Moretrench, a subcontractor on a project to repair a federally owned dam on the Mississippi River, brought suit under the Miller Act, 40 U.S.C. §§ 270a-270d, against its prime contractor, a joint venture named GAB. The district court stayed the suit, at GAB’s request, pending resolution of certain disputes between GAB and the Corps of Engineers (the owner of the dam). Mor-etrench appeals from the stay. The first and only question we shall have to consider is our appellate jurisdiction.
When a subcontractor incurs an additional expense as a result of a change order issued by the owner, or some other change in circumstances for which the owner is responsible, the prime contractor, naturally, does not want to have to reimburse the subcontractor out of its own pocket, but instead wants the owner to bear the expense. To this end, the disputes clause in the contract between GAB and Moretrench provided that in the event of a dispute between the parties that involved the owner, Moretrench would be bound by the determination of responsibility made in accordance with the procedures set forth in the contract between GAB and the Corps of Engineers. That contract provided for initial determination by a federal contracting officer with a right of appeal to a board of contract appeals or to the United States Claims Court.
One of the disputes (and the subject of Count I of Moretrench’s complaint) was over extended pumping. Moretrench, whose job in the project was to “dewater” the area behind a cofferdam, claimed that it had to keep pumping for 292 days beyond the term specified in its contract with GAB, and it sought additional payment for the extra days. GAB duly submitted the claim to the Corps, which acknowledged liability for 95 days at the specified contract price of $5,100 per day and remitted payment for them at that rate to GAB, which in turn paid Moretrench. More-trench argues that GAB, not the Corps, was responsible for the other 197 days of extra pumping, and hence that the only remaining quarrel over the issue is between it (Moretrench) and GAB — a quarrel to which the pending proceeding in the Claims Court is irrelevant. However, GAB claims that not it but the Corps was responsible for the extra 197 days; that is one of the issues in litigation in the Claims Court.
*1286 In Count II of its complaint Moretrench seeks an additional payment of $664,000 for a work modification. The Corps’ contracting officer allocated this amount to Moretrench, and it was paid over to GAB. But rather than remit the money to More-trench, GAB has retained the money as a potential source of funds for satisfying its claims against the Corps arising out of the contract, and these claims too are pending in the Claims Court. Finally, Count III seeks $200,000 that the Corps allocated to Moretrench but then retained in order to offset overpayments that the Corps says it made to GAB under the contract. GAB denies that there were overpayments, and this is another issue in the Claims Court. (So Counts II and III involve mirror images: GAB retaining Moretrench’s money in Count II, the Corps retaining More-trench’s money in Count III.) Moretrench argues forcefully that all three disputes are purely between GAB and the Corps, and that it is entitled to get its money now, without waiting years for the proceeding in the Claims Court to end. In so arguing, Moretrench relies on a provision in the disputes clause of the subcontract that nothing in that clause “shall be construed in any manner to affect Subcontractor’s rights and remedies against the Contractor involving disputes or claims not solely due to the acts or omissions of the Owner.”
The stay granted by the district court is, of course, an interlocutory order. It does not resolve Moretrench’s lawsuit against GAB, but merely postpones proceedings in the suit until a final determination by the Claims Court of the claims that Moretrench submitted to GAB for presentation to the Corps of Engineers. In arguing that the stay is appealable even though it is interlocutory, Moretrench relies primarily on the “Enelow-Ettelson” doctrine, an obscure and disfavored doctrine of appellate jurisdiction, see
Olson v. Paine, Webber, Jackson & Curtis, Inc.,
Moretrench’s suit against GAB is a suit at law; it seeks damages for breach of contract. The fact that it also seeks a declaratory judgment is irrelevant. Although a suit which seeks both legal and equitable relief is deemed equitable for purposes of applying the
Enelow-Ettelson
doctrine unless the equitable relief sought is nominal
(Olson v. Paine, Webber, Jackson & Curtis, Inc., supra,
So the critical question is whether or not the stay sought and granted in this case is based on an equitable claim or defense. Not all stays are, of course; else one of the two elements of the
Enelow-Ettelson
doctrine (suit at
law, equity
stay) would be superfluous. In
Microsoftware Computer Systems, Inc. v. Ontel Corp.,
We have no desire to interpret this discredited doctrine broadly, but it would be no service to the cause of reform to make arbitrary distinctions among types of equity claim or defense and allow only a subset to form the basis of stays appealable under section 1292(a)(1). Conceivably the panel in
Microsoftware
misconstrued a stay designed merely to avoid parallel litigation as one designed to protect the party seeking the stay from being harassed by multiple suits (although other cases have equated the two grounds of stay, notably
Crosley Corp. v. Hazeltine Corp.,
So — to return at long last to the particulars of this suit — if Moretrench had sued GAB on the same claim in two courts, and one of the courts had stayed the case before it to spare GAB from being harassed by Moretrench, the stay would have been equitable in character, and hence immediately appealable if (as here) the suit sought to be stayed was an action at law. But that is not the character of the stay. More-trench, as it is at pains to stress, is not a party to the proceeding in the Claims Court. Although in granting the stay on GAB’s motion the district judge did mention the desirability of avoiding duplication of that proceeding, this, as we have just said, may not be enough to distinguish a “law” stay from an “equity” stay. More important, the idea behind the stay in this case was not that GAB should be spared from being harassed by parallel suits in different forums (they are not parallel), but that the subcontract with Moretrench makes the proceeding in the Claims Court a condition precedent to Moretrench’s obtaining damages from GAB in the present suit. A stay based on a term of the parties’ contract making some procedure a condition precedent to enforcing the contract is not per se equitable in character. It is *1288 neither itself rooted in equity notions, as would be a stay designed to prevent the defendant from being harassed by a multiplicity of lawsuits, nor designed to allow the defendant to assert an equitable defense such as unclean hands.
