Two separate appeals from one judgment and one motion to affirm have been docketed as three cases by the above numbers, but by stipulation they are consolidated and considered together.
The plaintiff, Amanda L. Morton, brought suit in the Circuit Court of St. Louis against the Hiram Lloyd Building Construction Company, the Southwestern Telegraph Telephone Company, and the Union Electric Light Power Company, seeking to recover damages on account of the death of her husband, caused, it is alleged, by the negligence of the three defendants. On trial to a jury in the Circuit Court of St. Louis, a verdict was rendered in her favor in the sum of seven *370 thousand, five hundred dollars against the defendant Hiram Lloyd Building Construction Company, and in favor of the other two defendants. A motion for new trial was filed by Amanda L. Morton as against the Southwestern Telegraph Telephone Company, hereafter for convenience called "the Telephone Company," and the Union Electric Light Power Company, hereafter called "the Power Company;" and a motion for new trial was filed by the Hiram Lloyd Building Construction Company, hereafter called "the Construction Company." These motions were overruled at the June term, 1916. On June 26, 1916, the Construction Company appealed from the judgment against it to the St. Louis Court of Appeals, and a short transcript was duly sent to that court. At the same term, on September 29th, the plaintiff, Amanda L. Morton, appealed from said judgment to the St. Louis Court of Appeals and her appeal was duly allowed. A transcript of the judgment and order granting the appeal of the plaintiff, Amanda L. Morton, although ordered by the trial court sent to the St. Louis Court of Appeals, was sent to this court and appears here under the serial number 20143. Those transcripts thus rested in the two courts until July 24, 1918, when the respondents in the plaintiff's appeal, the Telephone Company and the Power Company, filed a joint motion to affirm in the St. Louis Court of Appeals, accompanied by the certificate of the Clerk of the Circuit Court of the City of St. Louis, as provided by Section 2047, Revised Statutes 1909, showing that the judgment had been rendered, as stated above, and the appeal taken. This motion was by the St. Louis Court of Appeals on the same day sustained and the judgment affirmed. Three days later, July 27, 1918, the Construction Company, appealing defendant, filed a motion in said court to set aside the order of affirmance, with suggestions in support of same. To this the other defendants, Telephone Company and Power Company, filed suggestions in opposition. This motion, *371 October 5, 1918, was sustained and the order of affirmance set aside.
On the twenty-eighth day of October, 1918, Amanda L. Morton filed her motion in the St. Louis Court of Appeals to transfer the cause involving both appeals to this court and that motion was on November 19, 1918, sustained and the appeals transferred here where they appear under numbers 21431 and 21432.
The death of Ernest L. Morton, husband of plaintiff, from which arose her claim for damages, occurred on the twenty-sixth day of November, 1915, while he was employed by the appellant Construction Company. The Construction Company, under contract with the city, was at the time engaged in the reconstruction and repairing of a reservoir owned by the city. The reservoir was located in what is known as Reservoir Park; a strip of park surrounded the two basins which constituted the reservoir. The Construction Company had built a fence around the reservoir, dividing the strip of park which surrounded it, and the work was being done inside this inclosure. A line of poles ran from the northwest corner of the property southwardly across the fence to a point inside the park, there being at least two of such poles inside the inclosure. These poles were from twenty-five to thirty feet in height, and each one supported two cross-arms about eighteen inches apart. The upper cross-arms carried a telephone wire; the lower cross-arms carried three or four power wires which were charged with very high voltage of electricity. There was evidence tending to show that the telephone wire and upper cross-arms were owned by the Telephone Company. The defendant Power Company owned the power wires on the lower cross-arms, and through them conveyed current to a transformer and a meter where the current and power were delivered to the defendant Construction Company inside the inclosure. The Power Company had a contract with the Construction Company to furnish power for *372 use in the work which the Construction Company was doing.
On the 12th day of November, fourteen days preceding the death of Morton, the employees of the Construction Company, in the progress of their work, caused the first pole inside the inclosure to be broken off. A few days later this pole was replaced. On the eighteenth day of November, and eight days before the death of Morton, the employees of the defendant Construction Company, while engaged in "fleeting a guy," that is, moving a guy line forward with a pile driver, broke the telephone wire inside the inclosure, between the first pole inside and the first pole outside. The broken wire dropped down beside the first pole inside the inclosure, was gathered up by one of the Construction Company's employees, coiled up and hung on the pole. It remained intact between the first and the second poles inside the inclosure. There is some evidence indicating manipulation of the broken end in wrapping it around the pole. Soon after this wire was broken it began to sag between the first and second poles inside the inclosure. A day or two, or possibly longer, before the death was inflicted, it had sagged to within ten or twelve feet of the ground. In sagging down it came in contact with the power wires. On the twenty-sixth of November, in the afternoon, it was seen to sag to within four or five feet of the ground.
