contract, and, at the time of the institution and the trial of this cause, the respondent had not performed the obligations imposed on her by the contract, which were conditions precedent to her right to sue the appellants.” '

After a careful review of the testimony furnished in the record we discover no just ground for this contention. The plaintiff’s evidence tends to prove a faithful compliance with the terms of the contract on her part until November 25, when she refused to deliver more stone, because defendants had failed to pay therefor as agreed. The jury under proper instructions found that plaintiff was not in default, but that defendants were ; that they had not paid as they were required by the terms of the written contract. There was, too, ample evidence to justify the verdict. The law is that, where work is done under a contract providing for payment by installments at stated periods, and the payments are not so made, the contractor may quit the work, and then recover of the defaulting party for the amount done, at the contract rates. Bean v. Miller, 69 Mo. 384. Judgment affirmed.

All concur.