History
  • No items yet
midpage
Mordhorst Cleaning v. Cardamone
23CA0781
| Colo. Ct. App. | Sep 12, 2024
|
Check Treatment
Opinion Summary

Facts

  1. Derec Appiahkubi was adjudicated a level two sex offender and designated a predicate sex offender under the Sex Offender Registration Act during a hearing in Criminal Court, New York County [lines="12-13"].
  2. The order was entered on February 2, 2018, after a hearing led by Judge David Frey [lines="12"].
  3. Appiahkubi's defense primarily challenged the assessment of points under risk factor 9, without objecting to other risk factor assessments, including risk factor 12 [lines="18"].
  4. His prior criminal history included convictions for misdemeanor sex crimes of forcible touching and third-degree sexual abuse [lines="19"].
  5. The appellate court determined the record supports the level two sex offender adjudication while recognizing an error in classifying him as a predicate sex offender [lines="15-20"].

Issues

  1. Whether the assessment of points under risk factor 12 for not accepting responsibility was preserved for appellate review [lines="17"].
  2. Whether the assessment of points based upon Appiahkubi’s prior criminal history was properly made on appeal [lines="19"].
  3. Whether the lower court erred in classifying Appiahkubi as a predicate sex offender [lines="20"].

Holdings

  1. The contention regarding the assessment of points under risk factor 12 is unpreserved for appellate review, and the court declined to address it [lines="17"].
  2. The challenge regarding the assessment based on prior criminal history was improperly raised for the first time in a reply brief and was without merit [lines="19"].
  3. The appellate court modified the order, vacating the determination that Appiahkubi is a predicate sex offender, affirming the level two sex offender adjudication [lines="15-20"].

OPINION

23CA0781 Mordhorst Cleaning v Cardamone 09-12-2024
COLORADO COURT OF APPEALS
Court of Appeals No. 23CA0781
City and County of Denver District Court No. 22CV305
Honorable Stephanie L. Scoville, Judge
Mordhorst Cleaning, LLC, d/b/a Blue Ribbon Exteriors and Construction,
Plaintiff-Appellee,
v.
Geoff Cardamone and Katie Cardamone,
Defendants-Appellants.
JUDGMENT AFFIRMED
Division II
Opinion by JUDGE SCHOCK
Fox and Johnson, JJ., concur
NOT PUBLISHED PURSUANT TO C.A.R. 35(e)
Announced September 12, 2024
Allen & Curry P.C., Theodore A. Wells, Denver, Colorado, for Plaintiff-Appellee
The Arriola Law Firm, LLC, Erick S. Arriola, Englewood, Colorado, for
Defendants-Appellants
1
¶ 1 Defendants, Geoff Cardamone and Katie Cardamone (the
Cardamones), appeal the judgment entered for them and against
plaintiff, Mordhorst Cleaning, LLC, d/b/a Blue Ribbon Exteriors
and Construction (Blue Ribbon), following a bench trial. We affirm.
I. Background
¶ 2 Months after the Cardamones moved into their new home, the
fire suppression system froze and a pipe burst, causing extensive
water damage. The Cardamones filed an insurance claim and hired
a public adjuster to assist them with the insurance claim process.
¶ 3 The Cardamones hired Blue Ribbon to serve as the general
contractor for the repairs. The parties entered into one contract for
the repair of the fire suppression system and another for the repair
of the damage caused by the burst pipe. Neither contract included
a price for the work. Instead, the contracts provided that “materials
and specialty trade contractors shall be billed at cost plus twenty
percent . . . subject to change without notice,” and the general
contractor “shall be entitled to 10% overhead and 10% of the
amounts due and owing for repairs completed.” The parties entered
into additional agreements for other work not covered by insurance.
2
¶ 4 The public adjuster made several payments to Blue Ribbon
out of the insurance proceeds. But the Cardamones did not have
sufficient insurance coverage to pay the full cost of the repair and
restoration. So several months into the project, they requested
detailed information from Blue Ribbon about the remaining costs.
The owner and managing partner of Blue Ribbon, Ryan Mordhorst,
refused to provide the information, deeming it an unreasonable
request. Ten days later, Blue Ribbon stopped work on the project,
though the parties dispute who terminated the relationship.
¶ 5 Blue Ribbon sent the Cardamones a final invoice for
$13,940.54, which the Cardamones did not pay.
