In October 2017, the Federal Energy Regulatory Commission approved the application of Mountain Valley Pipeline, LLC, to construct a natural gas pipeline through West Virginia and Virginia. Building and maintaining that pipeline would require access to thousands of private properties, under which the pipeline would be buried. Accordingly, the Commission's approval permits Mountain Valley to obtain
Mountain Valley successfully negotiated easements allowing access onto the land of most of the affected landowners. To obtain the rest of the required easements, it initiated condemnation proceedings. Three district courts granted partial summary judgment to Mountain Valley, recognizing its right to take the easements. And because the eminent domain proceedings - including multiple trials to determine the amount of just compensation for each easement - would take years to complete, the courts also issued preliminary injunctions granting Mountain Valley immediate possession of the easements, so that it could begin construction without delay. To ensure that the landowners would be compensated fully, the district courts required Mountain Valley to post deposits, which the landowners could draw upon while the proceedings continued.
On appeal, the landowners do not dispute the grant of partial summary judgment to Mountain Valley, conceding that Mountain Valley has the substantive right to take easements by eminent domain. Thus, the only question before us is whether Mountain Valley may gain access to those easements now, or whether it must wait to start construction until the district courts can sort out just compensation. We hold that the district courts did not abuse their discretion in allowing Mountain Valley immediate possession, and therefore affirm the injunction orders.
I.
A.
In October 2015, Mountain Valley applied to the Federal Energy Regulatory Commission ("FERC" or the "Commission") for authorization to construct a 303.5-mile-long, 42-inch-diameter pipeline from Wetzel County, West Virginia, to Pittsylvania County, Virginia. When complete, the pipeline would transport up to two million dekatherms of natural gas per day, enabling shippers to access markets in the Northeast, Mid-Atlantic, and Southeast. Close to 300 parties, including residents and environmental groups, intervened in the Commission's process, and FERC received more than 2,000 written and oral comments during its review.
On October 13, 2017, the Commission issued a "certificate of public convenience and necessity" (the "Certificate") under the Natural Gas Act, 15 U.S.C. § 717f(e). The Commission found that the proposed pipeline is in the public interest, would meet a market demand, and is "environmentally acceptable." J.A. 2853. The Certificate authorized Mountain Valley to construct and operate the proposed pipeline, contingent on numerous conditions. Most significant for this appeal, the Certificate requires that the pipeline be complete and available for service within three years - that is, by October 2020.
Under the Natural Gas Act, legal challenges to a Commission certificate and its underlying public-interest determination may proceed only through specified routes. A party wishing to contest a certificate first must apply for rehearing before the Commission. 15 U.S.C. § 717r(a). After that, review may be had in the United States Court of Appeals for the District of Columbia or another federal circuit court with jurisdiction. Id. § 717r(b). Here, though numerous parties have challenged the Certificate, their efforts thus far have been unsuccessful. In November 2017, various intervenors applied to the Commission for rehearing and a stay of the Certificate, which ultimately was denied. While that request was pending, at least three petitions for review and for stay pending review
By late November 2017, within weeks of obtaining the Certificate, Mountain Valley had entered into three master construction services agreements to lay the pipeline. Mountain Valley sought to commence construction by February 2018 with completion anticipated for December 2018, well before the Commission's deadline of October 2020. Because tree-clearing in areas with protected bats must be completed during the winter season (between mid-November and March), even a brief delay would have postponed the project's start date until November 2018. However, Mountain Valley had developed a schedule to proceed in the event of that contingency, under which it still expected to meet the Commission's in-service deadline.
Mountain Valley acquired rights-of-way to portions of approximately 85 percent of the properties along the approved pipeline route in anticipation of construction. These include both permanent easements along the pipeline route, allowing its pipeline to lie underneath the land, and temporary easements for construction. However, Mountain Valley was unable to reach agreement with the hundreds of landowners who are now parties to this litigation (the "Landowners"
B.