Morton's work required him to be on the ground during the night. He was not a watchman, but what is termed, "the handy man" — the general utility man. It was his duty to see that the machinery was kept in operation and that everything was in proper shape during the night. Among other things, it was his duty to fill the boilers with water. Eight or ten feet from where the telephone wire sagged was a water pipe which came from the reservoir, at which pipe he could get water for the boilers. He went to work as usual on the twenty-sixth of November, at night. About eleven o'clock that night the Construction Company foreman *373 discovered his body lying across the telephone wire with his feet on the ground. Sparks were coming from his leg and body and his clothing was on fire. He was burned in such a way as to indicate that he met instantaneous death by electrocution. Other details in connection with the incident are furnished by the evidence as throwing light upon the issue as to whether the defendants, or any of them, were guilty of such negligence as to authorize a recovery. Such of these as are pertinent will be noticed in considering the proposition urged for a reversal.
The petition alleges a cause of action against each of the defendants in that they were each and all negligent in permitting the wire mentioned to sag and become charged with electricity in such manner as to become dangerous and cause death. There was no claim of contributory negligence on the part of either of the defendants, each of whom answered by a general denial.
I. The jurisdiction of this court is challenged by the respondent-defendants. They move to have case No. 21431 ordered back to the St. Louis Court of Appeals,Appellate Jurisdiction. or the appeal dismissed here, and case No. 20143 stricken from the docket.
Whatever be the modifications by recent adjudications of the ancient doctrine regarding the entirety of a judgment, the rule still obtains that there can be rendered in an action only one final judgment which must finally dispose of the case as to all parties. This is statutory. [R.S. 1909, sec. 2097; Wollman v. Loewen,
In case No. 21431, involving the same appeal as No. 20143, the respondents, the Telephone Company and the Power Company, filed in the St. Louis Court of Appeals the certificate of the Clerk of the Circuit Court provided for in Section 2047, Revised Statutes 1909, as a basis for a motion to affirm the judgment. This certificate did not show on its face a want of jurisdiction in the Court of Appeals; the judgment was affirmed and the order afterwards set aside on it being brought to the attention of the court that it was without jurisdiction. The matter then stood in the St. Louis Court of Appeals on the appeal of the Construction Company, and the appeal of the plaintiff as to the other two defendants. The plaintiff had not perfected her appeal, nevertheless the case was lodged in the St. Louis Court of Appeals by the action of the defendant-respondents. It is claimed by the Telephone Company and the Power Company here that inasmuch as the appeal was not perfected in accordance with the requirements of Sections 2047 and 2048, the Court of Appeals rightly affirmed the judgment. That court had no jurisdiction to make a final determination of the case, and an affirmance would be a final determination. It had authority only to determine whether in fact jurisdiction existed in that court and, having ascertained that it did not, it could only perform the mere formal act authorized by the statute of transferring the case to this court. [Sec. 3938, R.S. 1909; Moberly v. Lotter, 266 Mo. l.c. 464-6; Forsee v. Gates, 89 Mo. App. l.c. 581.] Therefore, on the transfer of the case here, with proper authority to make such transfer, this court acquired and has jurisdiction finally to determine the case represented by the two appeals. *375
II. Even if this court had not acquired jurisdiction by transfer of Case No. 21431 from the Court of Appeals, jurisdiction was lodged here by virtue ofAppeal to Wrong plaintiff's appeal as shown by her transcript inCourt. Case No. 20143.
