215 Mo. 705 | Mo. | 1909
Plaintiffs sued on a quantum meruit for the reasonable value of labor performed and material furnished.
The petition states in substance that on the 14th day of November, 1903, defendants entered into, a written contract with plaintiffs for the erection by plaintiffs of what is known as the gymnasium building at Warrensburg, Missouri, and to be used in connection with the State Normal School for Normal School District No, 2; that in pursuance of the contract plaintiffs entered upon the construction of the building and had constructed a portion thereof, when, on the 16th day of September, 1904, defendant wrongfully declared said contract at an end and prevented plaintiffs from .completing the building; that on and prior to said date plaintiffs had performed work and furnished material in the construction of said building, and had delivered upon the premises, for the purposes of being used in said building, material of the reasonable value of $22,086.95; that plaintiffs had received of defendants $9,008, leaving a balance due and unpaid of $13,078.95, for which, with costs, plaintiffs asked judgment.
Defendant for amended answer to the petition admitted that the plaintiffs were partners as alleged in the petition, doing business under the firm name of Moore Brothers; denied that defendant wrongfully
It was not alleged in the answer that the labor performed and material used in the construction of the building by plaintiffs up to the time defendant terminated the contract were not in compliance with the contract. The answer did not ask to recover back any portion of the money already paid by defendant to plaintiffs. It did not allege that the architect McDonald or the Board condemned any material furnished by plaintiffs for the construction of the building. The answer is voluminous and covers forty-eight printed pages.
Plaintiffs in their reply admitted the execution of the contract set out in the answer; that plaintiffs commenced the erection of the building under the contract and that on the 16th day of September, 1904, defendants stopped plaintiffs from working on the building and took possession. Plaintiffs then alleged that they would have completed the building according to the terms of the contract, but that they were prevented from doing so by “the wrongful acts, conduct, omissions- and neglect of the defendant’s agent, superintendent and architect, George E. McDonald, together with the weather conditions existing during the greater portion of the time after the plaintiffs entered upon the -construction of said building and until the said 16th day of September, 1904. ’ ’ The reply then further alleges that the superintendent McDonald wrongfully
Plaintiffs under the last provision of article 8 of the contract were not responsible for delays caused by strikes, accident and the unusual action of the elements and other unavoidable circumstances.
The record in this ease covers 685 pages.
The evidence showed that plaintiffs resided in Kansas City, Missouri, were contractors and builders in good standing, had engaged extensively in that business for many years and that A. A. Moore had charge of the construction of the building.
Plaintiffs introduced photographs showing the structure as it stood on September 16, 1904, at the time the defendants put plaintiffs off and took possession of the work. The first photograph showed the west side of the building; the second the east, the third the north, and the fourth the south side. The fifth picture showed the interior and the brick partition walls which extended to the floor joists, as high as they were built. As appears from the photographs the first or basement story of the building was constructed and some of the joists were laid on that floor, the brick partition walls were practically finished and practically all of the window caps were on. Plaintiffs introduced an itemized statement of the labor performed and of the material furnished by plaintiffs up to the time the contract was terminated and possession taken by defendants. After setting out
Mr. Latimer stated that he was a -contractor and builder, lived in Kansas City and was engaged principally in making estimates of material and labor necessary for the construction of buildings. He stated that at the request of A. A. Moore, one of the plaintiffs, about the time defendants took possession of the building he made an inventory of the labor performed and material furnished by plaintiffs in the construction of the building, produced the original inventory and estimates, and stated that the estimate in gross of the labor and material in the building amounted to $17,705.07 and that the material on the ground ready to be used in construction amounted to $3,076.40; that Mr. Moore, referring to A. A. Moore, foreman, and Mr. Moore’s son assisted him in making the inventory and it was carefully and correctly made. He stated that the building had reached what is termed the first or basement story and that some of the joists were on and the-brick partitions were practically all in. He was shown the itemized statement before referred to and stated that it was correct and practically the same as his own, except that his estimates aggregated
James A. Moore, a member of the firm, stated that he in connection with Mr. Latimer and Mr. Hout after defendants took possession of the building made the inventory and that he afterwards copied it and extended the prices as shown in the itemized statement, and that the statement was correct, together with the aggregates. He produced the original statement made by him and said it corresponded with the statement introduced in evidence, except that all the prices had not been extended on the original. He further stated that there had been no work on the job by the defendants at the time he made this inventory.
Mr. Dan M. Hout testified that he had been a contractor and builder for thirty-five years and was employed by the plaintiffs to look after the construction of the building. He stated that he was on the
The witness Mr. Latimer^ having stated how the prices were fixed and the estimates arrived at, referring to each item of plaintiff’s account, the witnesses A. A. Moore, James Moore and Hout were not asked either by plaintiffs or by defendants to gO' over the ground again. They testified to the correctness of the items and that the aggregates and balance as shown in the account and claimed by the plaintiffs were correct.
