OPINION
During road construction, trees on the property of respondent Kenneth Muehlst-edt, as well as those from the right of way, were cut and then buried on Muehlstedt’s property. When the buried trees later interfered with respondent’s attempts to build a house, he sued those involved with the road construction. A special jury verdict awarded respondent compensatory and punitive damages against various defendants. Following a new trial on damages, another jury awarded respondent less compensatory damages but more punitive damages. The trial court granted defendants a third trial if respondent did not accept a punitive damages remittitur, and this reduction was accepted. Defendants appeal, principally on the award of punitive damages, and respondent challenges the remit-titur and the trial court’s attorney fees determinations. We reverse and modify in part.
FACTS
In 1979 respondent paid $15,000 for three parcels of land, including Lots 11 and 12 in Lino Lakes, Minnesota. In 1984 respondent petitioned the city for road access to his properties. This request was granted and the city engineer, appellant John Davidson, who was also employed by appellant Tolz, King, Duvall, Anderson & Associates, Inc. (TKDA), drafted the necessary documents for construction of the road. The plans required that trees removed from the right of way be disposed of “off site” and that all other work be done on the right of way unless permission was obtained for workers to enter the abutting private property.
*895 The prime road construction contractor, appellant Northern Asphalt, Inc., subcontracted tree removal to appellant Dell Contracting. Prior to starting work, Davidson and Dell’s representative, appellant John Vickaryous, discussed tree removal. A subsequent telephone conversation between Vickaryous and Davidson occurred during tree removal. Vickaryous used a bulldozer to knock down trees on Lot 11 and to dig a hole in which the trees from respondent’s property and the right of way were buried.
Upon learning that trees were being buried on his land, respondent, who was planning to build a house on Lot 12, called Davidson. As a result, respondent, Davidson and Vickaryous all met on the site to discuss what had happened. During this conversation Davidson allegedly offered to remove the trees.
The next spring respondent built his house. In order to install his septic system, respondent had to have his contractor remove 38 truckloads of trees and refill the hole at a cost of $17,165. Respondent then sued the city, Davidson, TKDA, Northern, Dell, and Vickaryous.
At trial, conflicting testimony was entered regarding the contents of the Vickar-yous-Davidson telephone call. Also, testimony conflicted as to whether respondent consented to the burial of the trees during the on-site conversation. Testimony further conflicted regarding the number and type of respondent’s trees bulldozed by Vickaryous. The jury returned a special verdict awarding respondent $25,818 for the destroyed trees and $17,165 in compensatory damages for the burial of trees. The jury also assessed punitive damages against Vickaryous, Dell, Davidson, and TKDA. After statutory trebling of the compensatory damages for the destroyed trees, the award totaled $180,619.
Appellants moved for JNOV, noting respondent had offered no evidence of appellants’ abilities to pay punitive damages. The trial court denied the JNOV motion but found all damages excessive except the award for tree burial. The trial court then offered respondent the choice between a new trial or reduced awards on the damages deemed excessive.
Respondent opted for a new trial and in those proceedings he presented evidence of the appellants’ abilities to pay punitive damages. The trial court told the second jury that it was not to consider whether punitive damages were appropriate, and submitted the damages questions to the jury. The second jury awarded respondent $15,785 as compensatory damages for the bulldozed trees and assessed punitive damages greater than those assessed by the first jury against the same defendants, including a $500,000 assessment against TKDA. After statutory trebling of the tree loss award, damages in the second trial totaled $617,355. 1
Finding the punitive damages assessment against TKDA excessive, the trial court again granted respondent a choice between a new trial and an award of $100,-000 in punitive damages against TKDA. Respondent accepted the reduced award.
ISSUES
1. Are treble damages for injury to trees and punitive damages mutually exclusive? Did the trial court otherwise err in its approach to punitive damages?
2. Is the evidence sufficient to support special verdict findings? Did the trial *896 court abuse its discretion by allowing certain evidence of compensatory damages, or in its rulings on attorney fees.
ANALYSIS
1. Punitive Damages
The primary elements of the appeal are respondent’s challenge on the use of the final remittitur and TKDA’s allegation that the remaining $100,000 punitive damage award is still excessive. To reach a conclusion on these contentions, we also must address specific challenges to the entire punitive damage award.
a. Treble and Punitive Damages
By statute, compensatory damages for trees cut from the land of another are trebled. Minn.Stat. § 561.04 (1988). In
Johnson v. Jensen,
Here, the special verdict form allowed punitive damages to be assessed only for the burial of trees on respondent’s property, not for the damages to respondent’s trees. The jury instructions similarly required the jury to distinguish the trespass to respondent’s trees from trespass to respondent’s real estate. We conclude that the trial court’s instructions and the special verdict form are lawful. 2
b. Vicarious Liability
By statute, punitive damages can properly be awarded against an employer if the employee worked in a managerial capacity and acted in the scope of employment.