Plaintiff filed a proper affidavit for appeal during the June term, 1916, when the judgment was rendered against her in favor of the two non-appealing defendants. Her petition disclosed on its face she was suing for ten thousand dollars. The Constitution and the statute contemplated that her appeal should be granted to this court. She deposited with her application for appeal the ten dollars fee required to be paid by the appellant. The court, by an entry of record, sustained her application for an appeal,
but in the face of the statute and Constitution made the record recite that her appeal was allowed to the St. Louis Court of Appeals, which had no jurisdiction over her case, instead of allowing the appeal to this court as the Constitution and statute required. We will not presume that the trial court intentionally violated the law in granting plaintiff an appeal to a court having no jurisdiction of her cause, but on the contrary must presume that that portion of the order granting the appeal to the St. Louis Court of Appeals was the result of oversight ormistake. In any event, if the attention of the trial court had been called to the error it could, undoubtedly, upon proper notice have amended its record to comply with the requirements of the law, even after the case had been appealed to the appellate court. [State ex rel. v. Ellison, 210 S.W. 401, l.c. 403; Johnston v. Ragan,
We now have before us all the records and proceedings of the trial court in respect to this cause. All the parties are now before the court on a consolidated case. The record shows on its face that plaintiff filed a timely and proper affidavit for appeal, and did not ask that her appeal be allowed to the Court of Appeals which had no jurisdiction over her case. Plaintiff has taken all the steps which would have been necessary to present her case to this court had the trial court complied with the law in granting her appeal.
Upon the record thus presented disclosing a palpable mistake upon the part of the trial court, we will treat its record as having been properly corrected so as to show that plaintiff's appeal was granted to this court instead of to the St. Louis Court of Appeals. [State ex inf. v. Clardy, 267 Mo. l.c. 380-381; Tebeau v. Ridge, 261 Mo. l.c. 559; Davidson v. Land Imp. Co., 253 Mo. l.c. 229; State ex rel v. McQuillin, 246 Mo. l.c. 594; Darrier v. Darrier, 58 Mo. l.c. 233.]
III. Both appellants assign the same, and only one, error, which they claim was committed by the trial court in favor of the non-appealing defendants, viz.: that the verdict in their favor was against conclusive evidence of theirKnowledge of actionable negligence, on account of which theDefective Wire. motion for new trial should have been sustained. *377
There was no evidence that either of said defendants knew the telephone wire was broken or that it sagged, and no conclusive evidence that either of them had any reason to know such facts. It was for the jury to say, under proper instructions, whether those companies were negligent in failing to learn and guard against a condition which rendered the electric current dangerous. There were sufficient facts from which the jury might well find, as it did, that the Power Company did not fail to exercise the highest degree of care to prevent injury by its appliances, and that the Telephone Company did not fail to exercise ordinary care in that respect. The verdict is conclusive upon this court.
IV. The appellant-defendant assigns error to the failure of the trial court to sustain its demurrer to the evidence, claiming there was no evidence of any negligence on the partSufficient of the said appellant.Evidence.
The evidence shows that the appellant's employees broke the wire, which subsequently sagged, wound up the end of it in a careless manner which did not prevent its sagging, knew that it did sag and continued to sag more and more, a fact observable to anybody who passed that way. The Construction Company knew that it was receiving a very high power from the electric wires; it knew from the position of the wires in the park that the sagging telephone wire was likely to come in contact with the highly charged wires and become dangerous to anyone within whose reach it should come while on the ground. It was a condition from which a man of reasonable prudence should have foreseen that injury was likely to ensue.
The telephone wire on the upper cross-arms of the pole was broken on the eighteenth day of November by William E. Ahrens, appellant's pile-driver foreman. He ordered the broken end coiled up and hung on the pole by an employee. A few days afterwards, about four or five days before the death of Morton, he noticed *378 that the coil of wire which was hung up on the pole was working loose and he took a piece of marline and supposed he made it fast. On the day he broke the wire he reported the fact to Mr. Gove, superintendent of the Construction Company.
Mattox, another pile-driver foreman, was hauling concrete piles and placing them along the reservoir on Friday, the day preceding the night on which Morton was killed, and saw the coil of wire lying loose at the foot of one of the poles and warned his men to keep away from it. About three o'clock on that day Harry Clark, pile-driver, saw the wire between the poles sagging down from ten to thirteen feet from the ground.
H. Middleberg, construction foreman of the Construction Company, about four or five o'clock on the day Morton was killed, saw the wire sagging down between the poles to about four or five feet above ground. He had been requested by Mr. Ahrens, pile-driver foreman, on the day the wire was broken to take hold of it and throw it aside. He refused because the wire was dangerous.
There was evidence that Morton's duty required him to visit the hydrant within a few feet of the sagging wire for the purpose of procuring water for the boilers.
It was the duty of appellant to use reasonable care to keep the premises where Morton was obliged to work in a reasonably safe condition. As in the case of the other defendants, it was for the jury to say whether, under the evidence, the appellant failed to perform that duty, and such failure caused the death.
