89 W. Va. 367 | W. Va. | 1921
Stated in somewhat different language, but in effect the same as that contained in the order certifying them, the questions to be discussed are these: Is the property of a county, the court house and jail and the lot on which they stand, within the meaning of the mechanic’s lien law, as amended and reenacted by ch. 6, Acts, 1917, ch. 75, Code 1918? If not, is the county court liable for the unpaid debts due a subcontractor for materials, equipment and labor furnished by him and installed in a court house and jail? The questions the demurrer of the county court of Jackson county raised, and the answer of the circuit court of that county was in the negative.
The Jackson county court contracted with Prescott Construction Company May 24, 1917, seven days after the revised statute became effective, to construct and repair the county court house and jail, furnish all the labor and material and perform all the work necessary for that purpose, according to the plans and specifications incorporated in the contract, and made part of it, for a consideration payable as the work progressed. The original amount was $67,133.00, later
Subsequently, Prescott Construction Company contracted with Huntington Iron Works to furnish some of the materials and perform certain parts of the work provided for in the original and amended contract and specifications, payments therefor to be made upon the same terms and conditions, those to be made to Prescott Construction Company. These contracts the architect, L. J. Dean, approved when submitted for his approval, as required by the agreement with the county" court.
Huntington Iron Works began to furnish the materials and perform the work, it undertook to furnish and do, soon after the date of its contract with Prescott Construction Company, complied with the terms and conditions so prescribed, and completed it November 15, 1919, and Dean accepted it December 31, 1919, as completed; and although the county court paid Prescott Construction Company for the work it was to perform and did perform, the latter company did not pay Huntington Iron Wofks the amount due it, but left unpaid a balance of $6,380.39. For this balance Huntington Iron Works in due form prepared and caused to be recorded in the office of the county clerk of Jackson county a notice of mechanic’s lien, and perfected such lien in all respects in compliance with the mechanic’s lien statute. At least there seems to be no objection as to any lack of formality in the effort to procure a formally perfect lien.
Having become indebted to the plaintiff, The Moss Iron Works, in the sum of $4,242.15, and to the plaintiff, Wheeling Metal & Manufacturing Company in the sum of $1,833.01, in some manner not disclosed in the bill, Huntington Iron Works assigned and transferred to each of. them, out of the $6,640.39, the amounts due them respectively, and to enforce payment of the lien is the object of this suit.
Plaintiffs invoke the' provisions of sections 12 and 14 of chapter 6, Acts 1917, chapter 75, Code 1918, as authority for the liens and the right to enforce them by á sale of the court house and jail, and the ground on which they stand. By section 12, the state board of control, county courts, boards
According to section 14, the contractor is to be deemed and treated as the agent of the owner of the building, or other structure, and the improvements appurtenant thereto, and his interest in the lot on which the building is erected, improved or repaired, or onto which it is removed, and the owner and his property is liable for the full and true value of all work and labor done, and materials, machinery and equipment furnished by a sub-contractor, if the owner fails to require the contractor to execute a bond in the amount at least equal to the reasonable costs of such material, machinery and equipment, and labor performed, or to be performed pursuant to the terms of the contract, or fail to record the contract and bond, when so given, or accepts a bond 'for a less amount.
As the statute before the amendment contained the same general mechanic’s and labor liens provisions, without specific reference to property, real or personal, belonging to the public, or purchased and held for public use, as interpreted in Hall’s Safe & Lock Co. v. Scites, 38 W. Va. 691, it did not
Notwithstanding this broad and comprehensive language, language sufficiently broad and comprehensive to include a county court house and jail, and it was so considered by plaintiff in that case, the circuit court and this court held otherwise, and refused to approve and enforce the pretended lien. This holding is justified by an abundance of authority. Does either section of the revised mechanic’s lien statute warrant the application of any other rule or principle 1 Section 12 contains no terms and no language significant of an intention or purpose to permit a contractor or his subcontractor to acquire a lien upon public property, as a court house and jail, for the default either of the original contractor or another person, firm or corporation, that agrees to furnish and does furnish the material, equipment or labor required in the erection, construction or repair of such a building. It says not a word concerning a lien of any kind or character. Its intended and clearly disclosed purpose is to make it the duty of the corporations and boards therein specified to demand and exact a bond in a definite amount,