Under the Natural Gas Act, Mountain Valley's certificate entitles it to exercise the power of eminent domain to obtain any rights-of-way it cannot otherwise acquire, as necessary to construct, operate, or maintain the planned pipeline. See 15 U.S.C. § 717f(h). In other words, where Mountain Valley is unable to negotiate an easement with a landowner along the pipeline route, it may obtain a condemnation order granting an easement for a fair price set by the court.
Between receiving its Certificate in October 2017 and early December of that year, Mountain Valley commenced proceedings in three different district courts to condemn a 50-foot-wide path along the pipeline route in each jurisdiction. Within days of commencing each proceeding, Mountain Valley moved for partial summary judgment on its substantive right to take the easements by eminent domain. In the same motions, the company sought preliminary injunctions granting immediate access and possession during the pendency of the proceedings, in order to prevent construction delays.
But that eminent domain process, one district court estimated, could take more than three years to complete - bringing it outside FERC's in-service deadline of October 2020 - as the courts conducted proceedings to determine the amount of just compensation for each of the hundreds of easements in question. Accordingly, the courts turned to Mountain Valley's motions for preliminary injunctions, which sought immediate access while those proceedings were ongoing. Applying the four-pronged test for a preliminary injunction set out in Winter v. Natural Resources Defense Council, Inc. ,
The first element of the Winter test - likelihood of success on the merits - was easily satisfied, as the courts "ha[d] already determined on the merits that Mountain Valley has the right to condemn the landowners' property interests." S.D.W. Va. Opinion , at J.A. 2715. On the second element - irreparable harm - the district courts held that Mountain Valley would suffer various forms of irreparable injury if it were required to delay construction until after completion of the eminent domain proceedings. Most important, without a preliminary injunction, Mountain Valley would be unable to meet the Commission's October 2020 in-service deadline, which could come and go before the courts had finally determined due compensation for the hundreds of easements at issue.
In response, the Landowners proposed that any injunctive relief be delayed until November 2018, when bat-conservation regulations again would permit seasonal
The district courts further held that Mountain Valley's losses would exceed any harms a preliminary injunction might cause the Landowners, and that the balance of the equities - the third Winter factor - therefore favored preliminary relief. The key finding here, as one court explained it, was that virtually all harms identified by the Landowners would be inflicted as a result of the exercise of eminent domain itself, and not because of the preliminary injunction: Completion of the pipeline "will have the same impact on [Landowners'] property whether [Mountain Valley] is granted immediate access or commences construction only after [L]andowners have received just compensation." N.D.W. Va. Opinion ,
On the fourth element - the public interest - the district courts relied heavily on the Certificate itself, which was predicated on the Commission's finding that construction of the pipeline is in the public interest. The Landowners disagreed with that assessment, citing the dissenting opinion of one of the FERC commissioners and arguing that pipeline construction in fact would have negative effects on the environment and areas of historical and cultural importance. As the district courts explained, however, challenges to a FERC certificate must follow the prescribed statutory route, and condemnation proceedings may not be used to mount a collateral attack. "The Court will not second-guess FERC's determination that [Mountain Valley's] project will benefit the public need for natural gas as the [Landowners] request; FERC possesses the expertise necessary to make that determination." Id. at 531.
Accordingly, the district courts all found that Mountain Valley satisfied the Winter preliminary injunction standard and should be granted immediate possession. At the same time, the courts recognized that the Landowners were entitled to a "reasonable, certain, and adequate provision" for obtaining just compensation at the end of the condemnation proceedings. See, e.g. , W.D. Va. Opinion , at J.A. 1432 (quoting Cherokee Nation v. S. Kan. Ry . Co. ,
II.
The Landowners have not appealed the entry of partial summary judgment against them, nor the merits determination on which it rests: that under 15 U.S.C. § 717f(h), Mountain Valley currently has the right to exercise eminent domain and take easements on their property to build and operate the FERC-approved pipeline. But they do dispute the appropriateness of preliminary relief, and timely appealed the issuance of the three preliminary injunctions awarding Mountain Valley immediate possession of the easements while just compensation is determined.