See
Minn.Stat. § 549.20, subd. 2(c) (1990). Here, Davidson was a TKDA manager. TKDA, however, argues that under
Shetka v. Kueppers, Kueppers, Von Feldt & Salmen,
Shetka
involved an unsuccessful attempt to use the financial status of an alleged tortfeasor’s partners to determine a punitive damages award.
Shetka,
Appellant also relies on language in
Shetka
questioning whether the plaintiffs there could show willfulness of the partnership or nonconsulting partners.
Shetka,
Finally, appellants argue that a noncul-pable employer’s liability is limited to that of the defending employee. This contention is inconsistent with language of the punitive damage statute explicitly allowing punitive damages to be “awarded against” a principal if the offender was employed in a managerial capacity.
See
Minn.Stat. § 549.20, subd. 2(c);
see also Pacific Mut. Life Ins. Co. v. Haslip,
— U.S.—, —,
c.Retrial on Amount of Punitive Damages
Because the issue of punitive damages is often interconnected with the issues of liability and compensatory damages, it will usually be appropriate for a trial court, as an alternative to a partial new trial, to
*897
reduce an excessive punitive damage award to a reasonable sum.
See Hodder v. Goodyear Tire & Rubber Co.,
Where the amount of punitive damages is separately retried, the second jury will necessarily be made aware of the first jury’s liability determination. The trial court found that because the requisites of “substantial justice” were satisfied by the second trial, any error resulting from the retrial of the punitive damage issue alone was harmless under Rule 61. This judgment should stand. The mischief Hodder sought to avoid by discouraging partial new trials was the needless relitigation of fault to determine the egregiousness of that fault. Id. Ordering a third trial based on an alleged violation of Hodder would only exaggerate the problems sought to be avoided.
d. Punitive Damages in Cases Not Involving Personal Injury
Appellants argue that punitive damages are inappropriate in this case because there was no personal injury.
Eisert v. Greenberg Roofing & Sheet Metal Co.,
[T]he “punitive damages remedy concerns the vital state interest of protecting persons against personal injury.” The interests implicated in strict liability actions for injury solely to property are not so great as to warrant extension of this controversial remedy to those actions.
******
Where [a plaintiff’s] injury is limited to property damage, the public interest in punishment and deterrence is largely satisfied by the plaintiff’s recovery of compensatory damages. Punitive damages represent an extraordinary measure of deterrence. Denying their imposition in this case [which did not involve personal injury], after allowing punitive damages in strict liability actions for personal injury, reflects the higher value our society places on the safety of persons than it does on the security of property.
(Citations omitted.)
Initially, we note that
Eisert’s
prohibition of punitive damages for property damage is for products liability claims. Similarly, Minnesota’s punitive damage statute arose from concern over developments in products liability litigation.
See Minnesota-Iowa Television Co. v. Watonwan T. V. Improvement Ass’n,
Additionally, we observe that the 1978 punitive damage statute codified existing case law and applied only to previously recognized causes of action.
Lewis v. Equitable Life Assurance Soc’y,
Since the statute’s enactment, punitive damages have been affirmed by this court in cases not involving personal injury.
See, e.g., Hydra-Mac, Inc. v. Onan Corp.,
In sum, we decline to expand Eisert beyond its subject matter of product liability litigation. Any further enlargement of Ei-sert should be determined by the legislature or the supreme court.
While we do not read Eisert as a general prohibition on punitive damages where there is no personal'injury, Eisert and Hod-der require broadened appellate review on the amount of punitive damage awards in such circumstances.
The factors to be considered in determining the amount of a punitive damage award are enumerated in Minn.Stat. § 549.20, subd. 3. Under
Hodder,
Here, the profitability of the burial and the public hazard appear minimal. However, the jury apparently believed evidence that Davidson was aware he had not consulted with respondent about the use of his property to bury trees. The jury also heard evidence it could find sufficient to show improper concealment of facts. The relative sizes of the assessments suggest that the jury properly considered the appellants’ financial conditions.
The trial court concluded that the punitive damage award against TKDA was the product of passion or prejudice. We will not disturb this judgment. Regarding reduction, the trial court concluded that a $100,000 award on these facts was “more than adequate” to serve the purposes of punitive damages. Having in mind this assessment by the trial court as well as our elevated obligations of review where there is no personal injury, we affirm a punitive damage award of $70,000 against TKDA, double the sum awarded against Davidson.
e. Jury Instructions
Dell contends that the jury should have been told that the compensatory damages would be tripled. A specific jury instruction is not required unless the jury needs it to “intelligently determine” an issue.