¶ 6 Blue Ribbon then sued the Cardamones for the unpaid
invoice. The Cardamones asserted counterclaims for breach of
contract, civil theft, and unjust enrichment. They alleged that Blue
Ribbon had (1) failed to complete the work required by the parties’
contracts; (2) failed to pay subcontractors and material suppliers, in
violation of section 38-22-127, C.R.S. 2024; and (3) retained money
for work it did not perform and materials it did not deliver.
3
¶ 7 After a two-day bench trial, the district court found in favor of
Blue Ribbon on some issues and in favor of the Cardamones on
others. Four of those rulings are at issue in this appeal:
(1) The district court ruled against the Cardamones on their
claim for civil theft, finding that they failed to prove Blue
Ribbon received funds for the payment of any
subcontractor that it failed to pay, or that it acted with
the requisite state of mind in doing so.
(2) The court rejected the Cardamones’ claim of unjust
enrichment related to Blue Ribbon’s markup for cabinets
because the Cardamones agreed to the price for the
cabinets in separate contracts.
(3) The court rejected the Cardamones’ claim of unjust
enrichment for payments relating to the handling of their
personal property, finding that they had suffered no
losses that were not covered by insurance and that Blue
Ribbon had acted as a middleman for this work.
(4) The court found that the Cardamones were liable for
$5,653.99 for additional framing work. The court noted
that this amount was not included in Blue Ribbon’s
4
original complaint, but it concluded that the issue was
tried by consent because Blue Ribbon presented evidence
on this point at trial and the Cardamones did not object.
¶ 8 After awarding prejudgment interest and offsetting the
amounts awarded to each party, the court entered judgment in
favor of the Cardamones in the total amount of $8,768.74.
II. The Cardamones’ Claims
¶ 9 The Cardamones contend that the district court erred by
denying their claims for (1) civil theft; (2) excess cabinet markup;
and (3) Blue Ribbon’s retention of funds for personal property
services.
A. Standard of Review
¶ 10 Our review of a judgment following a bench trial presents a
mixed question of fact and law. State ex rel. Weiser v. Ctr. for
Excellence in Higher Educ., Inc., 2023 CO 23, ¶ 33. We review the
district court’s factual findings for an abuse of discretion and its
legal conclusions de novo. Id. In doing so, we defer to the district
court’s credibility findings and its assessment of the weight and
probative effect of the evidence. Amos v. Aspen Alps 123, LLC, 2012
CO 46, ¶ 25; Saturn Sys., Inc. v. Militare, 252 P.3d 516, 521 (Colo.
5
App. 2011). It is not our role to decide the facts or substitute our
judgment for that of the district court, and we will not disturb the
district court’s findings of fact “unless they are so clearly erroneous
as to find no support in the record.” Saturn Sys., 252 P.3d at 521.
B. Civil Theft
¶ 11 The Cardamones contend that the district court erred in
applying section 38-22-127 to their civil theft claim arising out of
payments owed to three subcontractors: Ridge Construction (Ridge),
The Contents Company (TCC), and Electronic Restoration Services
(ERS). They assert that Blue Ribbon received payments intended
for these subcontractors but intentionally failed to fully pay them.
Because the Cardamones have not shown that the district court’s
findings to the contrary are clearly erroneous, we affirm its ruling.
1. Additional Background
¶ 12 Blue Ribbon subcontracted with Ridge to obtain the framing
permit for the project. Ridge submitted the permits and invoiced
Blue Ribbon for the permitting fees. Blue Ribbon did not pay the
invoice, but it included the permitting fees in its final invoice to the
Cardamones. The Cardamones did not pay that invoice, and the
6
district court found that Blue Ribbon had not been compensated for
the permit by the public adjuster or the Cardamones.
¶ 13 The Cardamones contracted directly with TCC and ERS for
services related to their personal property insurance claim,
including inventorying, packing, cleaning, storing, and redelivering
their personal property. Although Blue Ribbon did not contract
with either TCC or ERS, it served as an intermediary between those
companies and the Cardamones. TCC and ERS submitted invoices
to Blue Ribbon, which passed them on to the public adjuster. The
public adjuster then paid Blue Ribbon, and Blue Ribbon paid TCC
and ERS after taking out a charge for its own overhead and profit.
¶ 14 Blue Ribbon paid TCC more than $40,000 and ERS more than
$8,000. But after Blue Ribbon stopped working on the project, both
companies billed the Cardamones additional amounts. Blue Ribbon
eventually paid TCC in full. Although the Cardamones asserted
that they paid a final past due invoice to ERS, the district court
found the evidence was insufficient to prove that they did so.
