Lead Opinion
This appeal is from an order granting the preliminary objections in the form of a demurrer of appellee, Brittany Estates (“Brittany”), and dismissing the mechanics’ lien complaint of appellant, Morehall Contracting Co., Inc. (“Morehall”), which had been filed in connection with a contract to perform certain grading and excavation work. Appellant claims that the trial court erred in dismissing its complaint on the ground that the work appellant performed for appellee did not constitute an “improvement” to property under the Mechanics’ Lien Law of 1963.
Morehall was a subcontractor to Chesterdale Construction Company, which in turn was general contractor at a construction project known as Brittany Estates. Brittany Estates is a townhouse and condominium development located in Caernarvon Township, Berks County. Morehall’s complaint alleged that, pursuant to a written contract with Chesterdale, dated September 27, 1988, Morehall performed a significant amount of construction work at the site of the
Our scope of review to a challenge to the sustaining of a preliminary objection in the form of a demurrer is well-settled:
A demurrer can only be sustained where the complaint is clearly insufficient to establish the pleader’s right to relief. Firing v. Kephart,466 Pa. 560 ,353 A.2d 833 (1976). For the purpose of testing the legal sufficiency of the challenged pleading a preliminary objection in the nature of a demurrer admits as true all well-pleaded, material, relevant facts, Savitz v. Weinstein,395 Pa. 173 ,149 A.2d 110 (1959); March v. Banus,395 Pa. 629 ,151 A.2d 612 (1959), and every inference fairly deducible from those facts, Hoffman v. Misericordia Hospital of Philadelphia,439 Pa. 501 ,267 A.2d 867 (1970); Troop v. Franklin Savings Trust,291 Pa. 18 ,139 A. 492 (1927). The pleader’s conclusions or averments of law are not considered to be admitted as true by a demurrer. Savitz v. Weinstein, supra.
*268 Since the sustaining of a demurrer results in a denial of the pleader’s claim or a dismissal of his suit, a preliminary objection in the nature of a demurrer should be sustained only in cases that clearly and without a doubt fail to state a claim for which relief may be granted. Schott v. Westinghouse Electric Corp.,436 Pa. 279 ,259 A.2d 443 (1969); Botwinick v. Credit Exchange, Inc.,419 Pa. 65 ,213 A.2d 349 (1965); Savitz v. Weinstein, supra; London v. Kingsley,368 Pa. 109 ,81 A.2d 870 (1951). If the facts as pleaded state a claim for which relief may be granted under any theory of law then there is sufficient doubt to require the preliminary objection in the nature of a demurrer to be rejected. Packler v. State Employment Retirement Board,470 Pa. 368 , 371,368 A.2d 673 , 675 (1977); see also Schott v. Westinghouse Electric Corp., supra [436 Pa.] at 291,259 A.2d at 449 .
Mudd v. Hoffman Homes for Youth, Inc.,
The Mechanics’ Lien Law of 1963 provides that:
Every improvement and the estate or title of the owner in the property shall be subject to a lien, to be perfected as herein provided, for the payment of all debts due by the owner to the contractor or by the contractor to any of his subcontractors for labor or materials furnished in the erection or construction, or the alteration or repair of the improvement, provided that the amount of the claim, other than amounts determined by apportionment under section 306(b) of this act, shall exceed five hundred dollars ($500).
49 Pa.S.A. § 1301. The definitional section of the Mechanics’ Lien Law further provides, in relevant part, that:
The following words, terms and phrases when used in this act shall have the meaning ascribed to them in this section, except where the context clearly indicates a different meaning:
*269 (1) “Improvement” includes any building, structure or other improvement of whatsoever kind or character erected or constructed on land, together with the fixtures and other personal property used in fitting up and equipping the same for the purpose for which it is intended.
******
(10) “Erection and construction” means the erection and construction of a new improvement or of a substantial addition to an existing improvement or any adaptation of an existing improvement rendering the same fit for a new or distinct use and effecting a material change in the interior or exterior thereof....
******
(12) “Erection, construction, alteration or repair” includes:
(a) Demolition, removal of improvements, excavation, grading, filling, paving and landscaping, when such work is incidental to the erection, construction alteration or repair....
49 Pa.S.A. § 1201. This Court has noted that the definition of “erection, construction, alteration or repair” contained in § 1201(12)(a) “was intended to declare existing decisional law [allowing mechanics liens to attach] with respect to such work upon the ground ... which is incidental to the erection, construction, alteration or repair of an improvement, as compared to such work when it is performed independently of any erection, construction, alteration or repair of an improvement, in which latter case no lien is allowed.” Sampson-Miller Assoc. Cos., v. Landmark Realty Co.,
Appellant’s Amended Complaint states, in relevant part, that:
[P]laintiff furnished labor and materials used in the erection and/or construction of an improvement, namely, a housing development known as “Brittany Estates”, in*270 that plaintiff furnished said labor and materials to perform the following erection and/or construction, as defined in the Mechanics’ Lien Law of 1963, 49 P.S. Sec. 1201(12)(a) and/or (c): topsoil stripping; earth grading; grading for building pads, including but not limited to the sample units and sales center; construction of a temporary roadway to permit contractors’ access to complete erection and/or construction of the aforesaid sample units and sales center; and erection and/or construction of a storm detention basis and related site work necessary to and a component part of the storm sewer system of the aforesaid housing development.