And although the language of section 14 may be broad enough to include county courts and other state agencies enumerated in section 12, it does not specifically name them, nor does any other section of the chapter. Section 12 alone does that. Nowhere else is there the slightest reference to the board of control, county courts, boards of education, boards of trustees and other legal bodies, having authority to contract for the erection, construction, alteration or repair of public buildings or other like structures, used or to be used for public purposes. Inclusion by reference or interpretation is not sufficient, when the right to perfect a mechanic’s lien or materialman’s lien upon public buildings is involved. To warrant the creation and enforcement of such a lien against public buddings, the authority must be specific, positive and unmistakable in its meaning and terms. They must leave open no room for construction or interpretation. If the legislature intended to authorize or permit the subjection of public buildings to liens as public property may be subjected, as by pursuing the method prescribed, it could and doubtless would have made its intention clear and explicit. To subject property owned and used by the public for the transaction of public business to mechanic’s liens, the authorization must, according to the general, indeed the almost invariable rule, be unequivocal not inferential. “There can be no mechanic’s lien on public property,” says Boisot, sec. 208, Mechanic’s Liens, “unless the statute creating such lien expressly so provides, since such a lien would be contrary to public policy, and would also be incapable of enforcement, not being subject to forced sale.” To support this statement he cites many decisions. See also, Hutchinson v. Krueger, 34 Okla. 23, 124 Pac. 591, Ann. Cas. 1914 C. 98, note. The statutes construed in these decisions, so far as we have examined them, authorize mechanic’s, artisan’s and laborer’s liens on all buildings and structures. Of course,
Plaintiffs, however, would have us accept their theory, which if tenable, would require such a construction of sections 12 and 14 as would warrant the liens claimed by them. According to plaintiffs, no other construction is permissible or possible in view of the context. That challenge goes direct to the heart of the subject dealt with by the authorities cited and by numerous others that could be cited. As before stated, a statute which has for its purpose the authorization of encumbrances in the form of mechanic’s and other like and similar liens against public property devoted to governmental uses must be explicit and positive. With this condition sections 12 and 14 fully complied, if plaintiff’s argument is meritorious ; but do they 1 Section 12 does, it is true, require a bond where the contract is for. the construction or improvement of property owned, usable and used, or to be used for the transaction of public affairs, but, as we have seen, it need not be recorded as part of the public record. The purpose of such a bond the section -fully discloses; it is for the protection, not of the contractor himself, but of those who contract with him for material, equipment and labor necessary for the completion of his contract. That being its paramount, if not its exclusive, purpose, the- contractor has a material interest in its execution and in insisting upon its execution, as the county court has, notwithstanding the provision exacting it. -But such interest does not begin and end in the contractor, it extends to every one with whom he contracts, where a public building is to be. improved. If a subcontractor undertakes to equip such a building it only devolves upon him to refuse to furnish the equipment, unless the bond required is given, as it is mainly to protect him. While it is true, if plaintiff’s theory is sound, that without such bond the contractor becomes the agent of the county court, and the county court liable to the sub-contractor for the equipment or labor so furnished, yet in that section, and
Nor is there to be found a sufficient basis for such inference in the language of section 9, although its provisions and the provisions of section 12 are similar. The general provisions of the act, considered as a whole, although apparently inclusive, are not broad enough to indicate publicly owned buildings, when construed in accordance with the prevailing weight of judicial authority.
Some significance certainly is to be attributed to the omission in section 12 of the requirement to record in the county court clerk’s office the bond called for in that section. It is to be filed, not with the clerk of the county court for record, but with the secretary, or other custodian of the records and other papers of the governmental agencies therein specified. Whatever influenced the legislature to substitute delivery to the clerk or custodian of the records and papers of such bodies for recordation in the county record office need not be surmised, in the face of the provision to the contrary. The fact remains outstanding that by no provision of the statute considered, is it necessary to record the contract in the county court clerk’s office, when public buildings are the subject of the improvement. When so filed it is available to anyone who may come to inspect it. While in the custody of the clerk, or other like official representative of such bodies, it is accessible to anyone lawfully entitled to know of its contents. Not so, when it is the bond given for the protection of a private owner of property, improved under the terms of a contract.
A second reason will appear upon a reasonable construction of the sections preceding number 12. It is not necessary to enter into detail as to the provisions contained in most of them. Their provisions are general, and have for their pur
But to what extent, if at all, may a contractor or sub-contractor avail himself of the benefit of such a lien on public property of any character, real or personal, usable and used for the transaction of the public affairs of the county, if he can not sell it to raise a fund sufficient to satisfy the lien? The only mode prescribed by law for the satisfaction of mechanic’s liens of any kind is by a sale of the property so encumbered. But section 43, ch. 39 expressly forbids the sale .of “lands, buildings and books belonging to a county and used for county purposes, by execution or other process.” A proceeding for the purpose of enforcement of a lien, created according to chapter 75, is in effect a process, within the meaning of the section cited. This prohibition alone furnishes ample justification of the ruling upon the demurrer.
The discussion by plaintiff’s counsel of the second question certified proceeds upon the theory that even if a mechanic’s lien is not enforceable by a sale of county property, yet, because the county court neglected to exact the bond required by section 12, its neglect imposes liability upon that court, and that to make the liability effective, the decree to be entered in tlie cause should include the county court. The right of plaintiffs to this relief, they base upon the agency brought
As what has been said responds to the question certified, the order of this court will approve the ruling upon the demurrer.
Affirmed.