292 F. 122 | 3rd Cir. | 1923
The District Judge struck out the complaint of David H. Moore, and entered judgment in favor of the defendant, Shisler. The case is here on writ of error from that judgment. The defendant owned a tract of land in Atlantic City, N. J., and entered into a written contract on July 25,1919, with Wesley B. Porch to erect 42 dwellings on the tract. Four days later, July 29, 1919, before any work was done, the contract and specifications were filed in the clerk’s office of Atlantic county to protect the owner against mechanics’ liens. Porch, general contractor, entered into a contract with David H. Moore, subcontractor, to furnish and install the plumbing and heating in the 42 houses. On completion of the plumbing and heating, Moore demanded payment from Porch, who refused to pay, and Moore thereupon notified Shisler in writing of the demand and refusal, and brought suit against Shisler in the Atlantic county circuit court. The case was removed to the federal District Court, and on motion the complaint was stricken out on the ground that suit was instituted before a cause of
The contract between Porch and Moore provides:
“On or about the 1st day of every month during the progress of the work, the plumbing and heating contractor [plaintiff] shall submit to the general contractor [Porch] a copy of the pay roll and other expenditures put forth by him, the plumbing and heating contractor, during the previous month; also a statement of the cost of materials incorporated in the structures. Upon the general contractor’s receipt of such, statement from the plumbing and heating contractor, he shall, within three days of the receipt of same, pay or cause to be paid to the plumbing and heating contractor a sum equal to 50 per cent, of such statement presented by the plumbing and heating contractor.
“At the entire and full completion of the work, the plumbing and heating contractor shall submit to the general contractor a full statement, showing the contract price for the work, plus any additions or deductions, with the full credits, and payment for the balance shall be made within thirty days after the receipt by the general contractor of such statement.”
According to Schedule B, annexed to the complaint, the work done and material furnished by plaintiff amounted to $56,152.10, and of that amount he had been paid $36,252.50, leaving a balance due of $19,-899.60. This balance, with interest, constituted the plaintiff’s demand. Consequently more than 50 per cent, of plaintiff’s monthly statement had been paid, and whatever was due, if anything, was part of the final payment, due 30 days after the submission of a “full statement” to the general contractor. But complaint shows that plaintiff completed his work, rendered his “full statement,” made his demand, and served his stop notice, all on July 16, 1920. The defendant alleged that nothing was due Porch under the contract, because he- abandoned the contract, and the work of completing the houses by defendant in accordance with its terms required all the money due the contractor. These facts could only be established by a trial. But, whether or not defendant could establish them, the plaintiff is bound by his contract with the contractor, and could not demand the money in question, except in accordance with the terms of his contract. Payment of the second 50 per cent, could be made at any time within 30 days from the time of the
We are unable to follow plaintiff’s contention, and the judgment of the District Court is affirmed.