2. Analysis
¶ 15 Colorado’s construction trust fund statute, section 38-22-
127(1), provides:
7
All funds disbursed to any contractor . . .
under any . . . construction, or remodeling
contract or on any construction project shall
be held in trust for the payment of the
subcontractors . . . who have a lien, or may
have a lien, against the property, or who claim,
or may claim, against a principal and surety
under the provisions of this article and for
which such disbursement was made.
A violation of this subsection constitutes theft, as defined in section
18-4-401, C.R.S. 2024. § 38-22-127(5); see also § 18-4-405, C.R.S.
2024 (providing for civil action to recover treble damages for theft).
¶ 16 Colorado courts have construed theft under section 38-22-
127(5) to incorporate the culpable mental states in section 18-4-
401(1). See People v. Anderson, 773 P.2d 542, 544 (Colo. 1989); see
also Franklin Drilling & Blasting, Inc. v. Lawrence Constr. Co., 2018
COA 59, ¶ 18 (holding that a plaintiff must prove a culpable mental
state to prove civil theft under similar Public Work Trust Fund
statute, section 38-26-109, C.R.S. 2024). One such culpable
mental state is that the defendant “[k]nowingly uses . . . the thing of
value in such manner as to deprive the other person permanently of
its use or benefit.” § 18-4-401(1)(b). This means the defendant
must “be aware that his manner of using the trust funds is
8
practically certain to result in depriving another person of the use
or benefit of the funds.” Anderson, 773 P.2d at 545.
¶ 17 The district court found that the Cardamones did not prove
Blue Ribbon failed to pay Ridge, TCC, or ERS any amounts for
which it received payment from the Cardamones. As to Ridge, the
court found that Blue Ribbon did not receive payment from the
Cardamones for the permits. As to TCC, the court found that it was
paid in full. And as to ERS, the court found that the Cardamones
failed to prove that they were required to pay an additional invoice.
The court also found that there was no evidence that Blue Ribbon
held any additional funds in trust for payment of ERS.
¶ 18 The Cardamones do not point to anything in the record that
refutes these findings. Instead, they argue more generally that
because Blue Ribbon received total funds that exceeded the
amounts due, it was required to pay all outstanding amounts before
taking any profit. But section 38-22-127(1) does not require a
contractor to hold all funds it receives on a project in trust until all
subcontractors have been paid. It requires the contractor to hold
funds in trust for the payment of subcontractors “for which such
disbursement was made.” § 38-22-127(1). In other words, a
9
contractor must pay a subcontractor all amounts for which the
contractor itself has received payment. The Cardamones do not
identify any evidence that they made payments to Blue Ribbon for
the purpose of paying Ridge for permits or paying TCC or ERS for
the amounts billed after Blue Ribbon stopped work on the project.
¶ 19 The Cardamones cite Mordhorst’s testimony that Blue Ribbon
received more money for framing related work than it paid Ridge.
That testimony does not show that Blue Ribbon received any funds
for the permits. To the contrary, Mordhorst testified that the
Cardamones refused to pay anything for the permits. And the
“permits” line item on the final invoice — which the district court
found the Cardamones had not paid — supports that conclusion.
Similarly, the fact that Blue Ribbon received payments for other
amounts billed by TCC and ERS does not show that it received
payment for the amounts that were billed several months later.
¶ 20 The district court also found that Blue Ribbon did not act with
the requisite state of mind to commit civil theft with respect to
either the permitting fees or the personal property claims. See
10
Anderson, 773 P.2d at 544. That finding is not clearly erroneous.
1
Mordhorst’s testimony that he received more money for framing
related work than he paid Ridge does not establish that Blue
Ribbon was aware that its conduct was “practically certain” to
deprive the Cardamones of the use of funds intended for the
payment of permits. See id. Nor does Mordhorst’s retention of
overhead and profit on earlier invoices from TCC and ERS establish
that Blue Ribbon knowingly deprived the Cardamones of the use of
funds intended for the payment of other personal property invoices.
That is particularly true given the nature of the parties’ ongoing
disputes. See § 38-22-127(2) (providing that a contractor need not
hold funds in trust if the contractor “has a good faith belief that
such . . . claim is not valid or . . . , in good faith, claims a setoff”).