We "review the decision to grant or deny a preliminary injunction for an abuse of discretion." Safety-Kleen, Inc. v. Wyche ,
The Landowners advance two principal arguments against the preliminary injunctions. First, they argue that federal courts lack authority to grant immediate possession - that is, possession prior to the determination and payment of just compensation - and that the injunctions therefore are legally infirm. And in the alternative, they argue that the district courts improperly applied the Winter factors and abused their discretion in awarding preliminary relief here. For the reasons given below, we disagree on both counts.
A.
We begin with the Landowners' threshold argument: that district courts may not order immediate possession of condemned property under 15 U.S.C. § 717f(h). Instead, the Landowners contend, the district courts were authorized to grant Mountain Valley access to the easements in question only after eminent domain proceedings were completed, with just compensation for each individual easement calculated and paid.
We note at the outset that this is a statutory argument, not a constitutional one. The Landowners concede, as they must, that the Constitution does not prohibit condemnations in which possession comes before compensation. The Supreme Court settled that question nearly 130 years ago in Cherokee Nation , holding that the Constitution "does not provide or require that compensation shall be actually paid in advance of the occupancy of the land to be taken."
Instead, the Landowners argue that there was no statutory authority for what they call "take-first, pay-later" condemnations. Under the Natural Gas Act,
But as the Landowners recognize, our court has rejected precisely this argument before, holding in East Tennessee Natural Gas Co. v. Sage ,
We disagreed. What the landowners' argument "overlook[ed]," we explained, was "the preliminary injunction remedy provided in the Federal Rules of Civil Procedure that were adopted with the tacit approval of Congress."
This case is on all fours with Sage . As in Sage , there already has been a finding that the gas company has a substantive right to condemn the easements in question, here in the form of partial summary judgment rulings that are unchallenged on appeal. And the district courts adequately safeguarded the Landowners' interests with a deposit provision that is similar to but more protective than the one we approved in Sage , in that it requires Mountain Valley to deposit with the court an amount that is several times larger than the estimated value of the condemned easements
The Landowners do not dispute that Sage , by its terms, governs this case. Instead,
B.
The only remaining question for this panel is whether the district courts abused their discretion in issuing preliminary injunctions under the Winter standard. On this question, too, Sage is highly instructive. In Sage , after holding that district courts may grant immediate possession to a gas company with a valid FERC certificate, we went on to consider whether the gas company could satisfy the standard conditions for preliminary relief.
Success on the merits was not only likely but guaranteed, we held, given the district court's determination - uncontested on appeal - that the gas company had the right to condemn the landowners' property.
Since Sage was decided in 2004, many courts, both within and outside this circuit, have issued preliminary injunctions granting immediate possession to gas companies under closely analogous circumstances. See, e.g. , S.D.W. Va. Opinion , at J.A. 2713-14 (collecting district court cases); Columbia Gas Transmission, LLC v. 1.01 Acres ,
It is with Sage and this body of authority in mind that we review the district courts' preliminary injunctions for abuse of discretion, applying Winter 's four-pronged test. For the reasons given below, we find no abuse of discretion and affirm the entry of preliminary relief.
1.
The first Winter prong - likelihood of success on the merits - is uncontested, and for good reason. Mountain Valley has done more than establish a likelihood of success on the merits; it already has succeeded on the merits. The district courts granted partial summary judgment to Mountain Valley on its claim that it is entitled to exercise the power of eminent domain over the Landowners' property, notwithstanding the pendency of legal challenges to the Certificate, and the Landowners have not challenged those rulings on appeal. There is no question, then, that Mountain Valley may take easements across the properties at issue, making this the rare preliminary-injunction case in which success on the merits is guaranteed.
2.