Paulson v. Lapa, Inc.,
2. Other Issues
Appellants raise additional issues on the sufficiency of evidence for jury findings and the breadth of evidence permitted on compensatory damages. Respondent contends the trial court erred in denying an award of attorney fees.
a. The jury’s findings will be sustained if it is possible to do so on any reasonable theory, and we must consider the evidence
*899
in the light most favorable to the prevailing party.
Ruskamp v. Ferknes,
i. Davidson’s liability. Under the contract, engineer Davidson was responsible for “any and all questions” regarding completion of the roadwork. More specifically, Vickaryous testified that Davidson told him to put the trees on respondent’s property and that Davidson authorized him to knock down and bury the trees on respondent’s property with a bulldozer. Contrary testimony presents a credibility question for the jury. Also, because the contract indicates that Lino Lakes hired TKDA as the engineers for the project and Davidson was the ranking TKDA representative involved with the project, the record supports the jury’s conclusion that Davidson served as TKDA’s manager.
ii. Clear and convincing evidence of indifference. Willful indifference to support a punitive damages award is “a maliciousness, an intentional or willful failure to inform or act.”
Wikert v. Northern Sand & Gravel, Inc.,
b. Analogizing to
Baillon v. Carl Bolander & Sons, Co.,
Baillon
and
Rector, Wardens and Vestry of St. Christopher’s Episcopal Church v. C.S. McCrossan, Inc.,
Here, given the inconsistent evidence regarding the nature of the destroyed trees, we conclude that the trial court did not err under McCrossan in allowing evidence regarding both the diminution in the property’s value and the replacement value of the destroyed trees. Further, given the conflicting evidence, we also defer to the jury’s compensatory damage determination. 6
c. The trial court denied respondent’s motion for bad faith attorney fees
*900
under Minn.Stat. § 549.21, stating “[Appellants’] lawyers’ efforts * * * did not cross the line between zealous advocacy and bad faith.” Bad faith is an issue of fact which the trial court is in the best position to judge.
Uselman v. Uselman,
DECISION
We reverse punitive damage awards against appellants Vickaryous and Bell, affirm the $35,000 punitive damage award against appellant Davidson, and affirm the punitive damage award against appellant TKDA modified to the amount of $70,000. We affirm other trial court decisions attacked on appeal.
Reversed in part, and affirmed in part as modified.
Notes
. AWARD FIRST TRIAL FIRST REMITTITUR SECOND TRIAL SECOND REMITTITUR
Damage to trees $25,818 $5,000 $ 15,875
Vickaryous punitive $ 8,600 $5,000 $ 15,000
Dell punitive $17,200 $5,000 $ 20,000
Davidson punitive $20,800 $5,000 $ 35,000
TKDA punitive $39,400 $5,000 $500,000 $100,000
. Under Minn.Stat. § 549.09, subd. 1(b)(4) (1990), preverdict interest is not allowed for "punitive damages, fines or other damages that are noncompensatory in nature.” Thus, because Minn.Stat. § 561.04 allows recovery of "treble the amount of damages which may be assessed [for the destroyed trees]” only the first third of the trebled damages is compensatory. The remainder is at least "noncompensatory" and the trial court’s allowance of prejudgment interest on this amount must be reversed.
. In
Runia v. Marguth Agency, Inc.,
. We also observe that allowing punitive damages in cases not involving personal injury is consistent with the Prosser text:
Typical of the torts for which [punitive] damages may be awarded are * * * malicious prosecution and intentional interferences with property such as trespass, private nuisance, and conversion. But it is not so much the particular tort committed as the defendant’s motives and conduct in committing it which will be important as the basis of award. Statutes in most states have provided punitive damages for particular torts, as in the case of multiple damages for trespass.
Prosser & Keeton, The Law of Torts § 2 (5th ed. 1984) (footnotes omitted).
. Because the jury’s fault findings demonstrate that Vickaryous was directed to bury the trees by Davidson, we conclude that he lacked the willful indifference necessary to sustain a punitive damage award against him. Therefore, the assessment of punitive damages against Vickar-yous and Dell is reversed and we need not address whether Vickaryous acted in a managerial capacity for Dell.
. The argument that the trial court erred in entering judgment against Northern for compensatory damages is without merit. The contract states: "[Northern] * * * shall assume full responsibility for supervision of the work irrespective of the amount of work sublet * * *.” Further, a subcontractor is an entity "executing] part of the work under the terms of the contract * * "Work” is providing that which is necessary "to the successful completion of the project including all of the duties and obligations imposed by the contract upon the contractor.” Thus, a subcontractor is performing a portion of the contractor’s work under the contract. Under the terms of the contract, the contractor "shall be responsible for any damage *900 occasioned by or resulting from his * * * work * * * to property of any kind outside the construction area.”
