delivered the opinion of the Court.
A sub-subcontractor for the furnishing and installation of an air conditioning machine in the erection of a public junior high
On March 19, 1962, the appellee, Glassman Construction Company, Inc. (Glassman) and the Montgomery County Board of Education (the Board) entered into a general construction contract whereby, for a consideration of $1,742,600.00, Glass-man agreed to furnish all labor and materials necessary for the construction of the Randolph Junior High School in Rockville, Maryland. On the same date, in accordance with Code (1957), Article 90, Section 11 (the statute), Glassman, as principal, and the appellee, Home Indemnity Company (Home Indemnity), as surety, executed a labor and materials payment bond in favor of the Board as obligee in the sum of $1,742,600.00. Thereafter, Glassman entered into a subcontract with one John T. Lane (Lane) whereby Lane agreed to perform the heating, electrical and air conditioning work involved in the project. Lane entered into a contract with the beneficial appellant, Carrier Corporation (Carrier), whereby, for a consideration of $103,750.00, subsequently reduced to $102,000.00, Carrier agreed to install certain air conditioning equipment, including a centrifugal refrigeration machine.
Carrier brought suit under the statute and bond. Its action was in two counts. The first sought to recover $22,637.98 as the balance due Carrier on its original contract with Lane. As to this count, a judgment by consent was entered in favor of Carrier and satisfied by Glassman. In the second count, Car
The bond was conditioned upon the prompt payment by Glassman to all claimants for all labor and material used or reasonably required for use in the performance of the contract for the construction of Randolph Junior High School. “Claimants” were defined to include persons having a direct contract with a subcontractor of the principal.
The bond further provided as follows:
“3. No suit or action shall be commenced hereunder by any claimant,
a. Unless claimant, other than one having a direct contract with the Principal, shall have given written notice to any two of the following: the Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed. Such notice shall be served by mailing the same by registered mail or certified mail, postage prepaid, in an envelope addressed to the Principal, Owner or Surety, at any place where an office is regularly maintained for the transaction of business,'or served in any manner in which legal process may be served in the state in which the aforesaid project is located, save that such service need not be made by a public officer.”
The quoted terms of the bond embody the relevant terms of the statute.
At the trial, Ferdinand Rossiter testified for Carrier. He is Service Supervisor for the Washington, D. C. area in which
A major part of the alleged repair work consisted of the dehumidification of the centrifugal refrigeration machine. Rossiter testified that normally only about 40 hours of dehydration are required for this type of machine, but that, because of the amount of water in the machine and other conditions caused by the flood, the dehydration of this particular machine took approximately 300 hours. The dehydration process was started in the week ending May 29, 1963, according to Rossiter, and was completed on July 28. Several time tickets of an employee of Carrier were introduced in evidence; the one for the week ending July 30, 1963 shows that the last work on the machine was done on July 28.
In a letter dated, on its face, October 25, 1963, addressed to Home Indemnity, with copies to the Board and Glassman, Carrier referred to its earlier letter of September 5, in which it claimed some $33,000 in connection with its original work for the high school, and stated that it amended its claim to include $18,921.50 for services rendered to make necessary repairs to the centrifugal air conditioning machine which was damaged by flood. The letter was sent by certified mail. The Postoffice receipts show that Glassman and the Board received their copies of the letter on October 28, which was a Monday. October 25 was a Friday. The last day of the 90 day period from July 28 was Saturday, October 26.
In granting the appellees’ motion to dismiss, Judge Mathias
We are constrained to differ with the learned judge as to the conclusions upon which he rested his decision. The last issue discussed, although not decided by him, was briefed and argued -in this appeal and we decide it under Maryland Rule 885. We shall consider the three issues seriatim.
