Lead Opinion
OPINION OF THE COURT
On this appeal, we are called upon to determine whether defendant Nova Casualty Company (Nova) is discharged from its surety obligation to plaintiff Mount Vernon City School District (the School District) on the bases that the School District allegedly violated New York’s Lien Law by improperly diverting construction contract payments constituting trust fund assets to a nonbeneficiary and breached the terms of the parties’ performance bond. We hold that under the facts of this case, Nova has not demonstrated that discharge of its surety obligation is warranted. We also consider whether the School District is entitled to attorneys’ fees expended in the prosecution of this litigation, and conclude that the request for attorneys’ fees was properly denied.
L
On December 26, 2003, the School District and defendant DJH Mechanical Associates, Inc. (DJH) contracted for DJH to perform heating, ventilation and air conditioning (HVAC) work at A.B. Davis Middle School for a price of $919,000. The contract mandated that the School District make progress payments to DJH based upon DJH’s application for payment for work performed during the preceding calender month. The School District was permitted to terminate the contract if DJH, among other things, failed to furnish adequate assurance that DJH could complete the work.
The contract also required DJH to obtain a performance bond, which DJH secured from Nova, a compensated surety. The performance bond incorporates the terms of the underlying construction contract and provides that “[t]he Surety shall not
As relevant to the School District’s cross appeal, the contract between the School District and DJH further provides:
“The costs of finishing the Work include, without limitation, all reasonable attorney’s fees, additional title costs, insurance, additional interest because of any delay in completing the Work, and all other direct and indirect and consequential damages incurred by the Owner by reason of the termination of the Contract as stated herein.”
The performance bond as it relates to legal costs provides that
“[t]o the limit of the amount of this Bond, but subject to commitment by the Owner of the Balance of the Contract Price to mitigation of costs and damages on the Construction Contract, the Surety is obligated without duplication for: . . .
“[ajdditional legal, design professional and delay costs resulting from the Contractor’s Default, and resulting from the actions or failure to act of the Surety.”
In June 2004, while the contract work was underway, the School District received a notice to withhold/release payment (notice of cross-withholding) from the Department of Labor (DOL). The notice stemmed from DOL’s investigation of alleged prevailing wage violations by DJH on a previously performed public works project
The School District commenced this breach of contract action against Nova, seeking damages for the cost of completing the project and also attorneys’ fees, and against DJH, seeking damages for its failure to complete the contracted-for work. DJH defaulted.
Nova answered and moved for summary judgment, arguing, among other things, that the School District violated article 3-A of the Lien Law
Supreme Court declined to grant either party summary judgment. In denying Nova’s motion, the court observed that the instant case was distinguishable from Matter of RLI Ins. Co., Sur. Div. v New York State Dept. of Labor (
Both Nova and the School District appealed, and Supreme Court ordered bifurcated trials. The liability phase was tried before a jury in March 2009. The jury returned a verdict in the School District’s favor, finding that DJH breached its contract with the School District by failing to complete its work and waived its right to terminate the contract.
The issues before Supreme Court post-trial were: (1) whether the School District’s $214,000 payment to DOL relieved Nova of liability under the performance bond and (2) whether the School District could recover attorneys’ fees for completing the project and prosecuting its claim in this litigation. Supreme Court held that the School District’s payment to DOL did not excuse Nova’s performance under the bond. The court again emphasized that Nova had not completed performance, and thus had “no right as a subrogee to [the] unpaid Contract Price or any Trust Fund monies that were wrongfully diverted” (
Nova and the School District both appealed, and the Appellate Division affirmed (see Mount Vernon City School Dist. v Nova Cas. Co.,
We granted Nova’s motion and the School District’s cross motion for leave to appeal (
IL
As a general rule, a surety may assert affirmative defenses to an obligee’s claim of breach of contract based on the obligee’s noncompliance with the terms of the performance bond or material alterations to the terms of the underlying contract (see 23 Lord, Williston on Contracts § 61:31 [4th ed]; Tishman Westwide Constr. LLC v ASF Glass, Inc.,
Though it was the early rule in New York that a surety obligation is “strictissimi juris, and [the surety] is discharged by any alteration of the contract. . . whether material or not, and . . . whether it is or is not to [the surety’s] injury” (Page v Krekey,
Here, Nova argues primarily that the School District’s payment to DOL of $214,000 in contract funds violated the Lien Law, and that the improper diversion constituted a breach of contract, which substantially increased Nova’s risk of loss on the performance bond. As such, Nova submits, it was discharged from its duty to perform. Reserving judgment on whether the payment indeed constituted a Lien Law violation, as that issue was not squarely decided by the courts below (see 78 AD3d at
