OPINION
This inverse condemnation case is before the court after argument on defendant’s motion for summary judgment arid plaintiff’s motion for partial summary judgment on the issue of liability.
FACTS
The facts either have been stipulated or they have not been contested in accordance with RUSCC 56(e).
An Operating Agreement incorporated into the Offer To Sell Real Property (the “Contract”) provided at paragraph 4:
It is expressly understood ... that MORTON has retained fee simple title to all of its Weeks Island property, except with respect to the specific property interests being conveyed ... and, accordingly, that MORTON has the full right and title with respect to the remainder of its property at Weeks Island, to utilize the same for any and all business purposes, including — but not limited to — the construction of the New Mine, free from any interference from the activities of the UNITED STATES in connection with the oil storage program, except to the extent expressly set forth in this Agreement.
The Contract recited that plaintiff was to convey for $30 million “title only to the properties ... specifically described” and that plaintiff did not relinquish “its fee simple title, ownership or any appurtenances thereto with respect to its present fee simple title ownership of Weeks Island outside, either vertically or horizontally, of the said properties.”
Because Louisiana law did not recognize a fee simple in a horizontal stratum, such as the parties wished to convey between them, and would have forced the FEA to acquire either fee simple title of the salt dome to the center of the earth or an easement in a horizontal section, the parties agreed that the United States would institute condemnation proceedings in federal district court to acquire the stratum defined in the Contract. The Contract recited that Louisiana law did not affect the ability of the United States to acquire by condemnation fee simple title to the described interest “without, in the process, acquiring fee simple title or any other property interests to any areas outside those described ... which, by such specific descriptions, limits the scope of the properties intended to be acquired by the UNITED STATES.”
The Operating Agreement, inter alia, provided for the coordination of the parties’ activities and, in paragraph 5, that each party would
(b) [ejxercise due care and undertake all prudent precautions so as not to endanger*627 person or property or cause injury, death, loss or property damage at Weeks Island; (c) Comply with all applicable requirements of MESA, or its successor; (d) Coordinate their facilities and activities so as to avoid any injury, death, loss or property damage, and so as to minimize any disruption of activities at Weeks Island, except to the extent expressly provided for in this Agreement.
Owing to government time constraints, the Operating Agreement was concluded and condemnation proceedings instituted before the results were published of the geotechnical survey commissioned by the FEA to determine the necessary sill thickness between the storage cavern and the new mine. An FEA memorandum dated June 1, 1977, covering a meeting between officials of the FEA and plaintiff, supports plaintiff’s assertion that a pressing timetable existed for the commencement of oil storage. The General Accounting Office in a report issued on August 14, 1978, entitled “Questionable Suitability of Certain Salt Caverns and Mines for the Strategic Petroleum Reserve” [hereinafter cited as the “GAO Report”], also stated that officials of MESA’s successor, the Mine Safety and Health Administration (“MSHA”), had found that the FEA’s “mine testing program was not adequate.”
The FEA-commissioned survey, published in November 1977, after the district court’s order for delivery of possession on October 20, 1977, advised against mining below the storage cavern; moreover, another study undertaken by MESA’s successor MSHA concluded in July 1978 that at least a 650-foot sill was necessary to protect against the danger to the cavern of “blowouts” unless facts were provided which would assure the adequacy of a lesser thickness. Blowouts, which were not foreseen by the parties in agreeing to the original sill, are holes in the ceilings of salt mines, some hundreds of feet high, which result when blasting in gas-bearing salt formations causes more salt to be broken than planned. Such an occurrence is unpredictable, and if one of these holes were to extend up to the oil storage cavern, an obvious catastrophe would result. Before the Louisiana court ordered delivery of the property conveyed on October 20, 1977, however, plaintiff had commenced construction on the new mine within the additional 350-foot area which, together with the original sill, would have formed the 650-foot recommended sill. (This additional 350-foot area will be referred to hereinafter as the “additional sill.”)
In a memorandum to the Secretary of Labor, MSHA Assistant Secretary Robert B. Lagather stated in mid-1978, referring to DOE’s operating the oil reserve facilities without adequate buffers, that “[s]hould the present course of action be continued by DOE, we will have no recourse other than to issue withdrawal orders as mandated by ... the Federal Mine Safety and Health Act of 1977....”
Among other efforts to persuade MSHA that the additional sill was not necessary, plaintiff commissioned its own study to assess whether the additional sill was required to guard against blowouts. The study results failed to persuade MSHA that a lesser sill was adequate, although MSHA officials as of early 1979 indicated their willingness to discuss the matter further with plaintiff and to review any other tests or studies plaintiff wished to submit. The parties agree that MSHA’s position concerning the minimum 650-foot sill is the same today as it was in 1978-79. By letter of May 18, 1979, plaintiff advised MSHA that, as a result of the MSHA study, plans for an alternate mine had been developed and demanded compensation for the additional sill. Thereafter, plaintiff filed an amended answer in the condemnation action claiming additional compensation for its loss. Upon defendant’s motion for summary judgment asserting lack of jurisdiction, the district court declined jurisdiction over plaintiff’s claim, which it deemed one for inverse condemnation cognizable in this court, rejecting plaintiff’s characterization of the claim as one for severance damages arising from the original condemnation.