¶ 21 Finally, to the extent the Cardamones contend that Blue
Ribbon violated section 38-22-127(3) by failing to maintain
adequate records of account for the project, such a violation — even
1
The Cardamones assert that the interpretation and application of
section 38-22-127, C.R.S. 2024, is a question of law that we review
de novo. But they have not identified any legal error in the district
court’s application of the statute. Their disagreement with the
court’s factual findings does not mean the court misapplied the law.
11
if proved — would not prove their theft claim. See § 38-22-127(5)
(limiting “theft” to a violation of subsections (1) and (2)).
¶ 22 Thus, the district court did not clearly err in finding that Blue
Ribbon did not receive funds for the payment of Ridge, TCC, or ERS
that it failed to pay to those entities. In light of that finding, the
district court correctly denied the Cardamones’ civil theft claim.
C. Cabinet Claim
¶ 23 The Cardamones next argue that the district court erred by
denying their claim for unjust enrichment based on Blue Ribbon’s
markup for the cabinets, which exceeded the twenty percent
markup in the parties’ primary contracts. We are not persuaded.
1. Additional Background
¶ 24 The Cardamones selected and ordered custom cabinetry
through the Flooring Group. Because the Flooring Group is a
wholesaler, it did not invoice the Cardamones directly. Instead, it
invoiced Blue Ribbon, which then invoiced the Cardamones. The
Flooring Group charged Blue Ribbon $22,347.17 for the kitchen
cabinets and $4,821.13 for the bathroom vanities. Blue Ribbon
charged the Cardamones $39,757.19 and $7,556.76, respectively.
12
¶ 25 Mr. Cardamone signed separate contracts with Blue Ribbon
for the cabinets and vanities. Mr. Cardamone testified at trial that
he was concerned that the price of the cabinetry was excessive, but
he felt pressure to agree to it due to time constraints. He signed the
agreement after Mordhorst told him “[t]he price is the price.” The
cabinets were delivered damaged and the wrong color. But by that
time, Blue Ribbon had stopped working on the project, and it
refused to work with the Flooring Group to correct the issues.
¶ 26 In their post-trial brief, the Cardamones asserted that Blue
Ribbon had been unjustly enriched to the extent its markup
exceeded the standard twenty percent markup in the parties’
primary contracts. The district court rejected the claim because the
cabinets were covered by separate contracts confirming the price.
2. Analysis
¶ 27 Unjust enrichment is “a quasi-contractual, equitable remedy
designed to undo a benefit conferred on one party at the unfair
expense of another party.” Pulte Home Corp. v. Countryside Cmty.
Ass’n, 2016 CO 64, ¶ 63. It “seeks to restore fairness . . . when the
plaintiff has no alternative right under an enforceable contract.”
Alderman v. Bd. of Governors of Colo. State Univ., 2023 COA 61,
13
¶¶ 22-23 (cert. granted May 6, 2024). But “[a] party generally
cannot recover for unjust enrichment . . . where there is an express
contract addressing the subject of the alleged obligation to pay.”
Pulte Home Corp., ¶ 64.
¶ 28 The record supports the district court’s finding that the
Cardamones and Blue Ribbon entered into separate contracts for
the cabinetry that set its price. Mordhorst testified that the parties
entered into one contract for the kitchen cabinets and one for the
bathroom vanities, both of which stated the price the Cardamones
owed. He also testified that the Cardamones had an opportunity to
ask questions about the price before they signed the contracts. Mr.
Cardamone similarly testified as to these separate agreements. And
although he thought the price was high and felt pressured to sign
the agreements, he acknowledged that he signed them voluntarily.
¶ 29 The Cardamones assert that the district court’s finding that
the cabinets and vanities were subject to separate agreements “does
not comport [with] the evidence presented.” But they don’t explain
why, particularly in light of the testimony above. They do not cite
anything in the record to support their assertion that the cabinets
were included in the primary rebuild contract and, thus, limited to
14
a twenty-percent markup. See C.A.R. 28(a)(7)(B) (requiring
appellant to cite “the authorities and parts of the record on which
the appellant relies”); Brighton Sch. Dist. 27J v. Transamerica
Premier Ins. Co., 923 P.2d 328, 335 (Colo. App. 1996) (“[I]t is not the
duty of the reviewing court to search the record for evidence to
support bald assertions.”), aff’d, 940 P.2d 348 (Colo. 1997). And
even if they were, the Cardamones do not explain why the parties
could not later separately agree on the price for those cabinets.
