295 N.W. 720 | Wis. | 1940
Lien foreclosure. This action was begun on July 5, 1939, by H. S. Kaliher, plaintiff, against P. D. General Contractors, Inc., city of Rhinelander, and fifteen other lien claimants, defendants, under sec.
The claim of Kaliher was noticed for trial at the general term beginning September 18, 1939. The case was called for trial on November 13, 1939, having been twice postponed. Counsel appeared for the plaintiff, for General Contractors, for the city of Rhinelander, for L.C. Shea Company, and for Sutliff Lumber Supply Company. Upon the opening of the trial the court's attention was directed to the fact that on November 11, 1939, an affidavit of prejudice had been filed on behalf of General Contractors. Thereupon counsel for General Contractors stated that Mr. Pacholski, president of General Contractors, could not be present and that "they are relying upon the efficacy of the affidavit of prejudice, and insist upon change of venue."
After some discussion the court held that the affidavit was not filed within the statutory period. After considerable colloquy between the court and counsel, the court directed that the trial of the claim of the plaintiff be proceeded with. Evidence was taken on behalf of the plaintiff. The court found the amount of dirt excavated and backfilled under the contract; that the amount due at the contract price was $3,079.75; *516 that at the instance and request of General Contractors the plaintiff performed extra services of the value of $135.20; that plaintiff had been paid $1,589, and there was a balance due of $1,625.95, from which should be deducted $60 on account of the use of a steam boiler, leaving a net balance of $1,565.95.
The court also found that the plaintiff notified the clerk and treasurer of the defendant, city of Rhinelander, on the 12th day of April, 1939, before any payment was made to the defendant, General Contractors, and that the plaintiff gave due notice of his claim on account of the contract and the work done thereunder.
As a matter of law the court concluded that the plaintiff was entitled to judgment for the sum found due with interest from January 1, 1939, together with $50 costs and disbursements; that plaintiff is entitled to a lien pursuant to sec.
"That the defendant city of Rhinelander, when the rights of all claimants under section
Judgment was entered on February 13, 1940, from which the defendant, P. D. General Contractors, Inc., appeals. The first contention of General Contractors is that the court was in error in failing to change the venue of the action when an affidavit of prejudice was filed on November 11, 1939, by General Contractors. There are two answers to this contention: First, the affidavit was not timely filed; second, it was not joined in by all the defendants on the same side.
Sec. 261.08 (3), Stats., provides:
"When the judge named in the affidavit is the presiding judge of the circuit, such affidavit must be filed and motion thereon made on or before the first day of the term, at which the case is triable, or within ten days after the case is noticed for trial. . . ."
The term in the city of Rhinelander in Oneida county opened on the 18th day of September, 1939. The case had been noticed and put on that calendar. Upon being reached, provision was made for impleading other lien holders and the case continued until the 24th day of October. There was another continuance and the case was finally set for trial on the 13th day of November, 1939, and all parties given two weeks' notice. The affidavit of prejudice was made on behalf of General Contractors and filed by direction of counsel not of record.
In Will of Rice (1912),
"On the appeal by defendants composing the firm of Nath. Pereles Sons, the point is made that the court erred in denying their motion for a change of venue. They were proper and necessary parties. In such situation a change of venue is not grantable except upon the application of all upon the same side. All being necessary parties to the main controversy to which the issues as to separate defendants, including Nath. Pereles Sons, were incidental, making several judgments probable though parts of one general decree *518 covering the chief controversy, the action could not be split up and part tried in one place and part in another. It was an inseparable controversy with a major issue and several minor ones germane thereto. In such cases, an application for a change of venue by one of several on the same side, or similarly interested, is not within the statute. [Citing cases.] All parties who have appeared, and are not merely nominal; but, are, really, interested in the controversy on one side though not necessarily on the same side of the record, constitute one party within the meaning of sec. 2625 [261.08], Stats., and must act in harmony, though the affidavit may be made in their behalf by any one on behalf of the others, the motion being in behalf of all."
Here there were complaints, cross complaints, answers, and replies. Conceding that all lien claimants may within the rule laid down in Will of Rice, supra, be on the same side, certainly the defendants, city of Rhinelander and General Contractors, are in some respects on the same side and in other respects not. The cross complaint of General Contractors and the answer of the city of Rhinelander disclose that their interests were to some extent adverse. Under the circumstances of this case even if the affidavit was timely filed, which it was not, General Contractors was not entitled to a change of venue for both reasons. While it is not a ground for denying a change of venue, it appears that the affidavit in this case was filed for purposes of delay. This is a procedure which cannot be approved. Counsel of record very properly refused to file the affidavit of prejudice for purposes of delay.