Under article 3-A of the Lien Law, funds received by an owner and/or contractor in connection with a contract for a public improvement must be held in trust to ensure payment of trust beneficiaries, namely, subcontractors, architects, engineers, surveyors, laborers and materialmen, as well as payment of taxes and expenses incurred by the construction (see Lien Law § 70 [1]; § 71 [2]; see also Caristo Constr. Corp. v Diners Fin. Corp.,
However, whether the School District’s payment of contract funds to DOL as DJH’s assignee violated the Lien Law is irrelevant to Nova’s surety obligation, because Nova did not perform by funding completion of the work upon DJH’s default as required under the performance bond. As such, and as found by the courts below, it is not subrogated to the rights of the article 3-A trust beneficiaries as a completing surety and lacks capacity to raise any alleged violation of the Lien Law. This case is therefore wholly distinguishable from those cases on which Nova relies, where we allowed subrogees of trust beneficiaries to assert superior claims to trust assets and recognized their right to invoke the Lien Law to challenge wrongful diversions (see Matter of RLI,
The dissent opines that in so holding we “facilitate [ ] the School District’s participation in [the] long-prohibited practice [of ‘pyramiding’]” (dissenting op at 40). However, nothing we have said condones that practice or insulates the School District from any claims that may properly be asserted by an article 3-A trust beneficiary who, as a result of the School District’s payment of contract funds to DOL, was left unpaid. We simply conclude that Nova, which bears the burden of establishing grounds for its discharge, has yet to show how its surety obligation was impaired. Even if, as the dissent concludes, “[fit is difficult to fathom . . . [that] all trust claims had been paid” (id. at 43), we cannot release Nova from the very obligation it contracted to undertake on a hunch. Nova did not demonstrate that the transfer of funds to DOL resulted in any workers, subcontractors or other article 3-A trust beneficiaries having unpaid claims for which the School District reimbursed them, or that such reimbursement was part of the damages claimed against Nova. Though the dissent finds that we “fail[ ] to provide any explanation whatsoever regarding how the diversion of $214,000 that could have been applied toward the completion of the HVAC job did not harm the surety’s interests” (id. at 44), it is neither our, nor the School District’s, burden to do so.
We thus conclude that the School District did not breach the terms of the performance bond, and that the alleged illegal diversion of trust funds did not excuse Nova’s performance. As surety, Nova breached the performance bond by refusing to complete the project.
m.
On its cross appeal, the School District argues that the lower courts erred by declining to award the School District attorneys’ fees that it incurred in the prosecution of this action because the construction contract and bond at issue provide for recovery of all attorneys’ fees, and because Nova’s breach occasioned the lawsuit. “Under the general rule, attorneys’ fees and disbursements are incidents of litigation and the prevailing party may not collect them from the loser unless an award is authorized by agreement between the parties or by statute or court rule” (Matter of A.G. Ship Maintenance Corp. v Lezak,
Here, paragraph 6 of the bond provides that Nova “is obligated without duplication for” “[additional legal, design professional and delay costs resulting from the Contractor’s Default, and resulting from [Nova’s] actions or failure to act.” The underlying construction contract, which is incorporated by
Accordingly, the order of the Appellate Division should be affirmed, without costs.
Notes
. The project was later determined to be a contract with the Mahopac School District (the Mahopac project).
. Article 3-A provides that funds
“received by an owner for or in connection with an improvement of real property in this state, including a home improvement loan, or received by a contractor under or in connection with a contract for an improvement of real property, or home improvement, or a contract for a public improvement in this state, or received by a subcontractor under or in connection with a subcontract made with the contractor for such improvement of real property including a home improvement contract or public improvement or made with any subcontractor under any such contract, and any right of action for any such funds due or earned or to become due or earned, shall constitute assets of a trust for the purposes provided in section [71]” (Lien Law § 70 [1]).
Section 71 (1) provides that trust assets held by an owner “shall be held and applied for payment of the cost of improvement.” Trust assets held by a contractor or subcontractor “shall be held and applied for [certain specified] expenditures” including “payment of claims of subcontractors, architects, engineers, surveyors, laborers and materialmen” who are trust beneficiaries; payment of payroll and other project-related taxes; payment of project-related benefits, wage supplements and surety bond premiums; and payments to which the owner is entitled (see id. § 71 [2] [a]-[f); [5]). Pursuant to section 72, any transfer or application of funds to a purpose other than those specified in section 71 (1) and (2) is a diversion of trust assets. Such misappropriation constitutes larceny (id. § 79-a).