The demurrer to the evidence was properly overruled.
V. Error is assigned by the appellant to the admission of the evidence of an actuary who testified by mortuary tables to the life expectancy of the plaintiff at the time of her husband's death, and the expectancy *379
of the deceased at the time of his death. ItLife Expectancy. was shown that her expectancy was 25.27 years and his expectancy was 23.08 years. This was in accordance with the mortuary tables of insurance companies. It was not objected that these tables were different from the tables provided by statute. It is now settled in this State that mortuary tables are admissible in a case of this kind. The actual recovery by the plaintiff must be the pecuniary loss which she has suffered and will suffer by being deprived of the support of her husband during the remainder of their joint lives, and the only way the jury can estimate the duration of their joint lives is by the mortuary tables of both. It is not proper to base the estimate upon the expectancy of the one who is likely to live the longest, but on the one whose expectancy is least. Of course, as has been said, there can be no absolute certainty as to the duration of anyone's life. The tables are simply evidence for the jury to consider in estimating the damages to accrue, damage which at best is more or less conjectural. [Schlereth v. Railway Co.,
It is further objected by appellants that the court erred in permitting the plaintiff to testify to her age and her state of health, also to the age of the deceased and his earning capacity, on the ground that there was no allegation as to those matters. It is held by this court that where damage naturally flows from the injury, which is the basis of the suit, as a reasonable consequence of the same, it need not be pleaded. In case of a death claim it is proper to show the condition of health, earning capacity, age, etc., of the party killed, as well as his habits, without pleading those specific facts. [Boyd v. Railroad,
VI. Appellant asserts there were errors in the admission of certain items of evidence on behalf of the plaintiff, where the plaintiff was allowed to state how much ofGeneral Objection. the deceased's wages were given for her support, that he spent his evenings at home, that she paid for his burial expenses, and that he protected her during the years of their married life.
In referring to the pages in the abstract of the record where this evidence was admitted and the objection of the defendant registered, it appears that the only objection in each case was that evidence was "irrelevant and immaterial." A general objection of that character is not sufficient to apprise the trial court and opposing counsel of the particular reason why the evidence is objectionable so as to authorize review here. [State ex rel. v. Diemer,
VII. Appellant criticises instruction number two, given on behalf of the plaintiff, upon the ground that it didn't require a finding by the jury that the Construction Company knew, or by the exercise of ordinary care could have known,Knowledge of Danger. the telephone wire was liable to come in contact with the power wire of the electric company and knew that such a contact would be dangerous.
The instruction objected to did require the jury, before finding for the plaintiff, to find existence of the highly charged electric wire and the telephone wire which ran on cross-arms of the same poles, "and that the defendant caused and permitted the telephone wire to become loose and sag dangerously near and to come in contact with said power wire, if any, and to become *381 charged with said electric current, if any, and conduct said current to a point near the ground and thereby endanger pedestrians on the ground near said wire."
A finding by the jury that the defendant negligently caused and permitted the condition mentioned is equivalent to a finding that the defendant knew the condition to exist. [Hall v. Mo. Pac. Ry. Co.,
Electricity is one of the most dangerous agencies discovered by modern science and used in conducting power. [Clark v. Railroad, 234 Mo. l.c. 423; Hill v. Union Electric L. P. Co.,
Appellant cites in support of its position the case of Nephler v. Woodward,
This was to illustrate the distinction between a condition which is obviously dangerous so as to charge a party responsible for its existence with knowledge of its dangerous character, and one where such dangerous character must be proven and found by the jury, as the case there under consideration.
VIII. Instruction number seven given on behalf of plaintiff on the measure of damages was objected *382 to as not correctly stating the rule by which the jury could estimate the measure of damages. It reads:
"The court instructs the jury that if you find in favor of the plaintiff you will, in assessing her damages, award her such sum, not exceeding ten thousand dollars, as you find from the evidence will fairly and justly compensate her for all, ifMeasure of any, pecuniary loss you find from the evidence sheDamages. has sustained, or will sustain, as a necessary result of the death, if any of Ernest L. Morton."
Instructions similar in form and of like intendment have been approved several times by this court. [Powell v. Railroad, 255 Mo. l.c. 453-456; Mintor v. Brandstreet Co.,
The judgment is affirmed.
Railey and Mozley, CC., concur.