| City of New York Municipal Court | May 28, 1888

Pitshke, J.

The court below submitted to the jury the entire question whether the contract was made between the parties as alleged, and the jury found for the plaintiff. That matter was properly left to the jury to decide and determine. Patten v. Pancoast, 15 N. E. Rep. 893. Upon the question of damages the court instructed the jury, under exception, that, as damages for defendant’s failure to complete the filling in of the trestle, they might consider what it would cost plaintiff to build an embankment along the line of the railroad sufficient to keep the water from flowing m upon his land, and that, as damages for defendant’s failure to construct a depot site, plaintiff might recover the value of the earth necessary for that purpose, and cost of carting it. The rule of damages laid down by the court was the only part of the charge excepted to. The final and conclusive finding of the jury being that the contract was unfulfilled, plaintiff was entitled to be compensated to such extent as to enable him to be put in the like position he would have been in had the contract been duly performed. He should have just indemnity for his resulting loss, (Baker v. Drake, 53 N.Y. 211" court="NY" date_filed="1873-09-23" href="https://app.midpage.ai/document/baker-v--drake-3615640?utm_source=webapp" opinion_id="3615640">53 N. Y. 211, 216;) that is to say, “the plaintiff is to have that compensation which will leave him as well off as he would have been had the contract been fully performed, ” (per Folger, J., Kidd v. McCormick, 83 N. Y. 397;) and “he should, so far as money can do it, be placed in the same situation with respect to damages as if the contract had been performed,” (Robinson v. Harman, 1 Exch. 855.) The right of recovery on part of the plaintiff, as contractee, extended, in short, to all damages flowing naturally and proximately from the breach, (Tuers v. Tuers, 100 N. Y. 200, 2 N. E. Rep. 922,) though other causes, thereby set in motion, and not otherwise producing such a result, have contributed to the injurious consequences, (Pollett v. Long, 56 N.Y. 200" court="NY" date_filed="1874-03-24" href="https://app.midpage.ai/document/pollett-v--long-3586061?utm_source=webapp" opinion_id="3586061">56 N. Y. 200.) The court below left it to the jury, as a question of fact, whether there was a contract entered into with reference to filling in an embankment along the railroad contiguous *66to plaintiff’s salt meadow, and further filling for a depot site there, or for either of such purposes-; and if satisfied, by a preponderance of testimony, of the existence of the contract as stated by plaintiff, they were to consider and determine whether or not there was a performance, and how far. The whole matter was, hence, submitted properly and completely to the jury for final determination.

There was clear evidence, and the jury have found that the plaintiff, as owner of the adjoining property, desired to prevent the flowing over of water from one side of said railroad to the other, and upon his lands; and, applying to the railroad to do the filling, he elsewhere, at the superintendent’s instance, procured the required earth for defendant, provided it was used for the aforesaid purposes of filling in the trestle-work and filling up a depot site, by placing such earth thus furnished at the points designated. Instead of doing this, the defendant took the earth, and used it at some other place on its road, putting only porous cinders and like indifferent material into the trestle-work along plaintiff’s premises, and never even attempting to fill up any depot site; and, that being the case, the plaintiff evidently derived no benefit therefrom or from the agreement found by the jury. The company," on the trial, denied the condition of affairs as above depicted, claiming it had a prior and paramount arrangement for the same earth with the owner thereof for using it for railroad purposes anywhere on its road; but the jury, to whom this matter was also specifically submitted with proper instructions to render a verdict for defendant if they believed this version, have found to the contrary, and in plaintiff’s favor, thereon. There was more than sufficient earth provided by plaintiff to make that depot site and fill in the trestle-work fully. The depot site would have been alongside the filling in the trestle; that is, partly on defendant’s roadway and partly upon plaintiff’s ground contiguous thereto. Both localities could easily have been filled in with the sand and gravel supplied by plaintiff in a manner as contracted for. The objection to the cinders and ashes deposited (in lieu of said sand and gravel) in the trestle, was that the water leaked through, and such filling was therefore utterly useless to plaintiff. Sand and gravel, however, would answer the purpose, and the place whence plaintiff was to procure the filling earth was the place from which the defendant obtained the sand and gravel. Testimony was properly admitted regarding the cheapest cost of carting sand and gravel and filling in said trestle-work, and making the depot site therewith, as agreed, from the nearest point where sand and gravel can be obtained, and the lowest price of sand and gravel at such point nearest to the locality. This would constitute the measure of plaintiff’s damages, recoverable for defendant’s breach of the contract averred by plaintiff. That is, it would be the fair price or cost of what he (plaintiff) was to get by the contract, the existing embankment of ashes and cinders being worthless to him. Laraway v. Perkins, 10 N.Y. 371" court="NY" date_filed="1852-12-05" href="https://app.midpage.ai/document/laraway-v--perkins-3587426?utm_source=webapp" opinion_id="3587426">10 N. Y. 371, 373. In other words, it is the price for which the transporting and placing the requisite earth by others on the locality, and in the manner as agreed might have been obtained, the company’s contract price to so carry the earth there being “nothing, ” i. e., in consideration of its thereby obtaining ground, without payment, for a solid railroad embankment. To that effect; Ogden v. Marshall, 8 N.Y. 340" court="NY" date_filed="1853-06-05" href="https://app.midpage.ai/document/ogden-v--marshall-3598935?utm_source=webapp" opinion_id="3598935">8 N. Y. 340.

The jury’s verdict was entirely reasonable, under the evidence. Its amount is not to be questioned on this appeal, as the defendant objected below only generally to the right of plaintiff to have a verdict at all, and wholly failed to raise the specific question of its correct amount. Tuers v. Tuers, 100 N. Y. 202, 2 N. E. Rep. 922. The verdict is amply sustained by the evidence adduced. There was sufficient authority shown to make the said contract binding on defendant. The plaintiff first applied, in relation to the subject, to the company’s president, at its offices, who referred and sent him to the vice-president; and the latter instructed him to deal with the superintendent, Mr *67Barton. The president (or vice-president for him) had presumably proper authority to make such filling-in agreements, and instruct Barton accordingly, even for depot sites. As the defendant took away all the earth obtainable under the contract, by thus taking the benefit of plaintiff's contract with Bogert, and using the sand and gravel procured by plaintiff for his contract with defendant’s officers, the defendant has adopted and is estopped from denying the action of the general superintendent on behalf of the company; which latter is therefore thereby bound to the contract by him entered into. Wild v. Mining Co., 59 N.Y. 644" court="NY" date_filed="1874-12-15" href="https://app.midpage.ai/document/wild-v--new-york-and-austin-silver-mining-company-3608397?utm_source=webapp" opinion_id="3608397">59 N. Y. 644.

The other exceptions taken by the defendant during the trial are without merit, respectively. The order and judgment appealed from must be affirmed, with costs.

Yehiibas and McGown, JJ., concurred.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.