¶ 30 The Cardamones also hint at several factual challenges to the
cabinet contracts and Blue Ribbon’s performance, including that
the markups were “beyond excessive,” that Blue Ribbon delayed
payment to the cabinet supplier, and that Blue Ribbon did not
assist in resolving the incorrect delivery. But none of these
arguments negate the district court’s finding that enforceable
contracts existed. And although the Cardamones assert that they
were “under duress of timing and financial pressures,” they do not
dispute Mr. Cardamone’s concession that he signed the contracts
voluntarily. Having agreed to the prices for the cabinets, the
Cardamones could not claim Blue Ribbon was unjustly enriched.
15
D. Personal Property Claim
¶ 31 The Cardamones also assert that the district court erred by
denying their unjust enrichment claim related to Blue Ribbon’s
retention of funds for serving as the middleman between the
Cardamones and the companies handling the personal property
claim. They contend that Blue Ribbon was not entitled to retain
any portion of such funds because their contract with Blue Ribbon
did not cover the personal property portion of the claim and the
Cardamones were not aware that Blue Ribbon was involved.
¶ 32 To prevail on an unjust enrichment claim, a plaintiff must
prove that (1) the defendant received a benefit (2) at the plaintiff’s
expense (3) under circumstances that would make it unjust for the
defendant to retain the benefit without commensurate
compensation. Pulte Home Corp., ¶ 63. When the parties have an
express contract, a party may still recover for unjust enrichment for
matters outside of the contract. Id. at ¶ 64. We review the district
court’s ruling on an unjust enrichment claim for an abuse of
discretion. Lewis v. Lewis, 189 P.3d 1134, 1140 (Colo. 2008).
¶ 33 The district court agreed with the Cardamones that no
contract covered Blue Ribbon’s handling of the Cardamones’
16
personal property claim. But it found that the Cardamones did not
prove the second and third elements of their claim because (1) they
did not show that their personal property expenses were not fully
covered by insurance; and (2) the public adjuster, who acted as the
Cardamones’ agent, knew Blue Ribbon was serving in that role.
¶ 34 The Cardamones do not meaningfully challenge either of these
findings. Although they assert that they were “left to cover a
portion of [TCC’s and ERS’s] bills,” they do not cite any record
support for that assertion, and the district court found otherwise.
C.A.R. 28(a)(7)(B); see also Makeen v. Hailey, 2015 COA 181, ¶ 49
(“[W]e will not comb the record in search of additional facts to
support this claim.”). Beyond that, the Cardamones highlight facts
(again without record citation) that were either undisputed or
immaterial to the court’s resolution of their claim — namely, that
they contracted directly with TCC and ERS and that they did not
agree to Blue Ribbon’s involvement. Neither of these facts refutes
the district court’s determination that there was no unjust
enrichment where the Cardamones’ agent knew what was going on
the entire time and approved of Blue Ribbon’s participation.
17
¶ 35 We therefore conclude that the district court did not abuse its
discretion by denying the Cardamones’ claim for unjust enrichment
related to Blue Ribbon’s handling of the personal property claim.
III. Noninsurance Framing Cost
¶ 36 The Cardamones also contend that the district court erred by
awarding Blue Ribbon the unpaid amount for additional framing
work that Blue Ribbon did not plead in its complaint.
A. Additional Background
¶ 37 In its complaint, Blue Ribbon alleged that it was owed the
amount of its final invoice. Blue Ribbon’s damage disclosure and
the trial management order similarly stated that Blue Ribbon
sought to recover as damages the amount of the final invoice.
¶ 38 At trial, Blue Ribbon’s counsel asked Mordhorst about another
category of damages that was not included in the final invoice.
Specifically, Mordhorst testified that the Cardamones still owed
Blue Ribbon $5,653.99 for framing changes that were not covered
by insurance. He requested that this amount be awarded or
credited to Blue Ribbon. The Cardamones’ counsel did not object to
this testimony, but on cross-examination, he introduced Blue
Ribbon’s damages disclosure as an exhibit to show that Mordhorst’s
18
testimony was inconsistent with that disclosure. On cross-
examination, Mr. Cardamone acknowledged that the Cardamones
had not paid the full balance of the noninsurance framing invoice,
but he said that it was because the framing was not completed.