Plaintiffs’ testimony tended to show that they were not to blame for any delays that occurred in the construction of the building. Article 8 of the contract provided that plaintiffs should commence work immediately upon the building or within one week from the date of the approval of their bond and cause a steady progress of the same until its completion. Plaintiffs’ testimony tended to show that it was practicable tó do so, and that the winter weather following the execution of the contract would not have interfered with that work. Mr. Latimer testified that it would have been practicable to have commenced the construction of the building on the first of December, 1903, and to have proceeded continuously. And the testimony of Hout and Forrester was to the same effect. Moore testified that while he could not get any of the cut stone for the construction of the walls of the building, he could obtain all of the other material necessary to proceed with the construction of the
When the spring came, commencing with March and continuing up till September, there was an unusual rain fall, which caused another delay despite anything plaintiffs could do-. The fact that they had not been permitted by the architect to lay the foundation and put in the concrete during the winter and before the rains came made their work much more difficult during the rainy season. He testified that it was the most unusual spring he had ever seen, and that he had lived in Missouri for more than forty years. Aubry F. Smithson testified that he kept a record of the precipitation in Warrensburg during the spring of 1904, commencing with April. He testified to the number of days that rain fell, commencing on April 21st, and ending with August; that the total rain fall in Warrensburg during that time was 34.56 inches. Other
On the 27th day of April plaintiffs received of Pickle Bros, three wagon loads of sawed or cut stone. That stone had not been delivered earlier because it could not be quarried in the winter or in the early spring owing to the wet season. The evidence showed that plaintiffs, in order to get the stone from the Pickles as soon as possible, had gone on a note of the Pickles to enable them to raise money to quarry the stone. On the arrival of the stone, April 27th, defendants’ superintendent, McDonald, promptly condemned every foot of it. The Pickles refused to furnish more, all of which caused another delay. There were two quarries, one called the Pickle quarry and the other called the Forrester quarry, each situated about two miles from Warrensburg. Defendants’ superintendent, McDonald, then went to the Forrester quarry, examined it and the stone, four loads of which were on the cars and open to inspection, pronounced the 'stone good, fit to go into the building, and ordered and directed plaintiffs to make a contract with Mr. Forrester for stone to finish the building. Thereupon the plaintiffs, in accordance with the direction of Superintendent McDonald, contracted with Forrester for stone to finish the building. A written contract was entered into, dated May 17, 1904; Thereupon Forrester commenced to quarry stone immediately and sent it to the mill to be sawed for delivery to the plaintiffs at the building. On May 28th plaintiffs received of Forrester the first consignment of stone, and all the same quality of stone defendants’ superintendent, McDonald, examined and directed to be purchased. This stone McDonald also condemned, “pretty near all of it.”
The evidence showed that McDonald in this way condemned a great deal of stone that ought not to have been condemned under the contract and that was good building stone. Some, of the same stone condemned by McDonald while plaintiffs were on the job was accepted by him and put in the building after defendant terminated the contract.
In a conversation defendants’ superintendent, McDonald had with Mr. Forrester about the time he directed the plaintiffs to buy stone from Forrester, McDonald asked Mr. Forrester what he was going to charge the plaintiffs for stone and when told by Mr. Forrester that he was going to charge the same price
McDonald said to Mr. Graham, “He [McDonald] was going to take Moore Bros, down the line that they had never gone before and that they would know it before he got through with them, that he would make their heels hit the ceiling.” Mr. Graham said he had other conversations with McDonald to the same effect. Mr. Graham testified further that he was hauling at the time for plaintiffs and that McDonald told him that plaintiffs were not paying him enough for his work and that they did not pay their hands wages enough.
Mr. W. L. Hyer testified that McDonald requested him to see James Miller, who was then working for plaintiffs upon this job, and induce Mr. Miller to quit work. Mr. Hyer afterwards saw Mr. Miller and repeated to him what McDonald had said.
Plaintiffs were delayed in the construction of the building some week or ten days by a strike of the hands.
Mr. A. A. Moore testified that the delays heretofore mentioned all told amounted to five months and
Mr. James A. Moore, on cross-examination, testified that he made the figures and presented the bid for plaintiffs for the construction of this building and that there was a reasonable profit in the contract for the plaintiffs had they been permitted to complete the building. Mr. Moore presented his figures made at that time, which corroborated his statement. Mr. Moore further testified that McDonald at the time showed him the figures that he had made, which ran about $40,000: for the construction of the building.
Plaintiffs ’ evidence tended to prove that Mr. A. A. Moore on the part of the plaintiffs gave the building his personal and all necessary attention and supervision, and that D. M. Hout, the foreman employed, was a-competent man.
