This аppeal is from a grant of summary judgment in favor of defendants. We affirm.
In September 1981, defendants entered into a written contract with Nourjian Building Company (Nourjian) for the construction of a vacation home in Stowe. Defendants agreed to a contract price of $225,000. Nourjian was to complete performance by February 1982. Plaintiff, Morrisville Lumber Company, provided building materials and supplies on an open account to Nourjian. Nourjian had two accounts with plaintiff: a “general” account and an “Okcuoglu” account. A contract dispute between defendants and Nourjian over certain modifications and the completion date ultimately led to Nourjian’s termination in August 1982. Defendants thereafter completed construction on their own. Plaintiff seeks to recover frоm the defendants the unpaid balance for the materials and supplies which it had provided to Nourjian.
In August 1982, plaintiff filed a contractor’s lien against defendants’ home for the amount due on its “Okcuoglu” аccount; it did not include the amounts due on Nourjian’s “general” account upon which materials for defendants’ house were also charged. The lien was never perfected. In September 1982, plaintiff brought suit against Nourjian for the materials and supplies it had provided under both accounts. The plaintiff obtained a judgment by default against Nourjian for the amounts due for materials furnished on the job, which hаs not been satisfied.
The plaintiff then brought this action against defendants for the amounts plaintiff had been unable to collect from Nourjian. Plaintiff and defendants each filed motions for summary judgment which were denied. A later request for reconsideration of the motions was also denied. After additional discovery, defendants filed a renewed motion for summary judgment which was also denied. Thereafter, the court, on its own motion, reconsidered its earlier denial and granted summary judgment in favor of defendants.
Plaintiff’s first argument is procedural. Plaintiff contends that the trial court erred by reconsidering, on its own motion withоut a hearing, its earlier denial of defendants’ motion for summary judgment. As indicated, the trial court had denied summary judgment on three separate occasions prior to granting the motion in favor of defendants. It is plaintiff’s contention that V.R.C.P. 60(b) exclusively governs relief to be granted from the denial of a summary judgment motion, that no criteria required by Rule 60(b) for relief were present, and that Rule 60(b) has no provision allowing a court to reconsider an earlier denial on its own motion.
Plaintiff’s argument necessarily implies that the denial of a summary judgment motion is a final judgment. The denial of a motion for summary judgment, however, is an interlocutory order, and is not appealable as a matter of right. See
In re Pyramid Co.,
Plaintiff nevertheless contends that it was inappropriate for the court to have reviewed and granted defendants’ motion where it had beеn earlier denied. Procedurally, this was not error. The court had additional materials before it. See
United States
v.
Horton,
Our standard on review of a motion for summary judgment is the same standard as applied by the triаl court: summary judgment is only appropriate when the materials before the court
clearly show that there
The trial court properly determined that no genuine issue of material fact existed concerning Nourjian’s alleged status as defendants’ agent.
Paragraрh 10.1 of the Nourjian contract with defendants specified that “the contractor (Nourjian) shall supervise and direct the work, using his best skill and attention. The Contractor shall be solely responsible for all сonstruction . . . and for coordinating all portions of the work under the contract.” Paragraph 10.2 provided that “the Contractor shall provide and pay for all labor, materials, [and] equipment . . . .” Plаintiff relies heavily on the fact that Nourjian testified in deposition that he believed he was the defendants’ agent. His belief, however, does not preclude the court’s determination as a matter оf law that no agency relationship existed, where such a determination was clear from the evidence before the court. See, e.g.,
Frank W. Whitcomb Construction Corp.
v.
Cedar Construction Co.,
Plaintiff’s second argument is that it is entitled to equitable relief because defendаnts have been unjustly enriched through the use of materials that are now part of defendants’ home, and because the contractor’s lien statute, 9 V.S.A. § 1921, does not provide an adequate legal rеmedy.
The plaintiff relies on
Circus Studios, Ltd.
v.
Tufo,
The equitable doctrine of unjust enrichment rests upon the principle that a person should not be allowed to enrich himself unjustly at the expense of another.
Legault
v.
Legault,
Plaintiff further argues that a genuine issue of fact exists as to whether the money paid by defendants to Nourjian was specifically earmarked for supplies plaintiff provided Nourjian. Simply stated, it makes no difference. Defendants paid Nоurjian for all benefits received from Nourjian. Defendants were not therefore unjustly enriched. The success of a claim for unjust enrichment depends on the particular facts and circumstancеs of each case. This is not an appropriate case for such relief. To allow plaintiff to recover in these circumstances would be to require defendants to pay twice. Nо genuine issue of material fact exists as to plaintiff’s unjust enrichment theory.
Plaintiff’s reliance on
Pike Industries, Inc.
v.
Middlebury Associates,
Affirmed.