The second contention of General Contractors is that the court erred in failing to continue the trial of Kaliher's claim. We have examined the record from which it appears that it was a matter wholly within the discretion of the trial court and we find no grounds upon which it can be said that the trial court abused its discretion, especially so as the trial had been twice postponed and the plaintiff had witnesses in attendance who had come from long distances at considerable *519 expense. General Contractors it appears was trying to dictate the course of the trial for its own convenience.
The next contention is that the court erred in permitting the plaintiff Kaliher to enter judgment against General Contractors. It is the contention of General Contractors that only one judgment may be entered; that all the claims must be tried and judgment entered thereon simultaneously. We think this contention is not well taken. This is an equity case and the procedure is largely within the control of the trial court. Here there were a number of different lien claimants as to each of which there would be separate issues, one having no relation to the other. What the court proceeded to do was to try out these various claims. The judgment in this case adjudicated the amount of plaintiff's claim and it was further provided that the plaintiff have a lien upon the money and funds now or thereafter to become due from the city of Rhinelander but the judgment further provides:
"If the amount so found due the defendant P. D. General Contractors, Inc., is not sufficient to pay said judgment in full, then that the same be prorated."
This was to occur,
"when the rights of all claimants under section
This judgment is interlocutory in its nature. At some time in the future the court will determine when payment shall be made. When payment is made all lien claimants will be before the court and if the sum found due and owing General Contractors is insufficient, each will receive his pro rata share. We discover no prejudice to General Contractors in so proceeding.
It is next contended that the court erred in entering judgment on the findings. We have examined the findings and it is considered that the findings sustain the judgment. *520
The notice of motion was as follows:
"Take notice that the defendant, P. D. General Contractors, Inc., will on the annexed affidavit apply to the Hon. GEORGE J. LEICHT, circuit judge, and the circuit court above named on the 25th day of May, 1940, at 10 o'clock in the forenoon for all order," etc.
The affidavit upon which the motion is based is attacked on the ground that the matters stated therein were not within the knowledge of the affiant. While the language of the affidavit is not in proper form, still if it had been upon information and belief it would no doubt have been sufficient. It sufficiently appears that the reason that the time for settling the bill of exceptions should be extended is that the defendant has been unable to procure a transcript of the evidence on account of *521 illness of the reporter. While the affidavit might have been in the usual form and more explicit, we think it was sufficient.
Notice of the hearing of the first motion with the supporting affidavit was served by mail on the 17th day of May, 1940, and was received by plaintiff's counsel on May 20, 1940. The hearing was to be held on May 25, 1940, five days after the receipt of the notice. The service was clearly defective. Sec. 269.36, Stats. provides:
". . . If service be made by mail, the time shall be double the time required or allowed in case of personal service."
If service is made personally, eight days' notice is necessary (sec. 269.31); if by mail the statute requires sixteen days' notice.
The plaintiff also contends that the notice of motion was defective in that it designated no place of hearing. Concededly, the notice of motion should designate the place of hearing. It is the contention of General Contractors that the venue of this action being in Oneida county, it is to be implied therefrom that the motion was to be brought on for hearing at the courthouse at the time stated. There are cases so holding. 42 C.J. p. 483, § 53. However, none of them deal with a factual situation such as exists in this case. In this state, every term in each county is a special term for every other county in the same circuit (sec.
In response to plaintiff's contention, General Contractors urge that the motion of plaintiff to set aside the order of May 25, 1940, was not properly served. In response to that contention it is sufficient to say that General Contractors appeared and resisted the motion. Where there is a general appearance, of course there is a waiver of the defective service.
General Contractors further argue that an order extending the time for settling a bill of exceptions is not an appealable order. Just why this contention should be made in the face of three decisions of this court that an order granting or refusing to grant extension of time for settling bill of exceptions is appealable, we are not able to understand. Wood v.Blythe (1877),
The plaintiff having received no notice of the place where the order was to be brought on for a hearing, the notice not having been served within the time required by statute, the court was in error in denying plaintiff's motion to vacate the order of May 25, 1940. So there may be no *523 misunderstanding it should be said that we do not now review the order of May 25, 1940, but merely ascertain whether it was a valid, effective order. Orders are not reviewed on their merits on a motion to vacate them.
The merits of this controversy are submerged by the unusual number of procedural questions which are involved. Most, if not all, of these might have been avoided by reasonably careful attention to the rules of practice. This court avoids disposing of the rights of parties upon matters of practice if that is reasonably possible. While in a particular case the application of procedural rules may seem to be inconsequential and unnecessary, if procedural rules were not enforced the rights of parties would be still further jeopardized. If General Contractors has not had its day in court it is its own fault and it has no just grounds for complaint.
By the Court. — Upon the appeal of General Contractors, the judgment is affirmed. Upon the appeal of the plaintiff from the order denying his motion to vacate the order of May 25, 1940, the order is reversed, and the bill of exceptions is stricken because not settled within the time limited by statute.