Plaintiff Moore Excavating, Inc., brought this action seeking common-law indemnity and damages for negligence from defendant Consolidated Supply Co. The trial court granted defendant’s motion for summary judgment on both claims and entered judgment for defendant. Plaintiffs appeal requires us to resolve two unrelated issues. The first is whether the discharge element of the claim for common-law indemnity can be satisfied based on plaintiffs settlement of a claim with a third party on which defendant is also liable when the settlement did not legally extinguish defendant’s liability on the claim. The second issue is whether the terms of the contract between plaintiff and defendant create the kind of special relationship that can be a basis for a duty on defendant’s part to further plaintiffs economic interests. For the following reasons, we agree with the trial court’s resolution of both issues and affirm.
On review of a grant of summary judgment, we view the facts and all reasonable inferences that may be drawn from them in the light most favorable to the nonmoving party — in this case, plaintiff. ORCP 47 C;
Robinson v. Lamb’s Wilsonville Thriftway,
Plaintiff entered into an agreement with Aspen Meadows, LLC, (Aspen) to install a domestic water system in a manufactured home development. Plaintiff purchased the pipe and glue for that project from defendant. According to what plaintiff characterizes as “the standard of practice of contractors and suppliers in the industry and the area,” plaintiff relied on defendant to select the appropriate glue for the system “based upon the pipe specifications, the time of year for installation and other factors.” Plaintiff also relied on defendant’s expertise in carrying out that selection.
Plaintiff installed the water system, using the pipes and glue that it received from defendant. After the installation, Aspen discovered that the water system was leaking *327 and, based on that discovery, asserted claims against plaintiff. Plaintiff and Aspen entered into a settlement agreement pursuant to which plaintiff paid Aspen $37,000 and installed a new water system. Also pursuant to that settlement agreement, Aspen released all claims that it had against plaintiff. Plaintiff, for its part, reserved all of its claims against defendant. The settlement agreement did not release Aspen’s claims against defendant.
Defendant moved for summary judgment on plaintiffs indemnity claim on the ground that plaintiff could not prove that it had discharged defendant’s liability to Aspen. Plaintiff responded by producing its settlement agreement with Aspen as well as the affidavit of plaintiffs president, Roy Moore. That affidavit simply stated that Aspen asserted claims against/plaintiff resulting from leaks in the water system and that Moore incurred costs and expenses in defending against and satisfying those claims.
In reply, defendant argued that, because plaintiffs settlement agreement with Aspen did not demonstrate that Aspen released its claims against defendant, plaintiff could not prove that it had discharged defendant’s liability to Aspen. Shortly after defendant filed its reply, plaintiff submitted the affidavit of Jeffrey Payne, Aspen’s managing member, which indicatéd through the following averments that Aspen had no intention of pursuing any claims against defendant:
“5. Neither Aspen nor I have ever pursued or contemplated pursuing any claim against Consolidated Supply Co. arising out of the leaks in the water lines at the Project, or any other issues related to the Project.
“6. Neither Aspen nor I have any intention of pursuing any claim against Consolidated Supply Co. now or at any time in the future related to the water line leaks at the Project.
“7. As a result of the performance by Moore pursuant to the Mutual Release and Settlement Agreement between Aspen and Moore, Aspen is satisfied that it has received adequate compensation for all damages resulting from the *328 leaks in the domestic water line system at the Project discussed above and the domestic water line system at the Project has been replaced.”
In ruling on defendant’s motion for summary judgment on the indemnity claim, the trial court concluded that, because the settlement agreement did not expressly release Aspen’s claims against defendant, and notwithstanding the averments in the Payne affidavit, those claims survived. The trial court therefore determined that plaintiff produced no evidence to create a material issue of fact as to whether plaintiff had discharged defendant’s liability to Aspen. Thus, as a matter of law, plaintiff was not entitled to indemnity.
Plaintiffs primary argument on appeal is that the trial court erred in concluding that it was required to obtain a release of Aspen’s claims against defendant.