Dissenting Opinion
In 1930, when the Legislature enacted the predecessor to article 3-A of the Lien Law, it recognized a need to prohibit the damaging practice of “pyramiding” in the construction industry. Because the majority facilitates the Mount Vernon City School District’s (the School District) participation in this long-prohibited practice and inexplicably ignores the surety’s right to be discharged from the performance bond where the School District breached the bond,
Although a school district following the direction of the Department of Labor (DOL) may seem to be cast in a more sympathetic light than a surety seeking to disclaim liability for completing a project upon the default of a construction company, the majority misapprehends the nature of the Lien Law. As the majority acknowledges, it is of no import that the School District may have thought it was acting properly in following the directive of the DOL, because the rule prohibiting diversions of trust assets applies regardless of the intentions of the diverter (see RLI,
Lien Law § 72 (1) provides that
“[a]ny transaction by which any trust asset is paid, transferred or applied for any purpose other than a purpose of the trust . . . before payment or*42 discharge of all trust claims with respect to the trust, is a diversion of trust assets, whether or not there are trust claims in existence at the time of the transaction, and if the diversion occurs by the voluntary act of the trustee or by his consent such act or consent is a breach of trust.”
“Only after all trust claims have been paid or discharged does a beneficial interest in the remaining balance vest in the trustee owner or contractor” (RLI,
Here, the School District has most recently claimed that the payment of $214,000 to DOL was not a diversion of trust assets because all claims had been paid. Nowhere in the School District’s briefs to this Court is this argument mentioned. Rather, the School District argued that the “payment of the subject funds was for a trust purpose—to pay for work performed
Contrary to the majority’s view (that the violation of the Lien Law is “irrelevant”) the School District’s violation of the Lien Law matters, and it matters a great deal. The majority first acknowledges that a surety is not obligated to complete a construction job if it can demonstrate that it has a right to discharge due to the actions of another party, then inexplicably goes on to state that Nova has no right to rely on the School District’s violation of the Lien Law as a basis for discharge because it is not a completing surety. But Nova does not claim that it is “subrogated to the rights of the article 3-A trust beneficiaries as a completing surety” (see majority op at 37), nor does it argue that it has the same rights as a completing surety, and it certainly does not “lack[ ] capacity to raise any alleged violation of the Lien Law” (id. ) as the majority suggests. Rather, Nova simply asserts, and rightly so, that it has the same rights as any other surety—rights that are enforceable well before any possibility of completion arises. Nova was no longer under any obligation to complete the HVAC project once the School District illegally diverted the funds to the DOL. Nova is, of course, entitled to raise the issue insofar as it supports Nova’s legitimate breach of contract defense that, in making the payment,
The Lien Law violation is highly relevant, especially where, as here, the performance bond contains a provision in essence prohibiting diversions of trust fund assets. The plain language of the performance bond demonstrates that the surety sought to insulate itself from “obligations of the Contractor that are unrelated to the Construction Contract.” That language is unambiguous and should be enforced. That the $214,000 was earned as a progress payment does not render the diversion any less a violation of the performance bond’s prohibition on reducing or setting off the balance of the contract price for any of DJH’s unrelated obligations. The majority is under the impression that because the funds paid were earned (and therefore did not represent prepayment or overpayment of contract funds) the performance bond was not violated. However, prepayment and overpayment are simply examples of actions that would have violated the School District’s obligations to the surety. They are not the only actions that would entitle the surety to discharge.
Order affirmed, without costs.
. The construction contract between DJH Mechanical Associates (DJH) and the School District was incorporated by reference into the performance bond and the School District had certain contractual obligations to Nova Casualty Company (Nova) (and vice versa) because the bond was executed for the School District’s benefit:
“[a] suretyship arrangement is, at its core, the confluence of three distinct, yet interrelated, obligations. These obligations are embodied in the tripartite relationship of principal obligor [here, DJH] and obligee [here, the School District]; obligee and secondary obligor [here, Nova]; and secondary obligor and principal obligor. When a secondary obligor is bound to pay for the debt or answer for the default of the principal obligor to the obligee, the secondary obligor is said to have suretyship status. In other words, in transactions giving rise to suretyship status, the secondary obligor [here, Nova] is answerable to the obligee [here,*41 the School District] in some way with respect to a duty, the cost of which, as between the principal obligor and the secondary obligor, ought to be borne by the principal obligor” (Chemical Bank v Meltzer,93 NY2d 296 , 302 [1999] [citations omitted]).
. Indeed, the majority seems to acknowledge that this is not an exhaustive list (see majority op at 36 [noting that “where an obligee . . . increases the risks imposed on the surety by such acts as modifying the duties of the principal-contractor, extending the time for the principal’s performance, or making overpayments or premature payments, the surety may be discharged” (emphasis added)]).