The court submitted the question as to the causes of the delay in the construction of the building to the jury-
The defendants’ evidence did not contradict the testimony of the plaintiffs, but corroborated it.
Defendants introduced no testimony in conflict with plaintiffs’ testimony showing that it was practicable to have commenced the construction of the building immediately upon the execution of the contract in the fall of 1903, and to have proceeded until the building was finished; that McDonald, defendants’ architect and superintendent, refused to permit plaintiffs to commence upon the- execution of the contract, but delayed them until the spring of 1904, and that plaintiffs were delayed by the unusual and unprecedented rainfall in the spring of 1904, and by a strike.
Defendants’ architect and superintendent, George E. McDonald, was sworn by defendants and testified in the case. He did not deny that he had ordered plaintiffs not to commence the building until spring, 1904, or that he had condemned all of the Pickle stone.
Defendants’ evidence showed that after they terminated the contract with the plaintiffs they, in connection with their superintendent, George E. McDonald, made a contract with the Pickles for stone to finish the building and with which they did finish the construction of the building. The stone furnished by Pickle to defendants and their superintendent, McDonald, was from the same quarry and the same character of stone as that furnished by Pickle to. plaintiffs and condemned by defendants’ superintendent, McDonald, and was practically all approved, a very small portion of it condemned. Defendants’ bookkeeper testified that the total of Pickle’s bill for stone under this contract was $6,274.76, and the total amount of stone rejected amounted to only $248.50, being less than four per cent, and he further stated that this deduction arose partly on account of stone not being prepared in proper sizes and over a controversy as to a blacksmith bill.
Defendants introduced Charles Briener, who testified that he had been a stone contractor and superintendent for forty years, that he had built Convention Hall in Kansas City, that he examined the building after plaintiffs were put off the job, and that the material furnished and labor performed by plaintiffs were better than the contract called for and that he had' told McDonald so. He stated further, in response to question by defendants, that the work performed by plaintiff's was the hardest part of the job. He said: ‘ ‘ Laying the work and putting on the corners and getting ready for the work to be established is the hardest part and when you get to a certain height you have certain preparations for all of your material and you can rush it and it is easier.” McDonald entered no denial to this testimony or the testimony of Joseph Stone to the same effect. Nor did he deny that he stated to James A. Moore that the building could be erected for $40,000' as testified to by Moore.
As to the question of the value of the material furnished and labor performed by plaintiffs, defendants introduced testimony in conflict with the estimates testified to by plaintiffs ’ witnesses. Defendants, however, introduced no itemized statement showing the
Defendants’ testimony showed that after they took charge of the building they took their time and spent money freely. Defendants retained the services of their superintendent, George E. McDonald, hired Mr. J. N. Suddath to superintend, John Volmer superintendent or foreman of the stonework on the stone building, and Samuel Bratten to keep books for the “Board of Regents at the gymnasium building,” all in addition to the employees who labored with their hands. In this way the labor account amounted to $16,769.75, in a total expenditure for labor and material of $32,181.65. In other words, defendants expended $16,769.75 to put in place in the building only $15,411.90 worth of material.
One of the defendants’ superintendents, George E. McDonald, testified at the trial on the 21st day of August, 1905, eleven months and five days after defendants terminated the contract, that he would spend another three months and would expend $20,493.90 more money in completing the building.
Defendants offered no evidence as to the item of $3,250‘, which the answer alleges they had and would spend in litigation over this contract.
This first instruction of plaintiffs is challenged because it is asserted that it is a peremptory direction to the jury to- find for the plaintiffs, even though the amount theretofore paid by defendants was equal to or exceeded the value of plaintiffs’ work and materials. This is a misconception of the instruction. The right of plaintiffs to recover the value of the work done and materials furnished, without diminution by damages, was conditional, first, that the jury should find that defendants wrongfully refused to permit plaintiffs to perform their contract, and second, in no event were the jury permitted to find beyond the reasonable value of the work and labor furnished up- to the day they were forbidden to- do anything further on the building, and they were peremptorily required to allow defendants the amount already paid to plaintiffs.