I
Rossiter’s testimony on direct examination that the work done by Carrier on July 28 was in connection with the repair of the machine was explicit and unequivocal. Under cross-examination, he testified that, to the extent dehydration is normally required, Carrier was doing basic contract work for at least part of the time spent in dehydration. He seemed to be confused by the form in which some of the questions were put to him, but said that the dehydration of the machine was the last item of work he could find that was specifically and solely related to repair work as opposed to contract work. He could not designate the time spent on the job which was required for normal work as distinguished from time spent on repair. He admitted that the time ticket for the week-end of June 26, 1963, was the last specific ticket that indicates solely work on repair.
On re-direct examination, Rossiter again testified that the dehydration process was begun on May 29. He said that, normally, that process would have been over long before July 28, and testified, as he had on direct examination, that the dehydra
The appellees seek to uphold the trial court’s ruling on this issue under the rule that when the testimony of a witness is so vague, indefinite and self-contradictory as to be plainly of no probative value, it cannot be the basis of a legal conclusion. We find that rule inapplicable in this case. On a motion to dismiss, or for a directed verdict when the case is tried by a jury, the party against whom the relief is prayed is entitled to have the evidence and all reasonable inferences to be drawn therefrom viewed in the light most favorable to him. So viewed, we find that Rossiter’s testimony on behalf of Carrier was ample to have the issue of whether any repair work was done on July 28 submitted to the trier of the facts.
Rossiter’s testimony, under cross-examination, that he could not designate the time spent on repair work as distinguished from work on the original contract may well be taken as a general answer to a general question. That testimony must be viewed in the context of his prior statements, from which he did not depart, that, had it not been for the damage done by the flood, the dehydration work would have been finished long before July 28. Rossiter’s statement that the time record for the week-end of June 26 is the last that specifically related to repair work, taken in conjunction with the exhibits offered on behalf of Carrier, is consistent with his unequivocal testimony on direct and re-direct examination, that the work on July 28 was repair work. The time sheets for the week-end of June 26 show that an employee of Carrier was leak testing the machine at that time and found water in it from the original flooding. Clearly, that report could only relate to the repair work. The sheet for July 28 referred only in general terms to the dehydration, but the nature of the dehydration, as part of the repair job, is clearly evident by Rossiter’s testimony that, if it had not been for the damage caused by the flooding, the dehydration essential under the original contract would have been finished long before.
The weight of the testimony on behalf of Carrier was for the trier of the facts. But the sufficiency of that testimony, with
II
Judge Mathias’ conclusion that there was not sufficient proof that Carrier’s letter of October 25 was mailed within the 90 day period was based upon his finding that the mere fact the letter bore a particular date did not raise a presumption that it was mailed on that day. To rebut that finding, the appellant cites
Williams v. Woods,
There is no question of the fact that Carrier’s letter of October 25 was received on October 28. The letter, as is shown by the Postoffice receipts, was sent by Carrier from Syracuse, New York. It was delivered to Glassman in Washington, D. C. and to the Board in Montgomery County, three days after its date. October 25 was a Friday, so that the two intervening days, October 26 and 27, were Saturday and Sunday. The date of receipt of the letter is entirely compatible with the letter having been sent on the date it bears.
Moreover, if the letter had actually been mailed not on Friday, October 25, but on Saturday, October 26, it was still mailed within the 90 days. Assuming that it is the date of mailing which determines timeliness under the statute, the letter was mailed within the stated period unless it was not mailed until Sunday, October 27. It is a matter of common knowledge that business corporations are generally closed on Sundays, whether
On the particular facts in this case, we hold there was sufficient evidence that Carrier’s letter was mailed within the 90 day period to go to the trier of the facts.
We find more difficult the question of whether, under the statute, the contractor must receive notice within the 90 day period, or whether the notice is timely if it is mailed within that period by certified or registered mail. There are no Maryland cases on the subject. Under the wording of the statute, the decision could go either way. In interpreting the terms of the statute, therefore, we look to the legislative intent.