See Appellant’s Amended Complaint to Obtain Judgment upon Mechanics’ Lien Claim at 2. (R. at 7). In granting appellee’s preliminary objections and dismissing appellant’s complaint, the court reasoned that appellant failed to state a claim under the Mechanics’ Lien Law because “plaintiff’s allegations of work performed consist of erosion control and of earthwork as categorized in the contract ... unrelated to the erection or construction, alteration or repair, of an improvement to property as defined in the Mechanics’ Lien Law.” See Opinion, November 9, 1989 at 5-6. More specifically, the trial court apparently held that this allegation was insufficient as a matter of law because appellant had failed to allege that: (1) the work it performed was connected to the construction of any “improvement” on the property; and (2) “improvements” in fact had been erected at Brittany Estates. See id. After carefully reviewing the record, we cannot agree that the complaint “clearly and without a doubt” failed to allege that the work performed was related to an “improvement”.
The above-quoted averments, if accepted as true (see Mudd v. Hoffman, supra), would tend to establish that appellant performed significant groundwork in preparation for the construction of housing and administrative structures in Brittany Estates. Under the language of § 1201 and Sampson-Miller, supra, if construction has actually taken place in Brittany Estates, then the groundwork that
For the foregoing reasons, we reverse the order of the lower court and remand for proceedings consistent with this opinion.
Order reversed. Case remanded. Jurisdiction relinquished.
Notes
. 49 Pa.S.A. § 1101 et seq. Appellant also argues that the court below erred in dismissing its complaint because: (1) there is no statutory requirement that appellant allege that actual construction took place at Brittany Estates in order to state a claim; (2) the court failed to direct the parties to conduct discovery in order to determine whether construction had taken place at Brittany Estates; and (3) the court failed to accept photographs and affidavits documenting the progress of construction at Brittany Estates. Because of our disposition of appellant’s first claim, we need not address these issues.
Dissenting Opinion
dissenting:
I respectfully dissent. A mechanics’ lien for improvements to property attaches to the structure only, even if the work performed is preparation work not done to the structure itself. A complaint under the Mechanics’ Lien Law must allege that a structure exists. In neither the original
Morehall performed ground preparation clearly intended for the construction of housing units. Morehall filed a mechanics’ lien claim and a complaint against Brittany Estates. The complaint described the work done in terms of preparation for construction, but it did not allege that buildings were subsequently built. See the excerpt from the complaint, Judge Hoffman’s Opinion at 269-270. The trial court sustained Brittany Estates’ preliminary objections on the grounds that the labor performed was not the erection, construction, alteration or repair of an improvement to property as required by the Mechanics’ Lien Law, codified at 49 P.S. 1101 et seq, because the existence of a building was not alleged.
The right to a mechanics’ lien arises pursuant to the Mechanics’ Lien Law:
Every improvement and the estate or title of the owner in the property shall be subject to a lien, to be perfected as herein provided, for the payment of all debts due by the owner to the contractor ... for labor or materials furnished in the erection or construction, or alteration or repair of the improvement....
49 P.S. § 1301. An improvement means “any building, structure or other improvement of whatsoever kind or character erected or constructed on land ...” 49 P.S. § 1201.
Thus, the remedy of a mechanics’ lien is created for the purpose of securing priority of payment for work performed or materials furnished.in erecting or repairing a building. As a lien, it is a claim or charge upon realty, rather than merely against the owner, and therefore, proceedings for its enforcement are in the nature of proceedings in rem. See 23 P.L.E. Mechanics’ Liens § 1. “The proceeding here is against the building, and being in rem the lien must appear by the record ...” Hunter v. Lanning,
The court, dismissing the plaintiff’s complaint, held that “In no case ... has a lien been allowed for work on land alone where no building or permanent structure is erected.” Sampson-Miller,
Morehall makes two arguments to this court, both of which fail. First, he argues that the work done is covered under the Mechanics’ Lien Law because the nature of the
A line of cases interpreting section 1503’s requirements hold that so long as the filing of the lien gives sufficient notice to furnish “some data by which, in case of dispute, they may be enabled to ascertain the truth,” Tesauro v. Baird,
However, in the present case substantial compliance with the § 1503 notice requirement is not at issue. Rather, we are presented with the threshold issue of whether Morehall has alleged a material element of a claim under the Mechanics’ Lien Law so as to be able to invoke the statutorily created remedy at all. I would hold that it has not. The substantial compliance principle has never been applied to establish whether the essential element of whether a building exists has been pleaded. I therefore do not agree with Judge Hoffman’s conclusion that the complaint is good on the basis that it did not “clearly and without a doubt” fail to allege that the work performed was related to an improvement. I would rely, rather, upon the basic rule of law that a court should review mechanic’s lien claims with a strict construction of the statute. Sampson-Miller, supra.
Following a hearing pursuant to 49 P.S. § 1505, see Site Improvements, Inc., v. Central and Western Chester
Morehall’s complaint alleges that they did ground preparation work for buildings. Neither the complaint nor the amended complaint states that buildings were ever built. Exhibits (such as photographs) attached to a claim may be considered part of the pleading, Marchak v. McClure,
It is to be remembered that the Mechanics’ Lien Law provides a special remedy that is additional, concurrent and cumulative and does not derogate from any other available remedies. Halowich v. Amminiti, 190 Pa.Super 314,
For all the foregoing reasons, I would affirm the decision of the trial court.
