Lead Opinion
In August 1990, gеneral contractor defendant Paramount Homes, Inc. (“Paramount”) completed the house at issue in this case. Paramount sold the home to the original owner, who subsequently sold the house to plaintiff in 1993. On 29 August 1996, plaintiff filed suit against Paramount for defective construction of the house. Plaintiff alleged use of defective materials and improper installation of windows, doors, and exterior insulation and finish systems (“EIFS”) cladding, also known as synthetic stucco. Paramount, in
The parties acknowledge that thе applicable statute of repose in the present case is the real property improvement statute which states:
No action to recover damages based upon or arising out of the defective or unsafe condition of an improvement to real property shall be brought more than six years from the later of the specific last act or omission of the defendant giving rise to the cause of action or substantial completion of the improvement.
N.C. Gen. Stat. § l-50(5)(a) (1996) (emphasis added). While the statute does not clarify the meaning of “last act or omission” any further, “substantial completion” means
that degree of completion of a project, improvement or specified area or portion thereof (in accordance with the contract, as modified by аny change orders agreed to by the parties) upon attainment of which the owner can use the same for the purpose for which it was intended. The date of substantial completion may be established by written agreement.
N.C. Gen. Stat. § l-50(5)(c) (1996). N.C. Gen. Stat. § 1-50(5) applies to defective improvements to real property by a materialman, meaning
Paramount contends the court erred in granting CBC summary judgment because its “last act or omission” giving rise to the relevant claims was the repairs completed by CBC in 1994; therefore, the claim is valid since it was filed in 1997, well within the six year statute of repose. Paramount supports its position by citing New Bern Assoc. v. The Celotex Corp.,
In New Bern, plaintiff New Bern Associates brought suit against the Celotex Cоrporation (“Celotex”) alleging breach of warranties in connection with roofing materials manufactured by Celotex and installed on plaintiffs building. Construction of the building, including the installation of Celotex’s roofing materials, had been substantially completed on or prior to 18 March 1975. On 28 April 1986, Celotex asserted third-party claims for indemnity and contribution against T.A. Loving Company (“Loving”), the general contractor responsible for constructing the building and installing the roofing materials. In regards to when the statute of repose began to run, the Court held that the 1963 version of the statute applicable in New Bern is the same as the 1981 version, stating: “We think it means nothing different from the language of the 1981 version in which the statute runs ‘from the later of the specific last act or omission of the defendant giving rise to the cause of action or substantial completion of the improvement.’ ” Id. at 70-71,
The evidence in New Bern indicated that the completion date was 18 March 1975; however, one of Loving’s employees was involved in continuous efforts to repair the property from the 18 March 1975 completion date until after 28 April 1980. This Court found that the dispute over whether the individual was actually Loving’s agent after 28 April 1980 was a genuine issue of material fact as to whether Loving’s “last act or omission alleged to give rise to plaintiff’s injury occurred within six years of the date Celotex filed its third-party complaint,” and remanded the case in order for this determination to be made. Id. at 71,
While the Court in New Bern referred to the repairs in question as continuous efforts after the completion date, it gave no indication whether these repairs were pursuant to the original improvement cоntract, a warranty, or new and separate contracts. In the present case, Paramount alleges in its third-party complaint that CBC, pursuant to contract, supplied Paramount with windows, doors, and associated materials for use in construction of the house in 1990. Paramount further alleges that, pursuant to the plaintiff’s dissatisfaction with the materials:
CBC returned to the House [sic] in approximately the spring or summer of 1994 to inspect, repair, and rеplace the windows about which the plaintiff had complained. Upon information and belief, CBC performed this repair and replacement work pursuant to a warranty and did not charge the plaintiff for replacement parts provided.
While alleging in its third-party complaint that the repairs were completed pursuant to a warranty given in 1990, Paramount also attempts, in its brief, to classify the 1994 repаirs as duties under the original 1990 improvement contract. The allegations of the third-party complaint must be treated as true, as the court is ruling on a motion to dismiss for failure to state a claim upon which relief can be granted. Hickman v. McKoin,
Paramount has not contended that the 1994 repair should be classified as a new and separate improvement, thus starting the running of a second statute of repose. Therefore, this issue is not addressed. Paramount, however, does contend that thе statute of repose did not begin running or was “reset” in 1994 because CBC “must have believed that it had a duty to do those [1994] repairs, and any such
Assuming arguendo that a continuing duty of repair existed pursuant to a warranty, no evidence indicates that CBC had a continuing duty to repair under the improvement contract with Paramount. A warranty is unique in that it anticipates future performance; therefоre, this Court has held that a statute of limitations is tolled during the time the seller endeavors to make repairs to enable the product to comply with a warranty. Haywood Street Redevelopment Corp. v. Peterson Co.,
Haywood is distinguishable from the present case. Paramount, while alleging breach of implied and express warranties, does not rely on the statute of limitations found in N.C. Gen. Stat. § 1-52(1), which applies to breach of warranty. However, the holding in Haywood does indicate that once the improvement to which the warranty applied was completed, the applicable statute of limitations began running. A subsequent repair, pursuant to a warranty, tolled the running of the statute of limitations, but it did not “reset” the running of the statute of limitations. Likewise, Paramount presents no precedent for the proposition that the statute of repose, once it begins running upon completion of the improvement, can be “reset” or “tolled” during a repair. The holding of New Bern never determined affirmatively that
In another similar case, Cascade Gardens v. McKellar & Assoc.,
While equitable doctrines may toll statutes of limitation, they do not toll substantive rights created by statutes of repose. Stallings v. Gunter,
Statutes of limitation are generally seen as running from the time of injury, or disсovery of the injury in cases where that is difficult to detect. They serve to limit the time within which an action may*241 be commenced after the cause of action has accrued. Statutes of repose, on the other hand, create time limitations which are not measured from the date of injury. These time limitations often run from defendant’s last act giving rise to the claim or from substantial completion of some service rendered by defendant.