We also find no clear error or abuse of discretion in the district courts' findings that Mountain Valley would incur irreparable harm absent preliminary injunctions, in satisfaction of Winter 's second element. To establish irreparable harm, the movant must make a "clear showing" that it will suffer harm that is "neither remote nor speculative, but actual and imminent." Direx Israel, Ltd. v. Breakthrough Med. Corp. ,
First and most important, it is undisputed that without preliminary relief, Mountain Valley almost certainly would be unable to meet FERC's October 2020 in-service deadline. As the court explained in Sage , construction of a pipeline is a
In response to that straightforward case for preliminary relief, the Landowners urged the district courts to adopt a more "narrow[ ] analy[sis]," focused on whether Mountain Valley "needs access to their properties now or whether it still can meet FERC's deadline if granted access later." N.D.W. Va. Opinion ,
The Landowners' argument assumes that the need to narrowly tailor preliminary relief, see PBM Prods., LLC v. Mead Johnson & Co. ,
To establish that injury, Mountain Valley presented evidence of three types of monetary harm: lost revenues from the delay in pipeline service, estimated at $40 to $50 million per month; charges and penalties for the breach of construction contracts, totaling $200 million; and carrying costs to prolong the project, such as storage and personnel expenses, for an additional $40 to $45 million. The district courts closely scrutinized those alleged losses, noting testimony suggesting that "some of the claimed damage amounts might be lower," W.D. Va. Opinion , at J.A. 1423, or be "capable of mitigation," N.D.W. Va. Opinion ,
On appeal, the Landowners raise two principal challenges to the district courts' findings of irreparable injury. Most significantly, they insist that the district courts erred at the threshold in considering Mountain Valley's economic losses at all. According to the Landowners, prospective financial losses can never qualify as "irreparable
It is true that when anticipated economic losses will be recoverable at the end of litigation, then those losses generally will not qualify as irreparable for purposes of preliminary relief. See Di Biase v. SPX Corp. ,
This case is different, because here, Mountain Valley's economic losses would not be recoverable at the end of litigation. "No party contests that, if [Mountain Valley] suffers financial losses as the result of its inability to access the condemned easements, it will not be able to recover those losses in this or any other litigation." N.D.W. Va. Opinion ,
Like the district courts, we think all of this is clear enough from our general case law on irreparable injury and preliminary injunctions. But if there were any doubt, it would be resolved by Sage - which, as the district courts also recognized, expressly treats prospective economic injuries flowing from a delay in pipeline construction as a form of irreparable injury. Indeed, many of the of types of financial injury identified by Mountain Valley in this case - including losses flowing from delays in pipeline service and contractual breach - are precisely the same as those we credited in Sage as grounds for preliminary relief. See
The Landowners' second challenge to the district courts' findings of irreparable injury fares no better. According to the Landowners, Mountain Valley's prospective financial losses flow entirely from the company's voluntary decision to enter into early construction and service contracts, geared toward starting pipeline service well in advance of the FERC deadline. Harms resulting from breaches of those contracts, the Landowners argue, are thus "self-inflicted," and cannot be the basis for a preliminary injunction. Like the district courts, we disagree.
We do not doubt that some forms of "self-inflicted" harm may be discounted or ignored altogether in the preliminary-injunction analysis. See Di Biase ,
3.
Under Winter 's third prong, the district courts were required to weigh the equities, considering the harms the Landowners would suffer if preliminary injunctions issued - that is, if Mountain Valley were permitted to access the condemned land prior to determination and payment of just compensation. The district courts held that the balance of the equities favored Mountain Valley, principally because the Landowners' harms would be the same whether access was granted prior to or only after just compensation was paid. We find no error in the courts' reasoning.
Before the district courts, the Landowners presented affidavits and testimony about injuries to their property - tree-felling,
It is true, as the Landowners contend, that because the process of determining just compensation will be a lengthy one, the grant of preliminary relief means that their property will be disturbed sooner rather than later. But as we held in Sage , that is "simply a timing argument," not an independent injury traceable to the "taking [of] property before determining just compensation ."
