88 Wash. 602 | Wash. | 1915
On or about the 30th day of August, 1911, Josiah C. Moore, appellant, and Charles W. Saunders et al.,
In connection with these negotiations, two letters were written; one from appellant to respondents on August SI, and one from respondents to appellant on September 1st. Appellant contends that these letters constituted the entire contract between the parties. Respondents contend that they constituted only a part of the contract. Appellant prepared plans and specifications and submitted them to respondents about the 1st of October. Respondents, after examination of the plans, marked them approved and submitted them to contractors, inviting bids thereon. About October 7th, respondents notified appellant that the plans had been objected to and criticised by intending bidders and were unsatisfactory; that they were going to employ another engineer to correct them, and that his services were terminated. Appellant brought this action for the alleged contract price.
Granting, but without holding, that the two letters relied on are enough to make a contract between the parties, there is still an implication which the law raises where one, holding himself out as possessed of skill and accomplishment in a particular line of endeavor, contracts to do a certain thing which is dependent upon such expert knowledge: It is—that the thing when done will be fit for the use intended. Appellant, in seeming affirmance of this rule, relies upon the fact that respondents marked the plans “approved,” after they had been criticised by the Seattle Machinery Dealers Association and certain corrections and changes had been made by him in accordance with suggestions made by it. The testimony, however, will not bear out the contention that the association ever saw the plans. The specifications were submitted to the association and its opinion as to their fairness to intending bidders was invited.. They made some suggestions
The only question in the case, therefore, is whether the indorsement of the word “approved,” after the plans had been retained several days, is enough to bind respondents to pay appellant his per centum upon the contract price.
The testimony is that respondents are architects and not mechanical engineers, and have no technical knowledge of what such plans and specifications as were drawn by appellant should consist of or require, and it was because of this lack of knowledge that appellant was employed.
There is testimony tending to show that the indorsement of the word “approved” does not mean an acceptance which would bind a party to pay for them whether or no; that such act is no more than an identification or authentication, and does not exempt the one offering the plans from his implied contract to offer'a workable plan.
Upon the questions, whether the word “approved” means acceptance, and whether the plans offered were workable plans, we are not prepared, after reading the whole record, to say that the findings of the trial judge are not sustained by a preponderance of the evidence.
Several affidavits made by experienced mechanical engineers were offered in support of a motion for a new trial. It is asserted by the affiants that the plans are workable and that the word “approved,” when indorsed upon plans -and specifications, means adoption and acceptance. The meaning of the word “approved,” and the fitness of the plans, were made the material issues in the case by appellant, and upon these questions both sides offered the opinions of witnesses who qualified as expert mechanical engineers.
Under the assumption that either side might cumulate to an indefinite degree opinion evidence, testimony of customs, and the meaning of trade-names, it is universally held that new trials will not be granted for the purpose of measuring the opinions of men.
The case of Kenway v. Hoffman, 51 Wash. 105, 98 Pac. 98, is in many ways in point. There the question was as to certain defects in building plans. The plans had been offered as evidence at the trial. It was thereafter sought to show by experts that the plans were defective and incomplete. The court said “this matter was entirely open for investigation at the trial, and should have been taken up at that time. . . .” “The suggestions in the affidavits do not, therefore, constitute newly discovered evidence which could not, with reasonable diligence, have been discovered and produced at the trial.”
The motion for a new trial was properly overruled.
Affirmed.
Morris, C. J., Ellis, Mount, and Fullerton, JJ., concur.