1. To support liability in its favor, plaintiff argues that the district court’s decision that its claim did not arise from the original taking was based on an affirmative finding that, instead, a new taking had occurred. According to plaintiff, the latter determination should be given collateral estoppel effect in this proceeding because it was essential to the district court’s determination that jurisdiction was lacking. Defendant counters that the district court merely was characterizing plaintiff’s claim and that it would have been impermissible for the district court, in the process of deciding that it lacked jurisdiction, to adjudicate a claim for an additional taking. According to defendant, the district court thereby would have enlarged the taking beyond the interests specified in the Government’s complaint in condemnation for which alone that court had jurisdiction to award compensation.
The district court’s observations may be apt, but they do not foreclose this court from its independent inquiry as to whether a compensable taking has occurred. The issue decided by the district court was solely jurisdictional and did not slice through to the merits. See Mother’s Restaurant Inc. v. Mama’s Pizza, Inc.,
2. Plaintiff cites the district court’s Order for Delivery of Possession as granting the Government possession only “in accordance with the attached ‘Operating Agreement.’ ” Plaintiff argues that the “entire thrust” of the Operating Agreement is to allow, and even facilitate, plaintiff’s mining beneath the cavern; that the Contract and Operating Agreement provisions expressly reserving the uncondemned strata to plaintiff evince this intent; and that the Government made various representations to the same effect. These contractual provisions and representations, plaintiff contends, show an agreement between the parties giving plaintiff the right to mine the additional sill, which defendant has breached.
Plaintiff argues that the Government’s “need for a safe barrier to contain the oil so restricts and interferes with Morton’s use of its property as to constitute a taking of the 350-foot additional sill .... ” The district court summarized the matter well:
[T]he taking is a clear enlargement of the declaration of taking; the government is using the 350-foot portion ... as fully as it is using the 300-foot portion of the sill which was described in the declaration of taking....
... [T]he damages claimed here result from total, exclusive use of the remainder by the. government. When the property taken by the government is viewed as a container for oil, it is untenable to argue that the government only uses or exercises dominion over the inner volume of that container ....
United States v. 429.83 Acres of Land, Civ. No. 771149, slip op. at 6 (W.D.La. Mar. 16, 1983).
Defendant contends in its motion for summary judgment that MSHA’s action in preventing plaintiff from mining in the additional sill is an exercise of the police power and, as such, is noncompensable. Plaintiff opposes, arguing that an exercise of police power may be compensable, citing Pennsylvania Coal Co. v. Mahon,
“The term ‘police power’ connotes the time-tested conceptional limit of public encroachment upon private interests.” Goldblatt v. Hempstead,
“[T]he predominant characteristic of this area of law is a welter of confusing and apparently incompatible results. ... ” As the Supreme Court itself has acknowledged, “ ‘no rigid rules’ or ‘set formula’ are available to determine where regulation ends and taking begins.” Sax, Takings and the Police Power, 79 Yale L.J. 36, 37 (1964); see Yuba Goldfields, Inc. v. United States,
An old line of cases bases the distinction between a compensable taking and the exercise of the police power on whether the governmental action operates to secure a benefit for or to prevent a harm to the public (the “noxious use” theory). See, e.g., Mugler v. Kansas,
Many regulations of general impact, such as zoning laws, have been held to be noncompensable exercises of the police power on the similar theory that they secure an “average reciprocity of advantage,” Penn Central Transport Co.,
Even when the challenged regulation was of widespread or general application, the Supreme Court has held that if it goes too far in depriving an owner of the use of his property, a regulation will be held to constitute a taking. The classic formulation of this rule was in Pennsylvania Coal Co.,
Diminution in property value standing alone, however, does not constitute a taking. Penn Central Transport Co.,
In this case plaintiff clearly has no economically viable use of its salt besides mining it.
In Penn Central Transport Co.,
In the instant case, the restriction against plaintiff’s mining operations plainly is for the benefit of a specific public work. The Government is using the additional sill in exactly the same way it is using the original sill which it condemned and paid for. If plaintiff is not entitled to compensation for its inability to mine the additional sill, then the compensation paid to plaintiff when the original sill was condemned was a gratuity.
4. Defendant argues that plaintiff has failed to exhaust administrative remedies by challenging MSHA’s determination under the revised procedures set out in 30 U.S.C. § 815(d) (1976) (Supp. 1 1977), which call for an administrative hearing upon issuance of a challenged order by MSHA.
The short answer is that MSHA’s determination is not at issue here. Plaintiff is not seeking premature judicial review of the MSHA agency action, but is claiming just compensation for the loss of its property resulting from MSHA’s decision with which it has no quarrel. Although defendant posits that MSHA might be willing to approve a lesser sill, “taking” jurisprudence does not require a party seeking compensation to challenge the underlying governmental action solely to reduce the amount of a resultant “taking” if the Government’s actions otherwise amount to a taking.