1
Specifically, plaintiff argues that the Supreme Court’s decision in
Savelich Logging v. Preston Mill Co.,
In an action for indemnity, a plaintiff must plead and prove that (1) it has discharged a legal obligation owed to a third party; (2) the defendant was also liable to the third party; and (3) as between the plaintiff and the defendant, the
*329
obligation ought to be discharged by the defendant.
Fulton Ins. v. White Motor Corp.,
As earlier described, plaintiff offered three pieces of evidence in support of its position: the settlement agreement with Aspen, the Moore affidavit, and the Payne affidavit. The settlement agreement merely indicated that Aspen released its claims against plaintiff and that plaintiff reserved its claims against defendant. Nowhere did the settlement agreement indicate that Aspen released its claims against defendant. The Moore affidavit was similarly unavailing. Moore simply averred that Aspen asserted claims against plaintiff and that plaintiff incurred costs and expenses in defending against and satisfying those claims. Finally, the Payne affidavit simply stated that Aspen received adequate compensation for its damages and has no intention of pursuing any claims against defendant.
But an indemnity plaintiff must do more than show that the third party is content with a settlement and does not wish to exercise its legal rights against the indemnity defendant. Here, to borrow from the Supreme Court’s discussion of the discharge element in
Savelich Logging,
plaintiffs agreement with Aspen must “operate to protect * * * defendant
*330
against a claim” by Aspen that defendant is also liable for the damages that Aspen sustained as a result of the leaking pipes.
Here, the Payne affidavit establishes that Aspen is, as a factual matter, content with the settlement agreement between it and plaintiff. That affidavit would not, however, support a determination that plaintiff, through the settlement agreement or otherwise, extinguished defendant’s liability to Aspen. As a result, none of the evidence that plaintiff offered created an issue of material fact as to whether plaintiff discharged defendant’s liability to Aspen. The trial court properly granted defendant’s motion for summary judgment on plaintiff’s indemnity claim.
In arguing to the contrary, plaintiff urges that this court’s indemnity decisions require an indemnity plaintiff to show only that it incurred reasonable costs in settling or defending a claim and that those costs should properly be paid by the defendant. In support of that position, plaintiff cites
PGE v. Const. Consult. Assoc.,
*331
Specifically, in
PGE,
the indemnity plaintiff had successfully defended a suit brought by a third party. In seeking indemnity, the plaintiff maintained that, consistently with its successful defense of the underlying action, it was not liable to the third party. Relying on that assertion, the defendant argued that the plaintiff had to prove that it and the defendant had a common liability to the third party. Because the plaintiff denied any liability, it could not prove that element of its indemnity claim. We concluded that, in a case where the indemnity plaintiff denied liability to the third party but nevertheless incurred costs in defending against that claim, it was enough to show that “it was sued, reasonably incurred costs in defending and that, as between it and the putative indemnitor, the indemnitor should bear the burden of the defense.”
PGE,
In subsequent cases, we have reiterated that formulation.
2
We have not, however, stated that the
PGE
formulation was meant to supplant the elements identified in
Fulton.
Rather, as the discussion above suggests, the formulation set forth in
PGE
describes the necessary proof where the indemnity plaintiff denies liability to the third party. It does not dispense with the requirement that the indemnity plaintiff prove, as required by
Savelich Logging,
that it has discharged both its own and the defendant’s liability to the third party. Thus, in
Scott
the indemnity defendant conceded that it was liable for the amounts the indemnity plaintiff sought.
*332 In its second assignment of error, plaintiff argues that the trial court erred in granting defendant’s motion for summary judgment on plaintiffs negligence claim. Plaintiff alleged in its complaint that defendant was negligent “[i]n selecting and providing [plaintiff] with an inappropriate Cement,” and also in “failing to warn [plaintiff] that applying the Cement selected by [defendant] could lead to water leaks and a need to replace the Water System at the Project.” Plaintiff also alleged that defendant “selected the particular type of Cement to be used for installing the Waterlines,” and that plaintiff “was relying on [defendant’s] judgment to select suitable Cement for the Project.”
