467 A.2d 870 | Pa. Super. Ct. | 1983
This appeal involves several challenges to the lower court’s assessment of damages resulting from contracts entered into by appellant, a builder, and appellees, contractors. We find no merit in appellant’s contention that the lower court erred in failing to consider payments already made to appellee; however, we must remand for findings of fact in order to review appellant’s remaining contentions.
In February and March 1974, the parties entered into two agreements whereby appellees, owners of JRM Construction Co., would perform plumbing, heating and air conditioning work at both a condominium complex, Benson House, and a shopping center, Willowbrook, being built by appel
Appellant contends first that the lower court erred in failing to consider the amounts already paid on the initial contracts. The issues to be addressed at trial must be framed in the parties’ pleadings. See Pa.R.Civ.P. 1019 (contents of pleadings). Here, appellees’ complaint sought compensation for extra work performed beyond the requirements of the original contracts. Paragraph five of the complaint averred that the parties agreed that all extra work on the condominium project would be paid for on a time and materials basis. Paragraph sixteen dealt with extra work on the shopping center. In answer to paragraph five, appellant agreed to be liable for extra work approved by appellant as per specifications of the contract. The answer also noted that, “extra work was to be paid for by an agreed upon sum, prior to commencement of the work.” (Answer at paragraph 5). The answer to paragraph 16 admitted that extra work was performed on the shopping center. Moreover, the evidence offered at trial focused on the specific work done by appellees that warranted additional payment. Appellee John Morris testified as to each of his company’s actions that constituted extra work. For example, one extra for which the lower court
Because the lower court failed to provide findings of fact in support of its verdict, we cannot satisfactorily review appellant’s remaining contentions. Appellant contends that the lower court (1) failed to consider the supplemental contract for the shopping center; (2) erred in finding appellees justified in refusing to complete the condominium contract; and (3) applied an incorrect standard of damages. The lower court opinion, instead of offering the basis of its conclusions, simply reiterates its verdict and states its ultimate conclusions as to the parties’ actions. Because the opinion fails to address appellant’s specific contentions, we have no basis upon which to review appellant’s claims. See Builders of Sanitary Sewers, Inc. v. Tamaqua Borough Authority, 307 Pa.Superior Ct. 459, 453 A.2d 674 (1982) (remanded for specific consideration of appellant’s contentions).
It is so ordered. Jurisdiction retained.