Secretary of State v. Bryson,
There is no mechanic’s lien for work done for or materials supplied to public buildings, but the bond required by the statute is intended to give substantially similar protection. The purpose of the bond, based on the statute, is to- protect subcontractors and materialmen on State or other public projects where they have no lien on the work done.
Hamilton and Spiegel, Inc. v. Board of Educ.,
The statute provides that a claimant shall have a right of action upon the bond “upon giving written notice to the contractor within ninety (90) days from the date” the last of the labor was performed or the last of the material furnished or supplied. It does not state that the contractor must receive the notice within the 90 days. The notice “shall be served” by mailing it by registered or certified mail, postage prepaid. The
We regard it as significant in the question of statutory construction that the manner in which the notice is to be mailed is carefully set forth. Not only must postage be prepaid, but ordinary mail is not sufficient; the notice must be sent by registered or certified mail. The Legislature has eliminated claims of alleged oral notice as fulfilling the 90 day requirement and has provided, in effect, that receipt of the written notice by the contractor is essential to prove the mailing. These provisions do not, of themselves, answer the question of the legislative intent, but they may properly be taken as some evidence of an intent that, with the protection they give the contractor against unsupported claims of mailing, the mailing of the notice tolls the statutory period.
The language of the Maryland statute, with some minor variations not here material, is the same as that of the Federal statute known as the Miller Act, 40 U.S.C. 270b(a). Two Federal District Courts have held that, under the Miller Act, the 90 day requirement is met in respect of a sub-subcontractor when the notice letter is registered and mailed on or before the ninetieth day, although not received by the contractor until after that day.
United States ex rel. Lincoln Elec. Prods. Co., v. Greene Elec. Service of Long Island, Inc.,
In their able brief and oral argument, counsel for the ap
The appellees cite cases such as
United States ex rel. Miller & Bentley Equip. Co. v. Kelley,
For the reasons and on the authorities which we have discussed, we hold that mailing of the notice by the claimant within the 90 day period, in the manner prescribed, is sufficient compliance with the statute.
III
The appellees contend that, even if the findings on the first two issues are in favor of the appellants, recovery against the surety is barred because the work for which compensation is sought is not within the coverage of the bond. In essence, their argument is that the repair work in question is not ordinarily incident to the installation of a centrifugal refrigeration machine; hence the surety could not have undertaken liability to pay for work which was not contemplated under the original contract on which the bond was predicated but which later became necessary by reason of an unforeseen flooding of the machine. We do not agree.
The bond incorporates by reference another bond given at the same time by Glassman to the Board, conditioned on “full and faithful performance of the contract.” The contract calls
The condition of Home Indemnity’s bond is such that “if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect * * *” Claimant is defined as one under contract with the principal or subcontractor “for labor, material, or both, used or reasonably required for use in the performance of the contract * * q'be labor and materials supplied by Carrier were “reasonably required” for full performance of the principal contract, for without them the machine to be installed under the contract would not be in working order. The bond was required to be given by the statute for “the prosecution of the work provided for in the contract.” That work, in this case, was a machine installed in an operative condition, and the repairs were necessary to produce that condition.
The conclusion reached on this issue finds support in a federal court decision construing the analogous Miller Act. In
United States ex rel. Rushlight Co. v. Davidson, 71
F. Supp. 401 (D. Idaho 1947), a factual situation substantially analogous to that of the instant case was presented. A subcontractor on a government construction project sought recovery from the prime contractor and the surety which had guaranteed prompt payment for all labor and materials used in the prosecution of the work under the principal contract. Part of the work for which the subcontractor sought compensation involved repair of equipment which it had installed but which, as in the case before us, became damaged through no fault of the subcontractor. Recovery was permitted against the prime contractor and its surety. See also the following Miller Act cases in which a sub-subcontractor was held covered by the bond for the cost of additional work not covered by the original contract and not occasioned by any fault of the sub-subcontractor:
Johnson &
Judgment reversed; case remanded for a new trial in accordance with the above opinion; costs to be paid by appellees.