The defense here is, in the first instance, simply a contract defense: that Moretrench is not entitled to be paid until the proceeding in the Claims Court is over and done with, even though some of the disputes between the parties that have given rise to the present lawsuit may be outside the scope of that proceeding. (Whether this is a sound or an unsound defense is
the
issue on the merits, which we cannot decide unless we have appellate jurisdiction.) Some contract defenses are equitable; in particular, where a contract provides that the parties will refer any dispute arising under it to arbitration, and the provision is used to obtain a stay of judicial proceedings pending the arbitration, the stay is deemed equitable. But this is because of the supposition, probably erroneous and certainly beside the point, see
Hayes v. Allstate Ins. Co.,
The stay in this case is much like a stay granted because a plaintiff has failed to exhaust administrative remedies, or because the dispute is within the primary jurisdiction of an administrative agency. Indeed, the stay in this case may
be
such a stay rather than just an analogy to it — for is not the dispute process between the prime contractor and the Corps of Engineers, with appeal to a board of contract appeals or to the Claims Court, an administrative procedure that Moretrench must allow to be completed before it can obtain damages in court? Most cases hold that a stay pending completion of administrative proceedings is not equitable for purposes of the
Enelow-Ettelson
doctrine. See
Pepper v. Miani,
H.W. Caldwell & Son, Inc. v. United States for Use of John H. Moon & Sons, Inc.,
Moretrench bases an alternative argument for an immediate appeal on the “collateral order” doctrine, which treats as final (and therefore appealable under 28 U.S.C. § 1291) any judicial order that both definitively resolves an issue separate from the merits of the underlying dispute and is not effectively reviewable on appeal from
*1289
the final judgment in that dispute. See, e.g.,
Cohen v. Beneficial Industrial Loan Corp.,
Last, Moretrench appeals to a notion of “practical finality”: GAB has a variety of disputes with the Corps of Engineers arising out of the repair of the dam and pending before the Claims Court, and it may take years before all are finally resolved, and until then Moretrench will be irreparably harmed by being denied the payments to which it is entitled. There are two difficulties with this argument. The first is that while Moretrench tells us that the delay in payment is a hardship to a company of its size, it does not tell us what that size is or make any other attempt to lay a factual basis for its argument of irreparable harm. Prejudgment interest is the norm in contract litigation and therefore Moretrench will be compensated for the delay in receiving the payments due it under the subcontract. Of course the compensation may not be complete, for a variety of factors ranging from the interest rate to the particulars of Moretrench’s business, but none of these factors has been laid before either the district court or this court. The argument of irreparable harm is pure assertion — and vigor of advocacy is no substitute for facts.
We have said that the difference between money now and money later, though real, “is not the sort of irreparable harm that is effectively unreviewable on appeal.”
Uehlein v. Jackson Nat’l Life Ins. Co.,
that difference is involved here, as in
Palmer v. City of Chicago,
Second, to say that an order which does irreparable harm should be immediately ap-pealable mutilates the collateral-order doctrine by making one of its elements sufficient for appealability and the other redundant. It might be a good thing to have a single comprehensive safety hatch in the final-judgment rule of 28 U.S.C. § 1291, and thus allow interlocutory orders to be appealed whenever the order threatened irreparable harm (but only then), rather than to continue adding to the present patchwork of judicial and statutory exceptions. In a case of truly irreparable harm, the reviewing court will strain to fit the case into one of the exceptions, and thanks to their number and their vague edges will usually succeed; maybe it is time to bring doctrine into line with practice.
Viewed against this background,
Moses H. Cone Memorial Hospital v. Mercury Construction Corp.,
Of course Moretrench can move to dissolve the stay if and when developments in the Claims Court demonstrate to the district court’s satisfaction that GAB is unjustifiably withholding moneys that it has received from the Corps of Engineers for the benefit of Moretrench. But the stay is not appealable, and Moretrench’s appeal is therefore
Dismissed.