As to the further criticism, that the instruction left the jury without any guide as to what would constitute a wrongful termination of the contract by defendants-, we think it was equally groundless. The jury were fully advised in plaintiffs’ second instruction and defendants’ fourth instruction as to what conduct on the part of the plaintiffs would have justified defendants in dismissing plaintiffs and doing the work themselves. The instructions were to be -considered together, and when so read, the jury could not have been misled as to what conduct on part of plaintiffs justified defendants in taking the building out of their hands, especially when defendants’ instructions 7 and 8 are considered. We think the objections are without basis. Moreover, the jury found a sub
II. On the oral argument and in the briefs the insistence was and is that the verdict was excessive. The evidence on the value of the work to be done and materials furnished was all before the jury. Plaintiffs left nothing to conjecture as far as they could avoid it. When they were ordered to stop' work, they called in an expert contractor and builder, and they went over the whole work and measured it and made an itemized statement of all the work and materials. This original statement was before the jury. The witnesses who made it and did the measuring were examined upon it. On the other hand, the evidence as to the value of the work on the part of the defendants was of an unsatisfactory character and the jury credited plaintiffs’ witnesses. We see nothing in the record which would justify .ns in disregarding the finding of the jury as the result of passion, prejudice or obvious mistake. The verdict was approved by our brother on the circuit who saw and heard the witnesses; This assignment must be ruled against the defendants.
III. Defendants now say in their third assignment of error that, under the contract, the opinion of their architect was final in the absence of fraud, and that there is no charge of fraud in the reply. As to this, the reply pleaded that the architect wrongfully, wilfully and without any cause condemned and rejected the material furnished by plaintiffs, and defendants accepted this as a sufficient plea that the contract had been arbitrarily terminated and by their fourth instruction advised the jury of the right of the architect to' reject material and “unless such condemnation showed a design on his part to abuse his powers or to wilfully interefere with and retard the
IY. Error is asserted in refusing defendants’ fifth and eighth instructions and giving their converse, in instruction numbered three given for plaintiffs, in these words: “The court instructs the jury that the defendant in this case cannot in any event recover the sum of twenty dollars per day or any part thereof by reason of the provision in the contract providing that plaintiffs shall pay to defendants the sum of twenty dollars per day for each week day intervening after December 1, 1904, until the completion of the work.”
Article 8 of the contract provided: “The contractors hereby agree to commence work upon the building within one week from the date of the approval of their bond by the president of the board and to cause steady progress of same and to complete the works according to the drawings, plans, details and specifications in their true and full meaning on or before the first day of December, 1904, and 'upon their failure to so complete the work at the above-mentioned time they shall pay the board the sum of twenty dollars per day for each week day intervening after said date until the completion of the work.” The defendants prayed the court in effect that if plaintiffs failed to comply with their contract and by reason thereof it was necessary for defendants to take charge of and proceed to complete the building at a reasonable cost and in a reasonable time, then defendants were entitled to recover twenty dollars a day as liquidated damages as a counterclaim, not to- exceed $6,260, the time defendants claimed necessary to complete said building being 313 days. It is conceded defendants terminated the contract over two months before the time fixed by contract.
Article 4 under which defendants asserted their right to take charge and complete the contract, makes no provision for this penalty, but bound plaintiffs and their surety to- make good all reasonable expenses, charges, damage and cost of litigation.
In Gallagher v. Baird, 66. N. Y. Supp. l. c. 762, 763, a builder, sued on his bond, sought to limit his liability to the penalty in a contract like this, but the court said: “It is manifest that this clause contemplated a completion of the contract, with damages for delay. There was no completion, or attempt to complete, but an utter abandonment, and such clause was not intended to cover such a case, nor was provision made in the contract for such a contingency.” It was held the penalty was not the measure of damages, and obviously it was not.
*We cannot interpolate this clause for penalty into article 4 of the contract. We think the court was unquestionably right in refusing the defendants ’ instructions on this point and in giving plaintiff’s as above set out.
Y. Various objections are urged against plaintiffs’ second instruction, but we have practically disposed of some of them in what we have already said. As to the contention that it assumes the architect interfered with plaintiffs with regard to the concrete, and in rejecting material, a reference to the instruction is a sufficient answer. It expressly submitted those questions to be found by the jury. We think it does not conflict with defendants’ instructions.
YI. Instruction six requested by defendants was properly refused. The contract did not authorize defendants to terminate the contract if plaintiffs furnished an inferior grade of stone. It gave the archi
VII. It is argued that plaintiffs had made an improvident contract and were seeking some pretence to get out of it. All that matter was threshed out before the jury. The evidence consisted of opinions of various builders as to what the building would have cost if built according to plans and specifications. Some thought it would have resulted in loss to plaintiffs; others, that there was a fair profit in it. The jury were competent to pass upon all such suggestions as these and the good faith of plaintiffs. Certain it is that the termination of plaintiffs ’ contract has resulted in a large increase of the cost of this building. It is not our province to pass upon the weight and credibility of the witnesses, but if the plaintiffs’ witnesses are to be believed, as they evidently are, then the jury were fully warranted in finding that the architect did not deal fairly with plaintiffs and that his conduct in delaying the commencement of the building and in regard to the stone was without justification. The defendants have received plaintiffs ’ work and labor and materials and it seems to us that the jury correctly required them to pay for it.