274 F. 799 | 2d Cir. | 1921
This libel was filed in personam by the appellee, seeking to recover damages for breach of contract which resulted in injury to the scow Geraldine on August 17, 1916. The appellant was engaged in the construction of a subway under Flat-bush avenue in the borough of Brooklyn, New York City. On May
The theory of the libel is that the appellant’s slip was not of ample depth, and that, beginning with the removal of the dirt from the pier, it became necessary from time to time to dredge out the slip because the excavated material, in loading, would drop into the canal. On August 15, 1916, the scow Geraldine was placed alongside the appellant’s dock on the Ninth street slip for the purpose of receiving excavated material. The loading was commenced on the 16th and was continued on the 17th; on the afternoon of the 17th the scow was found grounded and leaking. She had six inches of water in her and proved to be two-thirds loaded. She grounded first at'the bow, and there was considerable leaking at the stem. About 15 or 20 minutes after she had grounded, a tug tried unsuccessfully to pull her away into deep water. She settled further and continued to leak rapidly. The pumping proved unavailing, and eventually her bottom planks and other parts amidships broke. It proved that the bottom at this point was too shallow at low tide, and this was the cause of the damage.
The contract between the parties provided that the libelant was “to supply the necessary boats, known as dumpers and derrick scows, and bring them alongside of the dock of the Cranford Company, in a position to receive the earth, sand, and gravel, and, when the same have been loaded and trimmed aboard the said scows by the Cranford Company, dispose of said earth,” and further “the Cranford Company agrees that they will provide berth at its dock for the loading of the above-mentioned boats, where there will be sufficient depth of water to float scows and dumpers at all stages of the tide.” There was sufficient evidence to warrant the finding of the District Judge below that the cause of the injury was the failure to carry out the provisions of the contract requiring appellant to provide a berth with water of sufficient depth 4o float scows and dumpers at all stages of the tide.
Hope for success on this appeal is based upon alleged error committed below in the trial court excluding testimony offered by the appellant tending to show that shallowness of the slip was caused entirely by the leakage of the excavating materials from the scows and dumpers which came to the slip. The contract provided that the obligation to keep a sufficient depth of water was upon the appellant and failure to carry out the provisions of the contract made the appellant primarily liable. Healey v. Moran Towing Co., 253 Fed. 334, 165 C. C. A. 116. It is contended that the court excluded testimony offered by the appellant tending to show that the appellee’s boats leaked the materials which were placed upon them, and that this filled up the bottom of the slip. This court will not reverse a decree because of error in excluding competent testimony in an admiralty case, for that would presuppose that the testimony offered would have actually
The appellee’s duty under the contract was to deliver the boats alongside the dock in a position to receive the earth, and if it became necessary thereafter to shift the scow, it was the duty of the appellant to do so, and to load and trim the scow, and then provide sufficient water at all tides to permit reasonably safe navigation. We think the court below committed no error in granting a decree to the appellee.
'Decree affirmed.