We note that, compared to the Western District of Virginia, the other two district courts did not address as directly the potential that immediate rather than postponed possession might be especially harmful to certain Landowners. In particular, the Southern District of West Virginia seems to have misapprehended our holding in Sage as requiring a finding in favor of a pipeline in the context of [Natural Gas Act] condemnation actions. S.D.W. Va. Opinion , at J.A. 2720 ("In Sage , the Fourth Circuit conclusively spoke on this issue in the context of [Natural Gas Act] condemnation actions."). Given the Supreme Court's instruction in Winter that a
Finally, the Landowners point to the possibility that ongoing legal challenges to the Certificate will bear fruit - in which case, they argue, the grant of preliminary relief will have caused them injury by allowing access that later would prove unjustified. The district courts declined to credit this argument, and properly so. As they had explained already in granting partial summary judgment to Mountain Valley on its substantive right to exercise eminent domain, only two entities - FERC and a court of appeals with jurisdiction under 15 U.S.C. § 717r(b) - may stay the enforcement of a FERC certificate pending resolution of legal challenges. "District courts in [Natural Gas Act] condemnation proceedings," by contrast, "do not have authority to consider other legal challenges to the FERC order, [or] ... the ability to stay condemnation proceedings to wait until other legal challenges are resolved." W.D. Va. Opinion , at J.A. 1415-16. The Landowners have not challenged that holding on appeal, and it forecloses their argument here: Any harms that might arise from the pendency of litigation around the Certificate are "not harms that would preclude the grant of immediate possession" to Mountain Valley in a condemnation proceeding. Id. at 1429.
4.
Finally, on the fourth Winter element, the district courts reasonably determined that the preliminary injunctions were in the public interest, as they would allow for expeditious construction of a FERC-approved pipeline. As we explained in Sage , the issuance of a FERC certificate signifies that the Commission - the agency charged with administering the Natural Gas Act - has determined that pipeline construction will advance the congressional purposes behind that Act and "serve the public interest," making available to consumers an adequate supply of natural gas at reasonable prices.
The district courts did not abuse their discretion in applying Sage to the facts of these cases. Mountain Valley's certificate rests on an agency finding that the proposed pipeline will benefit the public by meeting a market need for natural gas,
That is not to say, of course, that a FERC certificate necessarily will be dispositive of the public interest inquiry under Winter . Apart from setting an in-service deadline, a FERC certificate does not address timing, and so cannot establish by itself that immediate possession, as opposed to pipeline construction generally, is in the public interest. But echoing our reasoning in Sage , the district courts here concluded that because delaying construction would delay - or, if Mountain Valley were unable to meet its FERC deadline, frustrate entirely - the public benefits identified by the Commission, the public interest factor favored preliminary relief. See N.D.W. Va. Opinion ,
For the foregoing reasons, we find that the district courts did not abuse their discretion in granting preliminary injunctive relief to Mountain Valley. Accordingly, we affirm the district courts' orders.
AFFIRMED
Notes
The Commission denied the request for rehearing and to stay the Certificate in June 2018, several months after the issuance of the district court orders challenged in this appeal. Mountain Valley Pipeline, LLC, Equitrans, L.P. ,
This opinion typically uses the term "Landowners" to refer to all of the landowners in this consolidated appeal. When used in the context of a particular district court case, however, it refers only to the defendant landowners in that proceeding.
Of the three district court opinions, one is published and two are unpublished. The opinion of the Northern District of West Virginia is published at Mountain Valley Pipeline, LLC v. Simmons ,
Appraisal values ranged from $3,001 for many of the easements to six figures for some. The $3,001 estimate tracks the jurisdictional provision of the National Gas Act, limiting federal jurisdiction to those cases in which "the amount claimed by the owner of the property to be condemned exceeds $3,000." 15 U.S.C. § 717f(h).
Two of the district courts required each deposit to be three times the respective easement's appraisal value, while the third district court required the deposit to be four times the appraisal value.
Among other contentions, the Landowners argue that Sage created a circuit split with Northern Border Pipeline Co. v. 86.72 Acres ,
At the time Sage was decided, we analyzed preliminary injunctions under the balance-of-hardship approach set out in Blackwelder Furniture Co. of Statesville, Inc. v. Seilig Mfg. Co. ,
This unusual posture also addresses the Landowners' argument that mandatory preliminary injunctions - those that alter rather than preserve the status quo - are disfavored. See Taylor v. Freeman ,
We note that the Southern District of West Virginia did not recognize the distinction between the public interest in pipeline construction generally and in immediate access specifically. See Winter ,