¶ 39 The district court awarded Blue Ribbon the unpaid amount of
that invoice. It recognized that the amount was not included in
Blue Ribbon’s complaint, but it concluded that the issue had been
tried by consent because the Cardamones did not object.
B. Applicable Law and Standard of Review
¶ 40 C.R.C.P. 54(c) provides that “every final judgment shall grant
the relief to which the party in whose favor it is rendered is entitled,
even if the party has not demanded such relief in [its] pleadings.”
See also Twp. Homeowners Ass’n v. Arapahoe Roofing & Sheet Metal
Co., 844 P.2d 1316, 1318 (Colo. App. 1992) (“[T]he relief ultimately
granted is governed not by the demand [in the complaint], but by
the facts alleged, the issues, and the proof.”).
¶ 41 Thus, “[w]hen issues not raised by the pleadings are tried by
express or implied consent of the parties, they shall be treated in all
respects as if they had been raised in the pleadings,” even if the
pleadings are not amended. C.R.C.P. 15(b). A party who fails to
19
object to the introduction of evidence concerning such an issue is
deemed to consent. Bittle v. CAM-Colorado, LLC, 2012 COA 93,
¶ 43. Under such circumstances, the district court “has the duty to
consider [the] issue . . . even if the matter was not pled and no
formal application was made to amend” the pleadings, so long as
the issue was “intentionally and actually tried.” Id. at ¶¶ 43-44.
¶ 42 We review the district court’s decision to address an issue not
raised in the pleadings for an abuse of discretion. Id. at ¶ 41.
C. Analysis
¶ 43 We conclude that the district court did not abuse its discretion
by awarding Blue Ribbon the unpaid amount of the noninsurance
framing costs for three reasons.
¶ 44 First, the issue was “intentionally and actually tried.” Id. at
¶ 44. Not only did Mordhorst testify that Blue Ribbon was owed
this amount, but he explicitly requested that it be awarded to Blue
Ribbon as part of the judgment in the case. Blue Ribbon’s counsel
also cross-examined Mr. Cardamone about the remaining balance.
Then, in Blue Ribbon’s proposed findings of fact after trial, which
the district court ordered in lieu of closing argument, Blue Ribbon
requested that the court award it that amount. Thus, Blue Ribbon
20
did more than merely present “some evidence . . . germane to the
issue.” Id. (citation omitted). It put the Cardamones on notice that
Blue Ribbon was seeking to recover that amount.
¶ 45 Second, the Cardamones did not object to Mordhorst’s
testimony. See id. at ¶ 43 (“[C]onsent is generally found when
evidence is introduced without objection . . . .”) (citation omitted).
Although their counsel later introduced Blue Ribbon’s damage
disclosure to show that Mordhorst’s testimony was inconsistent
with it, he did not argue that Blue Ribbon was precluded from
seeking the additional amount. Nor did he object to Blue Ribbon’s
cross-examination of Mr. Cardamone on the same point.
¶ 46 Third, even if the Cardamones did not consent to try the issue,
they have not shown that they were prejudiced. See Davis v.
GuideOne Mut. Ins. Co., 2012 COA 70M, ¶ 73. Prejudice in this
context means “a lack of opportunity to prepare to meet the
unpleaded issue.” Id. at ¶ 74 (citation omitted). As the district
court noted, there was no dispute that Blue Ribbon had billed the
Cardamones for this amount and the Cardamones had not paid it.
To the extent the Cardamones assert that they did not pay the
21
balance because “the framing wasn’t completed,” they had ample
opportunity to litigate that issue as part of their counterclaim.
¶ 47 The district court therefore did not abuse its discretion in
considering this unpleaded issue under C.R.C.P. 15(b).
2
IV. Disposition
¶ 48 The judgment is affirmed.
JUDGE FOX and JUDGE JOHNSON concur.
2
The Cardamones’ reference to the district court’s denial of their
pretrial motion to amend their counterclaims to add additional
parties is a non sequitur. That motion — which Blue Ribbon
opposed — has nothing to do with whether the unpaid framing
invoice issue was tried by the consent of the parties.

Case Details

Case Name: Mordhorst Cleaning v. Cardamone
Court Name: Colorado Court of Appeals
Date Published: Sep 12, 2024
Docket Number: 23CA0781
Court Abbreviation: Colo. Ct. App.
Read the detailed case summary
AI-generated responses must be verified and are not legal advice.
Your Notebook is empty. To add cases, bookmark them from your search, or select Add Cases to extract citations from a PDF or a block of text.