In response to defendant’s motion for summaryjudgment, plaintiff offered the Moore affidavit in support of its argument that its “negligence claim is viable, based on the economic relationship between [plaintiff] and defendant.” In his affidavit, Moore reiterated that the “glue provided for the Project was chosen by [defendant]” and that, according to “the standard practice in the industry, [plaintiff] provided [defendant] with the specifications for the type of pipe and lengths required for the Project.” Defendant then
“provided a price for the materials, including the glue that [defendant] chose. It is standard practice in the utility and site contracting industry in the Portland Metropolitan Area for contractors such as Moore to rely on pipe suppliers such as [defendant] to select and supply the appropriate type of glue for a domestic water line system to be installed based on the dimension of the materials selected, the time of year the system would be constructed, and other factors.”
The trial court concluded that “the relationship between plaintiff and defendant, typical of contractors and suppliers, was arm’s length, not special,” and granted defendant’s motion. On appeal, plaintiff argues that the parties were in a special relationship because plaintiff authorized defendant to exercise “independent judgment on plaintiffs behalf’ and “in furtherance of [its] economic interests.”
Because the parties’ relationship arises out of a contract, plaintiff may bring a claim for negligence only if defendant is subject to a standard of care independent of the terms of the parties’ contract.
Georgetown Realty v. The Home Ins.
*333
Co.,
“the party who owes the duty has a special responsibility toward the other party. This is so because the party who is owed the duty effectively has authorized the party who owes the duty to exercise independent judgment in the former party’s behalf and in the former party’s interests.”
Id.
at 240 (emphasis in original). In other words, the party who owes the duty is charged with acting “ ‘at least in part, * * * to further the economic interests of the * * * person owed the duty of care.’ ”
Id.
(quoting
Onita Pacific Corp. v. Trustees of Bronson,
We applied those principles in
Gladhart v. Oregon Vineyard Supply Co.,
The trial court dismissed the plaintiffs’ claims. On appeal, the plaintiffs argued that their negligence and negligent misrepresentation claims were viable because the defendants’ “contractual obligation created an independent duty on which to base a tort claim.” Id. at 447. We disagreed. Applying the principles set forth in Georgetown and Conway, *334 we concluded that the plaintiffs had not sufficiently alleged the requisite special relationship. Specifically, we concluded that “ [although plaintiffs allege that they relied on defendants’ representations because of their expertise, plaintiffs do not allege that they employed defendants to exercise independent judgment on their behalf or that they gave control to defendants to achieve a particular outcome.” Id. at 449.
Here, plaintiff argues that “the parties’ contractual relationship reflects that ‘defendant exercised independent judgment on plaintiffs behalf,’ ” because defendant “selected and supplied the glue” after “plaintiff provided defendant with the specifications for the type of pipe.” Such a relationship, however, is not different from the one we considered in Gladhart, where the defendants selected and supplied grape plants. As we explained there, any duty on the seller’s part in that context arises out of the sales contract, not independently of it. Here, defendant contracted to sell plaintiff pipe and glue. In doing so, defendant did not assume an obligation to pursue plaintiffs economic interests. Moreover, the fact that plaintiff relied on defendant for information does not change the nature of their arm’s-length contractual relationship.
In
Conway,
the Supreme Court was careful to “emphasize the distinction” between a plaintiff who relies on representations, as plaintiff did here, and one who is “placed in a position in which he had a
right
to rely” on representations.
Affirmed.
Notes
Although plaintiffs opening brief suggested it was entitled to indemnity because it had partially discharged defendant’s liability to Aspen, in its reply brief plaintiff clarified that it did not intend to “invoke any indemnity concept premised on ‘partial indemnity.’ ” Rather, plaintiffs argument on appeal is that “its work performed for Aspen — along with its monetary payment — ‘fully extinguished’ defendant’s liability to Aspen.”
See Smith v. Urich,
