9 Utah 70 | Utah | 1893
The owner of a lot in Salt Lake City made a contract with a builder to erect a residence thereon, and the appellants and respondent were all sub-contractors in the first degree under the principal contractor. They all furnished material for use in the erection of the building, and, upon the principal contractor’s failure to pay in full therefor, filed notices of mechanic’s lien against the property. Suit was brought by these parties, and the cause was tried in the third district court on an agreed statement of facts. On an accounting between the owner of the property and the principal contractor it was ascertained that there was due the contractor the sum of 12,290, and by. agreement of the appellants and respondent the owner’s property was released of the liens upon his payment of that sum into court. The property of the owner having been released, the principal question to be determined is the right of priority to the fund paid into court as between the sub-contractors. The facts agreed upon between the several parties, sub-contractors, are, in substance, that the amounts due from the principal contractor to Spencer, By water & Co. is §442.30, to Morrison, Merrill & Co., $200, and to the Carey-Lombard Company, $4,396; that the several parties filed and had recorded against the property mechanics’ liens, respectively, December 22, 1890, November 15, 1890, and September 17, 1891; that the same parties commenced to furnish materials, respectively, on July 1, 1890, July 15, 1890, and on May 5, 1890; that they are sub-contractors of the first degree; and that all the liens were filed for record within 40 days from the date of furnishing the last material. Upon this statement
The sole question raised is as to whether the lien of each of the several claimants attaches on the date of filing the notice for record, or whether it attaches on the date of furnishing the first material. Section 1 of the act approved March 12, 1890, (Sess. Laws Utah 1890, p. 25, c. 30,) provides “that whoever shall do work or furnish materials by contract, express or implied, with the owner of any land, to any amount, for the construction, enlargement, alteration, or repair of any building or other structure upon such land, or in making any other improvements,' or in doing any other work upon such land, as stated in the following sections, shall have a lien1 upon such land, building, structure, and other improvement1 for the amount and value of the work so done, or materials so furnished, to the extent of the interest or claim of such owner thereto at the time of the commencement to do such work or to furnish such materials. Said lien shall likewise attach to another or greater interest in any of such property acquired by such owner at any time subsequent to' such commencement to do work or to furnish materials, and before the establishment of said lien by process of law,” etc. From this section it would appear that the legislature intended to. limit the lien to such persons as had either express or implied contracts with the owner of the land, and that such persons should have a lien for such materials or work to the extent of the owner’s interest or claim in the property “at the time of the commencement to do such work or furnish such materials,” and such lien is extended to any other or greater interest which the owner
But section 2 of the"same"act provides: “Whoever shall do work or furnish materials by contract, express or implied, with the principal contractor mentioned in the preceding section to any amount, for any of the purposes mentioned in the preceding section, shall be deemed a sub-contractor in the first degree, and shall have a lien upon any and all such property, in like manner as said contractor.” This is a provision for the sub-contractor, and it defines his status to be precisely the same as that of the contractor mentioned in the first section. The appellants and respondent herein are subcontractors of the first degree, and their rights are subject to the provisions of this section. The next section provides for sub-contractors in the second degree, and then follow other sections, which define the classes of property which are subject to lien, and the pérsons who may avail themselves of the law in regard to liens. Then follows section 10, which provides: “Any party claiming a lien shall file in the office of the recorder of the county wherein said land is' situated a statement containing — first, a notice of
Counsel for appellants contend that such lien does not attach until the date of filing the statement and notice, and that, in order for the lien to attach at the time of commencing to do work or to furnish material, it is necessary for the claimant to file a statement as provided in section 12, which reads as follows: “Any sub-contractor of either degree who shall intend to do work or to furnish
This section is limited to sub-contractors in either degree, and simply provides an additional safeguard if they choose to avail themselves of it. If a person enters into a contract with a contractor of a higher degree to do work or to furnish materials, and does not engage to enter upon the performance of it until at some future day, he may file this statement, and from the time he does file it “he shall have a lien for such work thereafter done or for such materials thereafter furnished by him, not exceeding the sum stated as the probable value thereof.” The effect of this is to protect him against, and to give him priority over, any other sub-contractors who'might commence to do work or to furnish materials between the date of his making
It is evident, from a careful consideration of the law in question, that the legislature intended to augment, rather than abridge, the rights of the laborer. The conclusion is that the word “may” was used in its ordinary sense, and that the provision of section 12 is permissive, and not mandatory.- The claimant may avail himself of it or not, as he chooses. If he does not, it will in no way interfere
Those above mentioned appear to be all the sections which are material to the determination of the question raised in t this case. While casual reading may develop some doubt as to the effect which ought to be given to their several provisions, yet more deliberate consideration has a tendency to point out the real intention of the legislature in enacting this law. Such intention cannot be ascertained by a consideration of the several sections separately. The whole act must - be construed together,