Adopting the position that the additional sill might not be necessary after all, defendant argues that “[ujntil it has probed the state of the art information available, and presented this information to MSHA, Morton cannot claim it has truly been prevented from mining the 350 feet of salt strata at issue.. ” Defendant continues that MSHA has not actually forbidden plaintiff to mine the additional sill, but merely made known its position that such mining would be unsafe. Plaintiff has already commissioned one study in an effort to show that the extra sill is unnecessary. MSHA informed plaintiff that, if anything, this study supported MSHA’s conclusions. Over four years later, MSHA still has not changed its position. Although MSHA announced its willingness to revise its opinion should plaintiff come forward with new evidence, there is nothing in the record to suggest that the possibility of some day proving the adequacy of a lesser sill is anything more than speculative. The right to just compensation does not depend on the Government’s action assuming such formal garb as a final administrative order, but only upon Government action having the effect of an exercise of the eminent domain power. See Yuba Goldfields, Inc. v. United States,
Plaintiff is prevented from excavating the new mine not only by MSHA’s de facto prohibition, but also by the danger of causing an inundation of oil onto the heads of its own miners, as revealed by the MSHA study. Thus, the Government’s storage fa
[Although there may be no official intention to acquire any property interest, certain governmental actions entail such an actual invasion of private property rights that a constitutional taking must be implied.
Eyherabide v. United States,
CONCLUSION
Based on the foregoing, plaintiffs motion for partial summary judgment is granted based on Count I of its complaint and is otherwise denied. Defendant’s motion for summary judgment is denied.
IT IS SO ORDERED.
Notes
. The proper interpretation of one contractual provision is disputed. See infra note 2.
. In particular, plaintiff faults defendant with violation of the provisions of the Operating Agreement, which require the parties not to endanger each other’s operations, by its failure to acquire the "additional sill needed to protect plaintiffs subjacent mining from inundation. Defendant argues that paragraph 5(c), in which the parties agree to “[cjomply with all applicable requirements of MESA” embodies a calculated risk taken by plaintiff that MESA (or its successor MSHA) would later require an additional sill, thereby thwarting plaintiff’s plans for the new mine. Defendant also makes the unsupported assertion that the $30 million was “for all claims,” which is contradicted both by the Contract language, quoted supra at 2 (evidencing a limited acquisition), and by joint stipulation no. 28 (evidencing payment for the mine and original sill only). Plaintiff retorts that since it was already bound to obey MSHA directives, the quoted provision really was in
Contractual provisions are to be construed in their context, looking at the document as a whole. See National Railroad Passenger Corp. v. United States,
. The issue to be tried, as framed by defendant, was
[w]hether Morton had reasons independent of, and not addressed by, the MSHA Task Force recommendation for not mining in the additional 350-foot buffer area. Defendant submits that because of other problems connected with mining in the 350-foot buffer area, Morton may have decided voluntarily not to mine there.
. Defendant did not oppose plaintiffs summary judgment motion on the ground that a genuine issue existed as to an alternative use. See supra note 3.
. Having drawn a distinction between the Government’s role as an “arbitrator” between conflicting activities in the private sector and its role as an “enterpriser” operating schools, building roads, maintaining an army, and acquiring assets and resources, Sax proposed:
[W]hen economic loss is incurred as a result of government enhancement of its resource position in its enterprise capacity, then compensation is constitutionally required .... But losses, however severe, incurred as a consequence of government acting merely in its arbitral capacity are to be viewed as a noncompensable exercise of the police power.
Id at 63. Sax based his proposal on the argument that the fifth amendment guarantee was intended not to protect property values or alleviate economic distress caused by governmental action, but as a safeguard against arbitrary, despotic, and self-aggrandizing government. The proposed rule also has the advantage that it gives content to the phrase “for public use” in the language of the fifth amendment.
. Although it is true that the original sill was sold as a container for the cavity to store oil and that the parties did not foresee the blowout phenomenon, the parties stipulated that the original sill was also intended to satisfy MSHA’s requirements.
. Defendant’s reply brief reprinted what it represents to be an exerpt from a government laboratory study conducted at Weeks Island in 1979 indicating that a 300-foot sill was adequate given the blowout phenomenon historically observed there. The parties did not stipulate to the admissibility of any such document; plaintiff challenges its authenticity; consideration of the reference is proscribed by RUSCC 56(c); and under flV.H. of this court’s “Order Governing Proceedings Before Trial,” entered on May 23, 1983, the proponent of summary judgment is required to submit documentary evidence to support its motion.
. Plaintiff also argues cogently that the Government has the responsibility of challenging an administrative decision which requires the DOE to purchase the additional sill to fulfill its obligations under paragraph 5(c) of the Operating Agreement. See supra note 2.