Trustees of Rowan Tech. v. Hammond Assoc.,
According to N.C. Gen. Stat. § 1-50(5), the statute of repose begins running at the later of the last act or omission or date of substantial completion. Other courts have held that since all liability has its genesis in the contractual rеlationship of the parties, an owner’s claim arising out of defective construction accrues on completion of performance “no matter how a claim is characterized in the complaint — negligence, malpractice, breach of contract.” SC. Dist. of Newburgh v. Stubbins & Assocs.,
Our holding coincides with the public policy encouraging repairs and subsequent remedial measures, codified in Rule 407 of the North Carolina Rule of Evidence. Rule 407 provides, in part: “When, after an event, measures are taken which, if taken previously, would have made the event less likely to occur, evidence of subsequent measures is not admissible to prove negligence or culpable conduct in connection with the event.” N.C.R. Evid. 407. The commentary to this rule makes its purpose clear:
The . . . more impressive, ground for exclusion rests on a social policy of encouraging people to take, or at least not discouraging*242 them from taking, steps in furtherance of added safety. The courts have applied this principle to exclude evidence of subsequent repairs . . . and the language of the present rule is broad enough to encompass [such application].
Id. (Commentary). The rationale behind this policy is that a party might avoid repairing work it had earlier performed, or a product it had earlier manufacturеd and sold, if it believed that such repairs might later be construed as an admission that the original work was improper or defective. See 2 Weinstein’s Federal Evidence § 407.03 [1] (1999). To allow subsequent repairs to restart the statute of repose would defeat the policy underpinning both Rule 407 and N.C. Gen. Stat. § 1-50(5).
Based on the foregoing, we hold that the last act or omission by CBC in completing the improvement at issue — in this case supplying materials for original construction of plaintiffs house — occurred on or prior to August 1990, the date of substantial completion. At that point, performance was completed by CBC and in accordance with N.C. Gen. Stat. § 1-50(5), the statute of repose began to run. The repairs in 1994 did not reset the running of the statute of repose. Therefore, the claims of Paramount against CBC are time-barred under N.C. Gen. Stat. § 1-50(5), as they were not filed until after August 1996, more thаn six years after the last act and date of substantial completion. The trial court did not err when it granted CBC’s motion to dismiss.
Affirmed.
Dissenting Opinion
dissenting.
I would hold that the trial court erred in dismissing Paramount’s complaint; therefore I respectfully dissent from the majority opinion.
When deciding a motion to dismiss, the trial court must determine “whether, as a matter of law, the allegations of the complaint, treated as true, are sufficient to state a clаim upon which relief may be granted under some legal theory . . . .” Harris v. NCNB,
The applicable six-year statute of repose begins to run at the later of (1) “the specific last act or omission of the defendant giving rise to the cause of action” or (2) “substantial completion” of the improvement. N.C.G.S. § l-50(a)(5) (Supp. 1998). The “last act” giving rise to the cause of action is determined by “the nature of the services [the defendant] agreed to perform.” Hargett v. Holland,
In this case, Paramount alleges CBC “made numerous express and implied warranties to Paramount, concerning the windows and associated materials used in construction of the [Monson house].” Accordingly, the nature of the services CBC agreed to perform allegedly included future duties during the warranty period. See Haywood Street Redevelopment Corp. v. Peterson Co.,
In any event, Paramount’s complaint further alleges “the CBC windows installed in the [Monson house] continued to leak and allow moisture intrusion behind the EIFS cladding on the [Monson house] even after CBC’s repair and replacement.” It therefore follows that the statute of repose began to “run anew” from the date of CBC’s
In addition, I believe New Bern Assoc. v. The Celotex Corp.,
Finally, I disagree with the majority’s conclusion that treating a repair as the “last act” would defeat our public policy encouraging repairs. To the contrary, treating a repair as the “last act” would, in fact, encourage repairs as an alternative to litigation. In other words, refusing to treat a repair as the “last act” would encourage the homeowner to bring suit immediately upon noticing a defect (i. e., before the statute of repose has run), rather than working with the contractor (or subcontractor) for a nonlitigious solution.
